Project Plan Summary

Project Plan Summary

.claude Framework: 78% → 100% Autonomous Operation

Created: 2025-11-13 Duration: 8 weeks Total Effort: 320 hours Team Size: 2 engineers + 1 DevOps (part-time)


Quick Overview

This plan transforms the .claude automation framework from human-in-the-loop orchestration (78% complete) to fully autonomous operation (100% complete) where agents communicate without human intervention.

4 Phases

  1. Phase 1: Foundation (Weeks 1-2) - P0 CRITICAL

    • Agent Discovery Service
    • Message Bus (RabbitMQ)
    • Task Queue Manager
    • Milestone: First autonomous workflow works
  2. Phase 2: Resilience (Weeks 3-4) - P0 CRITICAL

    • Circuit Breaker Service
    • Retry Policy Engine
    • Distributed State Manager
    • Milestone: System handles failures gracefully
  3. Phase 3: Observability (Weeks 5-6) - P1 HIGH

    • Metrics Collection (Prometheus)
    • Distributed Tracing (Jaeger)
    • Structured Logging (Loki)
    • Grafana Dashboards
    • Milestone: Full observability operational
  4. Phase 4: Polish (Weeks 7-8) - P1 MEDIUM

    • CLI Integration
    • API Documentation
    • Deployment Automation
    • Load Testing
    • Milestone: Production-ready system

Key Deliverables

Week 2 Milestone

  • Agents can discover each other
  • Agents can send/receive tasks via message bus
  • Tasks enqueued with dependencies
  • First autonomous multi-agent workflow: orchestrator → agent A → agent B → result

Week 4 Milestone

  • Circuit breakers prevent cascading failures
  • Tasks automatically retry (3 attempts with exponential backoff)
  • State syncs across nodes via S3
  • System recovers from failures within 60 seconds

Week 6 Milestone

  • Prometheus scraping metrics from all services
  • Jaeger showing end-to-end traces
  • Loki aggregating structured logs
  • Grafana dashboards operational

Week 8 Milestone

  • System handles 100+ concurrent tasks
  • All documentation published
  • CI/CD pipeline operational
  • Production deployment successful

Success Metrics (Final)

MetricCurrentTargetStatus
Autonomy0%95%⏸️ TODO
LatencyN/A<5s⏸️ TODO
Throughput1 task/min100 tasks/min⏸️ TODO
ReliabilityN/A99.9% uptime⏸️ TODO
Recovery TimeN/A<60s⏸️ TODO
Test Coverage0%80%+⏸️ TODO

Resource Requirements

Team:

  • 2x Full-Stack Engineers (Python, async/await, distributed systems)
  • 1x DevOps Engineer (part-time, weeks 1-2 and 7-8)

Infrastructure:

  • RabbitMQ cluster (3 nodes, HA)
  • Redis cluster (3 nodes, HA)
  • PostgreSQL 15+ (existing)
  • S3 bucket (state backups)
  • Prometheus + Grafana + Jaeger stack
  • Staging environment

Budget:

  • Infrastructure: $1,000 (8 weeks)
  • Monitoring tools: $400 (8 weeks)
  • Total: ~$1,400

Task Breakdown

Total Tasks: 135+

  • Phase 1: 40 tasks (80 hours)
  • Phase 2: 35 tasks (80 hours)
  • Phase 3: 30 tasks (80 hours)
  • Phase 4: 30 tasks (80 hours)

Task Format

All tasks follow this structure:

  • Task X.Y.Z: Description (N hours)
    • Sub-task 1
    • Sub-task 2
    • Sub-task 3
    • Acceptance: Clear criteria

Critical Path

Week 1-2: Infrastructure Setup → Agent Discovery → Message Bus → Task Queue

Week 3-4: Circuit Breaker → Retry Engine → Distributed State

Week 5-6: Metrics → Tracing → Logging → Dashboards

Week 7-8: CLI → Docs → Deployment → Load Testing → Production

Blockers:

  • Phase 1 blocks everything (foundation)
  • Phase 2 blocks Phase 4 (deployment needs resilience)
  • Phase 3 can run in parallel with Phase 4

Risk Mitigation

Top 3 Risks

  1. RabbitMQ performance bottleneck (Medium probability, High impact)

    • Mitigation: Load test early (Week 2), replace with Kafka if needed
  2. Production deployment failure (Medium probability, Critical impact)

    • Mitigation: Phased rollout (10%/50%/100%), robust rollback plan
  3. Team not trained on new system (High probability, High impact)

    • Mitigation: Comprehensive docs (Week 7), hands-on training

Rollback Plan

If deployment fails:

  1. Route 100% traffic to old system (<5 min)
  2. Investigate root cause (1-2 hours)
  3. Fix and re-deploy

Weekly Progress Tracking

Create weekly report:

WeekPhaseKey TasksCompletion %Blockers
1FoundationInfrastructure, Agent Discovery0%-
2FoundationMessage Bus, Task Queue0%-
3ResilienceCircuit Breaker, Retry Engine0%-
4ResilienceDistributed State, Testing0%-
5ObservabilityMetrics, Tracing0%-
6ObservabilityLogging, Dashboards0%-
7PolishCLI, Docs, Deployment0%-
8PolishLoad Testing, Production0%-

Next Steps

Immediate Actions (This Week)

  1. Review and Approve Plan (2 hours)

    • Review ORCHESTRATOR-project-plan.md
    • Get team approval
    • Clarify any questions
  2. Set Up Infrastructure (Day 1-2)

    • Deploy RabbitMQ cluster
    • Deploy Redis cluster
    • Set up Docker Compose for local dev
    • Create GitHub repo structure
  3. Kick-off Meeting (1 hour)

    • Review plan with team
    • Assign Phase 1 tasks
    • Set up weekly sync meeting
    • Create Slack channel for updates
  4. Begin Phase 1 (Day 3+)

    • Engineer 1: Start Agent Discovery Service
    • Engineer 2: Start Message Bus Implementation
    • DevOps: Support infrastructure setup

Files to Reference

  1. ORCHESTRATOR-project-plan.md - Complete detailed plan (this file's companion)
  2. AUTONOMOUS-AGENT-SYSTEM-DESIGN.md - Architecture design document
  3. .claude/README.md - Current framework documentation

Contact

Questions about this plan?

  • See detailed plan: ORCHESTRATOR-project-plan.md
  • See architecture: AUTONOMOUS-AGENT-SYSTEM-DESIGN.md
  • Contact: Project lead

Status: ✅ Ready to Execute Next Review: After Phase 1 completion (Week 2)


This is a summary. See ORCHESTRATOR-project-plan.md for complete task breakdown with checkboxes.