V2 PROJECT PLAN CONSOLIDATION Execution Checklist

V2 PROJECT PLAN CONSOLIDATION - Execution Checklist

Date: December 17, 2025 Launch Target: December 24, 2025 (7 days) Estimated Duration: 3.5 - 5.0 hours Status: ⏸️ READY FOR EXECUTION


Pre-Flight Checks

Environment Verification

  • Current directory: /Users/halcasteel/PROJECTS/coditect-rollout-master/submodules/core/coditect-core
  • Git status clean (no uncommitted changes)
  • All 6 files exist and accessible:
    • docs/05-project-planning/PHASE-4-TASKLIST-COMPONENT-ACTIVATION.md
    • docs/05-project-planning/COMPONENT-ACTIVATION-tasklist.md
    • docs/05-project-planning/PHASE-4-PLAN-COMPONENT-ACTIVATION.md
    • docs/05-project-planning/COMPONENT-ACTIVATION-project-plan.md
    • docs/05-project-planning/04-MASTER-tasklist.md
    • docs/05-project-planning/tasklist-with-checkboxes.md

Safety Preparations

  • Database backup created:

    cp context-storage/context.db context-storage/context.db.backup-2025-12-17
    • Verify backup file exists: ls -lh context-storage/context.db.backup-2025-12-17
  • Git branch created:

    git checkout -b consolidation/v2-project-plan-2025-12-17
    • Verify on correct branch: git branch --show-current
  • Database accessible:

    sqlite3 context-storage/context.db "SELECT COUNT(*) FROM work_items;"
    • Returns: 1361

PHASE 1: Safe Duplicate Removal ⏱️ 30-45 min

Start Time: __________ | End Time: __________

1.1 Verify File Identity

  • Invoke codebase-analyzer to verify MD5 hashes:
    • Compare PHASE-4-TASKLIST-COMPONENT-ACTIVATION.md vs COMPONENT-ACTIVATION-tasklist.md
    • Compare PHASE-4-PLAN-COMPONENT-ACTIVATION.md vs COMPONENT-ACTIVATION-project-plan.md
    • Result: Files are byte-for-byte identical ✅

1.2 Find All References

  • Invoke codebase-locator:
    • Search for PHASE-4-TASKLIST-COMPONENT-ACTIVATION
    • Search for PHASE-4-PLAN-COMPONENT-ACTIVATION
    • Check: CLAUDE.md, README, indexes, git history
    • Result: Complete reference list cataloged ✅

1.3 Remove Duplicate Files

  • Remove PHASE-4-TASKLIST:

    git rm docs/05-project-planning/PHASE-4-TASKLIST-COMPONENT-ACTIVATION.md
    • Verify: git status shows file deleted
  • Remove PHASE-4-PLAN:

    git rm docs/05-project-planning/PHASE-4-PLAN-COMPONENT-ACTIVATION.md
    • Verify: git status shows file deleted

1.4 Commit Removal

  • Git commit:
    git commit -m "chore: Remove duplicate Phase-4 files (PHASE-4-TASKLIST and PHASE-4-PLAN)

    - PHASE-4-TASKLIST-COMPONENT-ACTIVATION.md → COMPONENT-ACTIVATION-tasklist.md (kept)
    - PHASE-4-PLAN-COMPONENT-ACTIVATION.md → COMPONENT-ACTIVATION-project-plan.md (kept)
    - Both pairs were byte-for-byte identical
    - Newer naming convention without phase prefix preferred

    🤖 Generated with Claude Code
    Co-Authored-By: Claude Opus 4.5 <noreply@anthropic.com>"
    • Verify: git log -1 shows commit

Phase 1 Status: ⏸️ PENDING | ✅ COMPLETE


PHASE 2: Smart Merge Execution ⏱️ 60-90 min

Start Time: __________ | End Time: __________

2.1 Analyze Content Differences

  • Invoke codebase-analyzer for deep diff:
    • Extract all unique content from 04-MASTER-tasklist.md
    • Identify Phase 0.7 section (lines ~XXX-YYY)
    • Document task count differences (790 vs 730)
    • Document completion differences (575 vs 515)
    • Result: Structured diff report ready ✅

2.2 Extract Phase 0.7 Content

  • Copy Phase 0.7 section from 04-MASTER-tasklist.md:
    • Section title: ## Phase 0.7: Production Documentation Standardization
    • All subsections and tasks
    • Completion status metadata
    • Result: Phase 0.7 content saved to temporary buffer ✅

2.3 Merge into tasklist-with-checkboxes.md

  • Open tasklist-with-checkboxes.md for editing
  • Insert Phase 0.7 after Phase 0.6 (Memory Management)
  • Verify document structure intact:
    • Headers properly nested
    • Checkboxes preserved
    • Markdown syntax correct
    • Result: Phase 0.7 inserted successfully ✅

2.4 Reconcile Metadata

  • Update task counts in header:

    • Total Completed: 515 → [NEW_COUNT]
    • Total Tasks: 730 → [NEW_COUNT]
    • Manually verify counts match reality
  • Update version:

    • Find: **Version:** 1.2.0
    • Replace: **Version:** 1.4.0
  • Update last updated date:

    • Find: **Last Updated:** 2025-12-09
    • Replace: **Last Updated:** 2025-12-17

2.5 Validate Merged File

  • Manual review of tasklist-with-checkboxes.md:
    • Phase 0.7 content present and complete
    • All checkboxes intact
    • No duplicate sections
    • Metadata updated correctly
    • File saves without errors
    • Result: Merged file validated ✅

2.6 Commit Merged File

  • Git add merged file:

    git add docs/05-project-planning/tasklist-with-checkboxes.md
  • Git commit:

    git commit -m "feat: Merge Phase 0.7 content from 04-MASTER-TASKLIST into TASKLIST-WITH-CHECKBOXES (v1.4.0)

    - Added Phase 0.7: Production Documentation Standardization section
    - Reconciled task counts (575→[NEW] completed, 790→[NEW] total)
    - Updated version: 1.2.0 → 1.4.0
    - Updated date: 2025-12-09 → 2025-12-17
    - Preserved all existing content and completion status

    🤖 Generated with Claude Code
    Co-Authored-By: Claude Opus 4.5 <noreply@anthropic.com>"
    • Verify: git log -1 shows commit

2.7 Archive Original File

  • Archive 04-MASTER-tasklist.md:

    git mv docs/05-project-planning/04-MASTER-tasklist.md \
    docs/99-archive/04-MASTER-TASKLIST-2025-12-04.md
    • Verify: File moved to archive with date suffix
  • Git commit archive:

    git commit -m "chore: Archive 04-MASTER-tasklist.md after merge (dated 2025-12-04)

    Archived as 04-MASTER-TASKLIST-2025-12-04.md
    Content preserved for historical reference

    🤖 Generated with Claude Code
    Co-Authored-By: Claude Opus 4.5 <noreply@anthropic.com>"

Phase 2 Status: ⏸️ PENDING | ✅ COMPLETE


PHASE 3: Reference Update Cascade ⏱️ 45-60 min

Start Time: __________ | End Time: __________

3.1 Find All References

  • Invoke codebase-locator to find references to:
    • PHASE-4-TASKLIST-COMPONENT-ACTIVATION
    • PHASE-4-PLAN-COMPONENT-ACTIVATION
    • 04-MASTER-TASKLIST (outside archive)
    • Result: Complete reference inventory ✅

3.2 Update References by Location

CLAUDE.md Files:

  • docs/CLAUDE.md
    • References updated: _____ / _____
  • docs/05-project-planning/CLAUDE.md
    • References updated: _____ / _____
  • Other CLAUDE.md files:
    • _______________________________
    • References updated: _____ / _____

README Files:

  • README.md (root)
    • References updated: _____ / _____
  • docs/05-project-planning/README.md
    • References updated: _____ / _____

project-plan.md:

  • docs/05-project-planning/project-plan.md
    • References updated: _____ / _____

Documentation Indexes:

  • docs/05-project-planning/INDEX.md (if exists)
    • References updated: _____ / _____

Other Files:

  • _______________________________
    • References updated: _____ / _____
  • Run broken link checker (if available)
  • Manual spot-check:
    • Open 3 updated files
    • Click/verify updated links work
    • Result: Zero broken links ✅

3.4 Commit Reference Updates

  • Git add all updated files:

    git add .
  • Git commit:

    git commit -m "docs: Update all references to consolidated project planning files

    Updated references:
    - PHASE-4-TASKLIST-COMPONENT-ACTIVATION.md → COMPONENT-ACTIVATION-tasklist.md
    - PHASE-4-PLAN-COMPONENT-ACTIVATION.md → COMPONENT-ACTIVATION-project-plan.md
    - 04-MASTER-tasklist.md → tasklist-with-checkboxes.md

    Files updated:
    - CLAUDE.md files
    - README files
    - project-plan.md
    - Documentation indexes

    🤖 Generated with Claude Code
    Co-Authored-By: Claude Opus 4.5 <noreply@anthropic.com>"
    • Verify: git log -1 shows commit

Phase 3 Status: ⏸️ PENDING | ✅ COMPLETE


PHASE 4: Database Integrity Validation ⏱️ 30-45 min

Start Time: __________ | End Time: __________

4.1 Verify Work Item Count

  • Query total work items:
    sqlite3 context-storage/context.db "SELECT COUNT(*) as total_items FROM work_items;"
    • Expected: 1361
    • Actual: __________
    • Status: ⏸️ MATCH | ❌ MISMATCH

4.2 Verify Feature F010.2

  • Query Feature F010.2:
    sqlite3 context-storage/context.db \
    "SELECT id, title, task_count, subtask_count FROM work_items WHERE id = 'F010.2';"
    • Expected: F010.2 | Pilot Phase 1 Launch | 7 | 95
    • Actual: ________________________________________
    • Status: ⏸️ MATCH | ❌ MISMATCH

4.3 Verify Epic E010 Linkage

  • Query Epic E010:
    sqlite3 context-storage/context.db \
    "SELECT id, title, parent_id FROM work_items WHERE id = 'E010';"
    • Expected: E010 | Rollout & GTM | NULL
    • Actual: ________________________________________
    • Status: ⏸️ MATCH | ❌ MISMATCH

4.4 Find File Path References

  • Query for file path references:
    sqlite3 context-storage/context.db \
    "SELECT id, title FROM work_items \
    WHERE description LIKE '%PHASE-4-TASKLIST%' \
    OR description LIKE '%PHASE-4-PLAN%' \
    OR description LIKE '%04-MASTER-TASKLIST%';"
    • Results: _____ work items found
    • List work item IDs: _______________________________

4.5 Update Work Item Descriptions

  • For each work item found in 4.4:
    • Update PHASE-4-TASKLIST-COMPONENT-ACTIVATION.mdCOMPONENT-ACTIVATION-tasklist.md
    • Update PHASE-4-PLAN-COMPONENT-ACTIVATION.mdCOMPONENT-ACTIVATION-project-plan.md
    • Update 04-MASTER-tasklist.mdtasklist-with-checkboxes.md
    • Total updated: _____ / _____

4.6 Database Integrity Check

  • Run integrity check:
    sqlite3 context-storage/context.db "PRAGMA integrity_check;"
    • Expected: ok
    • Actual: __________
    • Status: ⏸️ OK | ❌ ERRORS FOUND

Phase 4 Status: ⏸️ PENDING | ✅ COMPLETE


PHASE 5: QA Cross-Check & Final Validation ⏱️ 45-60 min

Start Time: __________ | End Time: __________

5.1 Final Reference Audit

  • Invoke codebase-locator for comprehensive search:
    • Search for PHASE-4-TASKLIST-COMPONENT-ACTIVATION
    • Search for PHASE-4-PLAN-COMPONENT-ACTIVATION
    • Search for 04-MASTER-TASKLIST (outside docs/99-archive/)
    • Expected: ZERO results outside archive
    • Actual: _____ results found
    • Status: ⏸️ ZERO | ❌ REFERENCES REMAIN

5.2 Content Quality Validation

  • Invoke codebase-analyzer to validate tasklist-with-checkboxes.md:
    • Phase 0.7 content present: ⏸️ YES | ❌ NO
    • Task counts accurate: ⏸️ YES | ❌ NO
    • No duplicate sections: ⏸️ YES | ❌ NO
    • Version = 1.4.0: ⏸️ YES | ❌ NO
    • Date = 2025-12-17: ⏸️ YES | ❌ NO
    • Overall content integrity: ⏸️ 100% | ❌ ISSUES

5.3 Conventions Compliance Check

  • Invoke codebase-pattern-finder:
    • File naming conventions followed: ⏸️ YES | ❌ NO
    • Git commit format correct: ⏸️ YES | ❌ NO
    • Archive strategy appropriate: ⏸️ YES | ❌ NO
    • Documentation updated per standards: ⏸️ YES | ❌ NO
    • Overall compliance: ⏸️ FULL | ❌ DEVIATIONS

5.4 Generate Reports

  • Create V2-CONSOLIDATION-SUMMARY-REPORT.md:

    • Files removed: 2
    • Files merged: 2
    • Files archived: 1
    • References updated: ALL
    • Database validated: YES
    • Report created: ⏸️ YES
  • Create V2-CONSOLIDATION-QA-REPORT.md:

    • Content integrity: 100%
    • Conventions compliance: FULL
    • Zero broken links: YES
    • Report created: ⏸️ YES
  • Create V2-CONSOLIDATION-DATABASE-VALIDATION.md:

    • Total work items: 1,361
    • F010.2 intact: YES
    • E010 linked: YES
    • Integrity check: OK
    • Report created: ⏸️ YES

5.5 Final Commit and Push

  • Git add all reports:

    git add docs/05-project-planning/V2-CONSOLIDATION-*.md
  • Git commit:

    git commit -m "chore: V2 PROJECT PLAN CONSOLIDATION complete - reports and final validation

    Consolidation Summary:
    - Removed: 2 duplicate files
    - Merged: 2 tasklist versions
    - Archived: 1 historical file
    - Updated: ALL references
    - Validated: Database integrity (1,361 work items)

    QA Status: PASSED ✅
    Content Integrity: 100% ✅
    Conventions Compliance: FULL ✅
    Broken Links: ZERO ✅

    Ready for CODITECT Pilot Phase 1 Launch (F010.2)
    Target: December 24, 2025 (7 days)

    🤖 Generated with Claude Code
    Co-Authored-By: Claude Opus 4.5 <noreply@anthropic.com>"
    • Verify: git log -1 shows commit
  • Push to remote:

    git push origin consolidation/v2-project-plan-2025-12-17
    • Verify: Push successful

Phase 5 Status: ⏸️ PENDING | ✅ COMPLETE


Post-Execution Validation

Consolidation Success Metrics

  • Files removed: 2 / 2 ✅
  • Files merged: 2 / 2 ✅
  • Files archived: 1 / 1 ✅
  • References updated: ALL ✅
  • Database integrity: VALIDATED ✅
  • QA status: PASSED ✅
  • Broken links: ZERO ✅
  • Content loss: 0% ✅
  • Git commits: 4 conventional commits ✅

Final Repository State

  • Active files: 3 (down from 6)
  • Archive files: 1
  • Total content: ~3,883 lines (down from 7,621)
  • Reduction: 50% fewer files, 49% less active content

Ready for Merge

  • All phases complete: ⏸️ YES | ❌ NO
  • All validations passed: ⏸️ YES | ❌ NO
  • Reports generated: ⏸️ YES | ❌ NO
  • Ready to merge to main: ⏸️ YES | ❌ NO

Merge to Main (Final Step)

Only proceed if all post-execution validations passed

  • Checkout main branch:

    git checkout main
  • Merge consolidation branch:

    git merge consolidation/v2-project-plan-2025-12-17
    • Verify: Merge successful
  • Push to remote:

    git push origin main
  • Delete consolidation branch:

    git branch -d consolidation/v2-project-plan-2025-12-17
    git push origin --delete consolidation/v2-project-plan-2025-12-17
  • Delete database backup (after 7-day retention):

    # WAIT 7 DAYS, then:
    rm context-storage/context.db.backup-2025-12-17

Emergency Rollback Procedures

If critical issue detected at any phase:

Full Rollback

# 1. Checkout main
git checkout main

# 2. Delete consolidation branch
git branch -D consolidation/v2-project-plan-2025-12-17

# 3. Restore database
cp context-storage/context.db.backup-2025-12-17 context-storage/context.db

# 4. Verify clean state
git status

Phase-Specific Rollback

  • Phase 1: git reset HEAD~1 && git checkout HEAD -- .
  • Phase 2: git reset HEAD~2 && git checkout HEAD -- . && git mv docs/99-archive/04-MASTER-TASKLIST-2025-12-04.md docs/05-project-planning/04-MASTER-tasklist.md
  • Phase 3: git reset HEAD~1 && git checkout HEAD -- .
  • Phase 4: cp context.db.backup-2025-12-17 context.db
  • Phase 5: git reset HEAD~1

Execution Started: __________ Execution Completed: __________ Total Duration: __________ Status: ⏸️ PENDING | ✅ SUCCESS | ❌ ROLLED BACK

Executed By: _______________________________ Approved By: _______________________________ Date: _______________________________


Document Version: 1.0 Created: December 17, 2025 For: CODITECT Pilot Phase 1 Launch (F010.2)