CODITECT V2 Master Project Plan

CODITECT V2 Master Project Plan

Project ID: P001 Project Name: CODITECT Platform - Complete Autonomous Development System Version: 2.0.0 Date Created: 2025-12-14 Status: Active Architecture: ADR-006 Work Item Hierarchy


Executive Summary

Vision

Transform software development from idea to production through fully autonomous AI agent orchestration with zero human intervention for routine tasks.

Project Scope

P001: CODITECT Platform encompasses:

  • 10 major epics (E001-E010)
  • 35 product features
  • 17,546 implementation tasks
  • 57 integrated submodules
  • 6-month aggressive timeline (175 days at 100 tasks/day)

Current Status (Sprint 25)

Overall Completion: 0% (V2 baseline - legacy V1 archived) Active Epic: E001 - Core Platform Autonomy (1,093 tasks) Sprint: 25 of 56 (45% timeline elapsed, 0% scope complete - rebaselined) Velocity Target: 1,000-1,400 tasks/sprint (autonomous operation)

Recent Milestones:

  • V2 project structure launched (ADR-006 implementation)
  • Legacy V1 flat task lists archived
  • Sprint 25 planning complete
  • E001 autonomy epic activated

Project Hierarchy

P001: CODITECT Platform
├── E001: Core Platform Autonomy (1,093 tasks) - ACTIVE
│ ├── F001.1: Component Activation System
│ └── F001.2: Orchestrator Enhancement

├── E002: Toon UI Integration (2,341 tasks) - PLANNED
│ ├── F002.1: React Component Library
│ ├── F002.2: Generative UI System
│ └── F002.3: Design System Integration

├── E003: Memory Intelligence (1,876 tasks) - PLANNED
│ ├── F003.1: Context Database Enhancement
│ ├── F003.2: Decision Extraction Pipeline
│ ├── F003.3: Knowledge Graph Integration
│ └── F003.4: Anti-Forgetting Automation

├── E004: Workflow Automation (2,198 tasks) - PLANNED
│ ├── F004.1: Custom Workflow Engine
│ ├── F004.2: Business Process Templates
│ ├── F004.3: State Machine Integration
│ ├── F004.4: Approval & Notification System
│ └── F004.5: Workflow Analytics

├── E005: Quality Assurance (1,542 tasks) - PLANNED
│ ├── F005.1: Automated Testing Framework
│ ├── F005.2: Quality Gates & Hooks
│ ├── F005.3: Performance Testing
│ └── F005.4: Security Testing

├── E006: Deployment Infrastructure (1,234 tasks) - PLANNED
│ ├── F006.1: CI/CD Pipeline Enhancement
│ ├── F006.2: Container Orchestration
│ └── F006.3: Production Monitoring

├── E007: Documentation System (987 tasks) - PLANNED
│ ├── F007.1: Auto-Generated API Docs
│ ├── F007.2: Interactive Tutorials
│ └── F007.3: Knowledge Base Integration

├── E008: Security & Compliance (1,654 tasks) - PLANNED
│ ├── F008.1: Authentication & Authorization
│ ├── F008.2: Secrets Management
│ ├── F008.3: Audit Logging
│ └── F008.4: Compliance Reporting

├── E009: Analytics & Observability (1,432 tasks) - PLANNED
│ ├── F009.1: Metrics Collection (Prometheus)
│ ├── F009.2: Distributed Tracing (Jaeger)
│ └── F009.3: Dashboards (Grafana)

└── E010: Rollout & GTM (3,189 tasks) - PLANNED
├── F010.1: Beta Testing Program
├── F010.2: Pilot Deployment (10 customers)
├── F010.3: Public Launch (GTM)
└── F010.4: Post-Launch Support

Epic Summary Table

Epic IDNameFeaturesTasksSprint RangeStatusCompletion
E001Core Platform Autonomy21,09325-26Active0%
E002Toon UI Integration32,34127-30Planned0%
E003Memory Intelligence41,87631-34Planned0%
E004Workflow Automation52,19835-38Planned0%
E005Quality Assurance41,54239-41Planned0%
E006Deployment Infrastructure31,23442-44Planned0%
E007Documentation System398745-46Planned0%
E008Security & Compliance41,65447-49Planned0%
E009Analytics & Observability31,43250-51Planned0%
E010Rollout & GTM43,18952-56Planned0%
TOTAL10 Epics3517,54625-56-0%

Epic Details (Quick Reference)

E001: Core Platform Autonomy

Goal: Enable agents to discover, communicate, and coordinate without human intervention Sprint Range: 25-26 (4 weeks) Tasks: 1,093 Source Files: ORCHESTRATOR-project-plan.md, COMPONENT-ACTIVATION-tasklist.md Details: epics/E001-AUTONOMY/EPIC-OVERVIEW.md

Key Deliverables:

  • Component activation system (290 components)
  • Message bus (RabbitMQ) for inter-agent communication
  • Task queue manager (Redis + RQ)
  • Agent discovery service
  • Circuit breaker resilience

E002: Toon UI Integration

Goal: Integrate Toon design system with generative UI capabilities Sprint Range: 27-30 (8 weeks) Tasks: 2,341 Details: epics/E002-TOON-INTEGRATION/EPIC-OVERVIEW.md

Key Deliverables:

  • React component library (50+ components)
  • Generative UI engine (AI-driven interfaces)
  • Design tokens integration
  • Accessibility compliance (WCAG 2.1 AA)
  • Storybook documentation

E003: Memory Intelligence

Goal: Eliminate context loss across sessions with intelligent memory Sprint Range: 31-34 (8 weeks) Tasks: 1,876

Key Deliverables:

  • Enhanced context.db schema
  • Decision extraction automation
  • Knowledge graph relationships
  • /cxq query expansion
  • Anti-forgetting validation

E004: Workflow Automation

Goal: Business process automation with visual workflow designer Sprint Range: 35-38 (8 weeks) Tasks: 2,198

Key Deliverables:

  • Custom workflow engine (BPMN-like)
  • 25+ pre-built workflow templates
  • State machine integration
  • Approval routing system
  • Workflow analytics dashboard

E005: Quality Assurance

Goal: Comprehensive automated testing and quality gates Sprint Range: 39-41 (6 weeks) Tasks: 1,542

Key Deliverables:

  • Unit/integration test framework
  • Pre-commit/pre-push hooks
  • Performance testing (load/stress)
  • Security testing (SAST/DAST)
  • 80%+ code coverage

E006: Deployment Infrastructure

Goal: Production-ready CI/CD and container orchestration Sprint Range: 42-44 (6 weeks) Tasks: 1,234

Key Deliverables:

  • GitHub Actions CI/CD pipeline
  • Docker multi-stage builds
  • Kubernetes deployment manifests
  • Prometheus/Grafana monitoring
  • Blue-green deployment automation

E007: Documentation System

Goal: Self-service knowledge base with auto-generated content Sprint Range: 45-46 (4 weeks) Tasks: 987

Key Deliverables:

  • Auto-generated API documentation
  • Interactive tutorials (step-by-step)
  • Searchable knowledge base
  • Video walkthroughs
  • FAQ automation

E008: Security & Compliance

Goal: Enterprise-grade security and audit compliance Sprint Range: 47-49 (6 weeks) Tasks: 1,654

Key Deliverables:

  • OAuth2/OIDC authentication
  • GCP Secret Manager integration
  • Comprehensive audit logging
  • Compliance reports (SOC2, GDPR)
  • Penetration testing results

E009: Analytics & Observability

Goal: Full-stack observability with real-time metrics Sprint Range: 50-51 (4 weeks) Tasks: 1,432

Key Deliverables:

  • Prometheus metrics collection
  • Jaeger distributed tracing
  • Loki log aggregation
  • Grafana dashboards (15+ pre-built)
  • Alerting rules (PagerDuty integration)

E010: Rollout & GTM

Goal: Public launch with beta testing and pilot programs Sprint Range: 52-56 (10 weeks) Tasks: 3,189

Key Deliverables:

  • Beta testing program (50 users)
  • Pilot deployment (10 customers)
  • Public launch event (March 11, 2026)
  • Post-launch support (90 days)
  • Customer success program

Sprint Roadmap

Current Sprint: Sprint 25

Dates: 2025-12-16 to 2025-12-27 (2 weeks) Goal: Launch V2 project structure and initial autonomy Assigned Tasks: E001 partial (547 tasks) Details: sprints/Sprint-25/SPRINT-PLAN.md

Upcoming Sprints

SprintDatesEpicGoalTasks
25Dec 16-27E001V2 Launch + Autonomy Start547
26Dec 30-Jan 10E001Autonomy Complete546
27Jan 13-24E002Toon UI Start585
28Jan 27-Feb 7E002Toon Components585
29Feb 10-21E002Generative UI586
30Feb 24-Mar 7E002Toon Complete585
31Mar 10-21E003Memory Intelligence Start469
...............
56Aug 25-Sep 5E010Public Launch637

Total: 32 sprints (64 weeks) at 1,000-1,400 tasks/sprint


Success Metrics

Project-Level KPIs

MetricBaselineTargetCurrentMeasurement
Autonomy0%95%0%% tasks completed without human
Velocity50/day100/dayTBDTasks completed per day
QualityN/A80%+TBDTest coverage %
UptimeN/A99.9%TBDSystem availability %
User Adoption01,0000Active users (post-launch)

Epic-Level Success Criteria

E001: Core Platform Autonomy

  • ✅ 290 components activated and callable
  • ✅ Agent-to-agent communication working
  • ✅ <5s task dispatch latency
  • ✅ 99.9% uptime with circuit breakers

E002: Toon UI Integration

  • ✅ 50+ React components production-ready
  • ✅ Generative UI demo working
  • ✅ WCAG 2.1 AA compliance validated
  • ✅ Storybook with all components documented

E003-E010: See individual epic overview files for detailed success criteria.


Risk Management

Critical Risks

Risk IDDescriptionImpactProbabilityMitigation
R001Autonomous agent failureHighMediumCircuit breakers, fallback to human
R002Scope creep (17K+ tasks)HighHighADR-006 strict hierarchy enforcement
R003Velocity <50 tasks/dayHighMediumAutomated task execution, parallel sprints
R004Integration failuresMediumMediumComprehensive testing, staged rollout
R005Security vulnerabilitiesHighLowSecurity epic (E008), penetration testing

Risk Mitigation Strategy

  • Weekly sprint reviews (velocity tracking)
  • Automated quality gates (prevent regression)
  • Staged epic rollout (E001 before E002)
  • Continuous integration testing
  • Fallback to V1 process if V2 fails

Dependencies & Constraints

External Dependencies

  • ADR-006 Implementation: V2 structure relies on work item hierarchy
  • Claude 4.5 API: Agent communication requires stable API
  • GCP Infrastructure: Production deployment needs GCP credits
  • Toon Design System: E002 depends on Toon component library

Technical Constraints

  • Token Limits: Files must stay <500 lines (V2 modular structure)
  • SQLite Database: context.db max size ~140MB (cleanup required)
  • Agent Autonomy: Limited to stateless operations (no persistent state)
  • Test Coverage: Must maintain 80%+ before production deployment

Resource Constraints

  • Engineering Team: 2 full-time engineers available
  • Budget: $105K for Year 1 (autonomous system ROI)
  • Timeline: 6-month aggressive schedule (175 days)
  • Infrastructure: Limited to GCP free tier during beta

Governance & Decision Rights

Decision Authority

Decision TypeAuthorityApproval Required
Epic priority changesProduct OwnerStakeholder review
Sprint scope adjustmentsScrum MasterTeam consensus
Architecture changesTech LeadADR approval
Budget changes >$5KProject ManagerExecutive approval
Timeline extensionsProduct OwnerStakeholder approval

Change Control Process

  1. Propose Change: Submit ADR or sprint adjustment request
  2. Impact Analysis: Estimate effort, dependencies, risks
  3. Review: Team discussion in sprint planning
  4. Approval: Authority level per table above
  5. Execute: Update V2 plan, communicate to team
  6. Verify: Retrospective review of change impact

Communication Plan

Stakeholder Updates

AudienceFrequencyFormatContent
Executive TeamMonthlyDashboardProject % complete, budget, risks
Product TeamWeeklySprint reviewVelocity, burndown, blockers
Engineering TeamDailyStandupTask progress, blockers
Customers (Beta)Bi-weeklyEmailFeature releases, known issues

Reporting Artifacts

  • Sprint Burndown: Auto-generated from /cxq (future)
  • Epic Progress: Manual calculation until ADR-006 Phase 4
  • Velocity Chart: Track tasks/day trend
  • Risk Register: Updated weekly in sprint planning

Quality Standards

Code Quality Gates

  • ✅ 80%+ unit test coverage
  • ✅ 0 critical security vulnerabilities
  • ✅ All pre-commit hooks passing
  • ✅ Linting/formatting compliance (black, flake8)
  • ✅ Type hints for all Python functions

Documentation Standards

  • ✅ All epics have EPIC-OVERVIEW.md
  • ✅ All features documented in overview
  • ✅ All tasks have descriptions and time estimates
  • ✅ Sprint plans created before sprint start
  • ✅ Retrospectives completed after sprint

Definition of Done (Task Level)

  • ✅ Code implemented and unit tested
  • ✅ Integration tests passing
  • ✅ Documentation updated
  • ✅ Code review approved
  • ✅ Merged to main branch

Definition of Done (Epic Level)

  • ✅ All features 100% complete
  • ✅ All tasks checked off in tasklist.md
  • ✅ Success criteria validated
  • ✅ Retrospective completed
  • ✅ Stakeholder sign-off

V1 → V2 Migration

Legacy V1 Files (Archived)

  • docs/05-project-planning/project-plan.md → Archived (historical reference)
  • docs/05-project-planning/tasklist.md → Archived
  • docs/05-project-planning/MASTER-TASKLISTS-CONSOLIDATED.md → Archived

V2 Active Files

  • docs/05-project-planning/v2/V2-MASTER-project-plan.md (this file)
  • docs/05-project-planning/v2/epics/E00N-*/EPIC-OVERVIEW.md (10 files)
  • docs/05-project-planning/v2/epics/E00N-*/tasklist.md (10 files)
  • docs/05-project-planning/v2/sprints/Sprint-N/SPRINT-PLAN.md (32 files planned)

Migration Tasks Completed

  • ✅ V2 directory structure created
  • ✅ README.md overview written
  • ✅ V2-MASTER-project-plan.md (this file) created
  • ✅ E001-AUTONOMY epic extracted from ORCHESTRATOR-project-plan.md
  • ⏸️ E002-E010 epic placeholders created
  • ⏸️ Sprint 25 plan finalized
  • ⏸️ V1 files archived with deprecation notice

Future Enhancements (ADR-006 Phases)

Phase 2: Database Integration (Sprint 26)

  • SQLite schema for work items
  • Python API for CRUD operations
  • Migration script: Markdown → SQLite

Phase 3: /cxq Integration (Sprint 27)

  • /cxq epic:E001 --status
  • /cxq sprint:25 --burndown
  • /cxq task:T001.042 --details

Phase 4: Automation (Sprint 28)

  • Automatic completion % rollup
  • Sprint capacity planning
  • Velocity trend analysis
  • Requirements traceability matrix

Phase 5: Visualization (Sprint 29)

  • Gantt chart export (Mermaid/D3.js)
  • Epic roadmap timeline
  • Critical path highlighting
  • Dependency graphs

Appendix

Glossary

  • Epic: Major product initiative (E001-E010)
  • Feature: Capability within an epic (F001.1, F001.2, etc.)
  • Task: Atomic work unit (~1-8 hours) (T001.001, T001.002, etc.)
  • Sprint: 2-week time-boxed iteration
  • Velocity: Tasks completed per day/sprint
  • Burndown: Remaining work over time

Contacts

  • Product Owner: Hal Casteel (hal@coditect.ai)
  • Scrum Master: TBD
  • Tech Lead: AI Agent Orchestrator
  • QA Lead: Quality Specialist Agent

Last Updated: 2025-12-14 Owner: CODITECT Core Team Status: Active - Sprint 25 Launch Next Review: 2025-12-27 (End of Sprint 25)