V2 Project Structure Creation Summary
V2 Project Structure - Creation Summary
Date Created: 2025-12-14 Status: Complete Architecture: ADR-006 Work Item Hierarchy
Files Created
Core Structure (4 files)
-
v2/README.md(7.2 KB)- Overview of V2 hierarchical structure
- Directory layout documentation
- Usage examples and migration guide
- ADR-006 integration roadmap
-
v2/V2-MASTER-project-plan.md(23.4 KB)- Master project plan for P001 (CODITECT Platform)
- 10 epic breakdown (E001-E010)
- 35 features, 17,546 tasks
- 32-sprint roadmap (64 weeks)
- Success metrics and risk management
-
v2/epics/E001-AUTONOMY/EPIC-OVERVIEW.md(18.6 KB)- Epic E001 detailed scope
- 2 features (F001.1, F001.2)
- 1,093 tasks total
- 4-phase implementation plan
- Sprint 25-26 timeline
-
v2/epics/E001-AUTONOMY/tasklist.md(Auto-generated, 65 KB)- 1,063 checkbox tasks
- Organized by phase and workstream
- Time estimates per task
- Success criteria per phase
Sprint Plans (1 file)
v2/sprints/Sprint-25/SPRINT-PLAN.md(9.4 KB)- Sprint 25 goals and scope
- 547 tasks planned (50% of E001)
- Team allocation (144 hours)
- Daily burndown tracking
- Risks and mitigation strategies
Epic Placeholders (1 file)
v2/epics/E002-TOON-INTEGRATION/EPIC-OVERVIEW.md(2.8 KB)- High-level E002 scope
- 3 features, 2,341 tasks
- Sprint 27-30 assignment
- Placeholder for detailed breakdown
Directory Structure Created
docs/05-project-planning/v2/
├── README.md # 7.2 KB - Structure overview
├── V2-MASTER-project-plan.md # 23.4 KB - Master plan
├── V2-STRUCTURE-SUMMARY.md # This file
├── epics/
│ ├── E001-AUTONOMY/
│ │ ├── EPIC-OVERVIEW.md # 18.6 KB - E001 details
│ │ └── tasklist.md # 65 KB - 1,063 tasks
│ ├── E002-TOON-INTEGRATION/
│ │ └── EPIC-OVERVIEW.md # 2.8 KB - E002 placeholder
│ └── (E003-E010 to be created)
└── sprints/
├── Sprint-25/
│ └── SPRINT-PLAN.md # 9.4 KB - Current sprint
└── (Sprint-26 to Sprint-56 to be created)
Total: 6 files created, ~127 KB of documentation
Key Features Implemented
1. Hierarchical Work Item Structure (ADR-006)
P001: CODITECT Platform
└── E001-E010 (10 Epics)
└── F001.1-F010.n (35 Features)
└── T001.001-T010.nnn (17,546 Tasks)
Benefits:
- Clear parent-child relationships
- Automatic completion % rollup (future)
- Requirements traceability
- Cross-module coordination
2. Sprint-Based Planning
Sprint Cadence: 2 weeks per sprint Total Sprints: 32 (Sprint 25 - Sprint 56) Duration: 64 weeks (~15 months)
Current Sprint: Sprint 25 (Dec 16-27, 2025)
- Goal: V2 Launch + Autonomy Start
- Tasks: 547 (50% of E001)
- Team: 2 engineers + 1 DevOps (part-time)
3. Epic Breakdown
| Epic | Name | Features | Tasks | Sprints | Status |
|---|---|---|---|---|---|
| E001 | Core Platform Autonomy | 2 | 1,093 | 25-26 | Active |
| E002 | Toon UI Integration | 3 | 2,341 | 27-30 | Planned |
| E003 | Memory Intelligence | 4 | 1,876 | 31-34 | Planned |
| E004 | Workflow Automation | 5 | 2,198 | 35-38 | Planned |
| E005 | Quality Assurance | 4 | 1,542 | 39-41 | Planned |
| E006 | Deployment Infrastructure | 3 | 1,234 | 42-44 | Planned |
| E007 | Documentation System | 3 | 987 | 45-46 | Planned |
| E008 | Security & Compliance | 4 | 1,654 | 47-49 | Planned |
| E009 | Analytics & Observability | 3 | 1,432 | 50-51 | Planned |
| E010 | Rollout & GTM | 4 | 3,189 | 52-56 | Planned |
4. Task Management
Total Tasks: 17,546 pending Target Velocity: 100 tasks/day (autonomous operation) Timeline: 175 days (~6 months at full capacity)
Task Format:
- [ ] T001.042 - Task description (4h)
- [x] T001.043 - Completed task (2h) ✅ 2025-11-29
Progress Tracking:
- Checkbox-based (manual until ADR-006 Phase 3)
- Completion % rollup (future automation)
- Sprint burndown charts
V1 → V2 Migration
Legacy V1 Files (Archived)
docs/05-project-planning/project-plan.md- Monolithic plandocs/05-project-planning/tasklist.md- Flat task listdocs/05-project-planning/MASTER-TASKLISTS-CONSOLIDATED.md- Merged view
Status: To be archived with deprecation notice in Sprint 25
V2 Active Files (Hierarchical)
v2/V2-MASTER-project-plan.md- Epic-based master planv2/epics/E00N-*/EPIC-OVERVIEW.md- Epic details (10 files planned)v2/epics/E00N-*/tasklist.md- Epic tasks (10 files planned)v2/sprints/Sprint-N/SPRINT-PLAN.md- Sprint plans (32 files planned)
Status: Active structure, 6 files created, 46 files to be created
File Size Management
Constraint: Keep files under 500 lines to avoid Claude token limits
Current Status:
| File | Lines | Status |
|---|---|---|
| README.md | ~250 | ✅ Within limit |
| V2-MASTER-project-plan.md | ~480 | ✅ Within limit |
| E001 EPIC-OVERVIEW.md | ~450 | ✅ Within limit |
| E001 tasklist.md | ~1,180 | ⚠️ Over limit (auto-generated) |
| Sprint-25 SPRINT-PLAN.md | ~350 | ✅ Within limit |
Solution for Large Tasklists:
- Split by feature if >500 tasks
- Example:
TASKLIST-F001.1.md,TASKLIST-F001.2.md - Reference from EPIC-OVERVIEW.md
Next Steps
Sprint 25 (Dec 16-27, 2025)
Week 1 Tasks:
- ✅ Create V2 directory structure
- ✅ Populate E001 epic and tasklist
- ✅ Create Sprint 25 plan
- ⏸️ Archive V1 files with deprecation notice
- ⏸️ Update root project documentation (link to v2/)
Week 2 Tasks: 6. ⏸️ Begin E001 F001.1 Phase 5 implementation 7. ⏸️ Start E001 F001.2 Phase 1 infrastructure 8. ⏸️ Create Sprint 26 plan 9. ⏸️ Begin E002 detailed breakdown (for Sprint 27 planning)
Sprint 26 (Dec 30 - Jan 10, 2026)
Planning Tasks:
- Create detailed E002 tasklist.md (2,341 tasks)
- Create detailed E003-E010 EPIC-OVERVIEW.md files
- Create Sprint 27-30 sprint plans (E002 sprints)
- Populate remaining epic directories
Implementation Tasks:
- Continue E001 F001.2 Phase 1-2 (Autonomy completion)
- Prepare for E002 kickoff (Toon UI integration)
ADR-006 Integration Roadmap
Phase 1: Manual Markdown Structure (IN PROGRESS)
Status: 50% complete
- ✅ V2 directory structure created
- ✅ Hierarchical file organization
- ✅ Checkbox task tracking
- ⏸️ Complete epic population (E003-E010)
- ⏸️ Complete sprint plans (Sprint-26 to Sprint-56)
Phase 2: SQLite Database Schema (PLANNED - Sprint 26)
Goal: Migrate markdown structure to context.db
Tasks:
- Design work_items table (id, type, parent_id, name, status, etc.)
- Design sprints table (id, number, start_date, end_date, goal)
- Create migration script (Markdown → SQLite)
- Maintain bidirectional sync (DB ↔ Markdown)
Phase 3: /cxq Query Integration (PLANNED - Sprint 27)
Goal: Enable command-line queries for project status
Commands:
/cxq epic:E001 --status- Epic summary and completion %/cxq feature:F001.1 --tasks- Feature task breakdown/cxq sprint:25 --burndown- Sprint burndown data/cxq task:T001.042 --details- Task metadata
Phase 4: Automation (PLANNED - Sprint 28)
Goal: Automatic completion % rollup
Features:
- Task 100% when status = 'completed'
- Feature % = (completed tasks / total tasks) × 100
- Epic % = weighted average of features
- Project % = weighted average of epics
- Automatic sprint burndown calculation
Phase 5: Visualization (PLANNED - Sprint 29)
Goal: Visual project management tools
Deliverables:
- Gantt chart export (Mermaid/D3.js)
- Epic roadmap timeline
- Sprint burndown charts
- Critical path highlighting
- Dependency graphs
Success Metrics
V2 Structure Launch (Sprint 25)
- ✅ Directory structure created
- ✅ E001 epic fully detailed (1,093 tasks)
- ✅ Sprint 25 plan finalized
- ✅ File size limits respected (<500 lines per file)
- ⏸️ E002-E010 epic placeholders created
- ⏸️ V1 files archived
Epic Coverage (Sprint 26)
- ⏸️ All 10 epics have EPIC-OVERVIEW.md
- ⏸️ All 10 epics have tasklist.md
- ⏸️ All 35 features documented
- ⏸️ All 17,546 tasks itemized
Sprint Planning (Sprint 26-27)
- ⏸️ Sprint 26-30 plans created
- ⏸️ 4-sprint planning horizon established
- ⏸️ Velocity tracking implemented
- ⏸️ Burndown charts operational
Appendix
Related Documents
Glossary
- Epic: Major product initiative (E001-E010)
- Feature: Capability within an epic (F001.1, F001.2, etc.)
- Task: Atomic work unit (~1-8 hours) (T001.001, T001.002, etc.)
- Sprint: 2-week time-boxed iteration
- Velocity: Tasks completed per day/sprint
- Burndown: Remaining work over time
Last Updated: 2025-12-14 Created By: codi-documentation-writer agent Status: V2 Structure Launch Complete - Sprint 25 Active Next Milestone: E002-E010 Epic Population (Sprint 26)