Work Item Hierarchy Implementation Multi Agent Orchestration Plan
Work Item Hierarchy Implementation - Multi-Agent Orchestration Plan
Document: WORK-ITEM-HIERARCHY-ORCHESTRATION-PLAN
Version: 1.0.0
Status: ACTIVE
Created: 2025-12-13
Owner: CODITECT Orchestrator Agent
Related ADR: ADR-006-WORK-ITEM-HIERARCHY
Related Standard: CODITECT-STANDARD-WORK-ITEMS
Execution Model: Multi-Agent Coordination with Parallel Work Streams
Estimated Duration: 8-12 weeks (320-480 engineering hours)
Token Budget: 180K total (90% of 200K budget, 10% reserved for coordination)
🎯 Executive Summary
Implementation Goal
Implement comprehensive Work Item Hierarchy system (Project → Sub-Project → Epic → Feature → Task → Subtask) with Sprint management, automatic completion rollup, and full /cxq integration.
Success Criteria
- ✅ Complete database schema with 4 core tables + 7 views
- ✅ 6 new slash commands operational (
/project,/epic,/feature,/task,/sprint,/workitems) - ✅ Extended
/cxqwith 10+ new query modes - ✅ Import/export functionality for markdown round-tripping
- ✅ Automatic percentage rollup working correctly
- ✅ 95%+ test coverage for all new functionality
- ✅ Migration path for existing project-plan.md files
- ✅ Complete documentation and HOW-TO guides
Orchestration Approach
Multi-agent coordination with bounded parallelism:
- Phase 1-2: Sequential (foundation must be solid)
- Phase 3: 3-way parallel (commands development)
- Phase 4: 2-way parallel (import/export + templates)
- Phase 5: Sequential (integration and migration)
Agent Team (9 Specialists)
- database-architect - Schema design and migration
- backend-engineer - Python module development
- command-developer (×3) - Slash command implementation
- integration-engineer -
/cxqextension - template-designer - Template and standards creation
- test-engineer - Test suite development
- orchestrator - Coordination and synthesis
📊 Gap Analysis
Current State Assessment
What Exists:
- ✅
scripts/context-db.py- SQLite foundation (1,000+ lines) - ✅
/cxqcommand - Query interface operational - ✅
PROJECT-PLAN-TEMPLATE.md- Basic template - ✅
TASKLIST-WITH-CHECKBOXES-TEMPLATE.md- Checkbox tracking - ✅ ADR-006 - Complete specification approved
- ✅ CODITECT-STANDARD-WORK-ITEMS - Naming convention standard
What's Missing:
- ❌ Work item hierarchy tables (projects, sub_projects, work_items, sprints)
- ❌ Completion rollup views (7 SQL views)
- ❌ Python CRUD module for work items
- ❌ 6 new slash commands
- ❌
/cxqextensions (--epic-progress, --sprint-status, etc.) - ❌ Markdown import/export parser
- ❌ Updated templates (V2 versions)
- ❌ HOW-TO guides (5 guides needed)
- ❌ Migration scripts for existing data
- ❌ Test coverage for new features
Impacted Files Analysis
Database Layer (2 files):
scripts/context-db.py- Add 4 tables + 7 views + indexes (~500 new lines)scripts/work_items.py- NEW: CRUD operations module (~800 lines)
Command Layer (7 files):
commands/project.md- NEW: Project/sub-project managementcommands/epic.md- NEW: Epic CRUD operationscommands/feature.md- NEW: Feature CRUD operationscommands/task.md- NEW: Task/subtask managementcommands/sprint.md- NEW: Sprint planningcommands/workitems.md- NEW: Import/export operationscommands/cxq.md- MODIFY: Add 10+ new query modes (~300 new lines)
Template Layer (7 files):
CODITECT-CORE-STANDARDS/TEMPLATES/PROJECT-PLAN-TEMPLATE-V2.md- NEWCODITECT-CORE-STANDARDS/TEMPLATES/TASKLIST-TEMPLATE-V2.md- NEWCODITECT-CORE-STANDARDS/PROJECT-REPORTING-STANDARD.md- NEWCODITECT-CORE-STANDARDS/HOW-TO-CREATE-NEW-EPIC.md- NEWCODITECT-CORE-STANDARDS/HOW-TO-CREATE-NEW-FEATURE.md- NEWCODITECT-CORE-STANDARDS/HOW-TO-CREATE-NEW-TASK.md- NEWCODITECT-CORE-STANDARDS/HOW-TO-PLAN-SPRINT.md- NEW
Migration Layer (2 files):
scripts/migrate-project-plans.py- NEW: Import existing project-plan.md filesscripts/work-items-demo.py- NEW: Demo data generator for testing
Test Layer (3 files):
scripts/test-suite.py- MODIFY: Add work_items test categorytests/test_work_items.py- NEW: Unit tests for CRUD moduletests/test_work_item_commands.py- NEW: Integration tests for commands
Documentation Layer (5 files):
docs/02-user-guides/WORK-ITEM-HIERARCHY-GUIDE.md- NEW: User guidedocs/03-architecture/adrs/ADR-005-work-item-hierarchy.md- EXISTS: Already createdCODITECT-CORE-STANDARDS/CODITECT-STANDARD-WORK-ITEMS.md- EXISTS: Already createddocs/08-agent-reference/WORK-ITEMS-COMMAND-REFERENCE.md- NEW: Command referenceCHANGELOG.md- UPDATE: Document v2.0.0 release
Configuration (2 files):
config/component-counts.json- UPDATE: Add 6 new commands.coditect/component-activation-status.json- UPDATE: Add 6 new commands
Total Impact:
- 2 modified files (context-db.py, cxq.md, test-suite.py, component configs)
- 23 new files created
- ~4,200 lines of code to implement
- ~8,000 lines of documentation to write
🏗️ Implementation Phases
Phase 1: Database Schema & Core Infrastructure (P0)
Duration: 2 weeks (80 hours) Token Budget: 30K tokens Agent: database-architect Dependencies: None (foundation layer)
Tasks (Detailed)
-
Schema Design (16 hours)
- T0001: Create
projectstable with constraints - T0002: Create
sub_projectstable with FK to projects - T0003: Create
sprintstable with date validation - T0004: Create
work_itemsunified table - T0005: Add all indexes (8 indexes across tables)
- T0006: Add foreign key constraints with ON DELETE actions
- T0007: Write schema migration script
- T0008: Unit test schema creation
- T0001: Create
-
View Creation (24 hours)
- T0009: Create
work_item_children_statsview - T0010: Create
work_item_progressview with rollup logic - T0011: Create
epic_progresssummary view - T0012: Create
sprint_burndownview - T0013: Create
project_progressoverview view - T0014: Create
sub_project_progressview - T0015: Create
work_item_dependenciesview (optional) - T0016: Test view performance with 1000+ work items
- T0009: Create
-
CRUD Module (32 hours)
- T0017: Create
scripts/work_items.pymodule - T0018: Implement Project CRUD operations
- T0019: Implement Sub-Project CRUD operations
- T0020: Implement Work Item CRUD (generic for E/F/T/ST)
- T0021: Implement Sprint CRUD operations
- T0022: Implement completion rollup calculation
- T0023: Implement recursive descendant queries
- T0024: Add transaction support and error handling
- T0025: Write comprehensive unit tests (95%+ coverage)
- T0017: Create
-
Migration Integration (8 hours)
- T0026: Integrate schema into
context-db.pyget_db() - T0027: Add database version tracking
- T0028: Create migration rollback functionality
- T0029: Test on existing context.db databases
- T0026: Integrate schema into
Deliverables:
- ✅ 4 tables created with all constraints
- ✅ 7 views operational
- ✅
scripts/work_items.pymodule with 100% test coverage - ✅ Schema integrated into context-db.py
- ✅ Migration path tested
Acceptance Criteria:
- Can create Project → Epic → Feature → Task hierarchy
- Completion % calculates correctly (by count and by points)
- All queries run in <100ms for 1000+ work items
- No SQL injection vulnerabilities
- All foreign keys enforce referential integrity
Phase 2: Command Implementation (P0)
Duration: 3 weeks (120 hours) Token Budget: 45K tokens Agents: command-developer (×3) in parallel Dependencies: Phase 1 complete
Parallel Work Streams
Stream A: Project & Sprint Commands (40 hours, command-developer-1)
- T0030: Create
/projectcommand spec - T0031: Implement
/project create - T0032: Implement
/project list - T0033: Implement
/project status - T0034: Implement
/project archive - T0035: Create
/sprintcommand spec - T0036: Implement
/sprint create - T0037: Implement
/sprint list - T0038: Implement
/sprint active - T0039: Implement
/sprint burndown - T0040: Implement
/sprint plan(interactive) - T0041: Implement
/sprint close - T0042: Write integration tests (both commands)
- T0043: Update component activation status
Stream B: Epic & Feature Commands (40 hours, command-developer-2)
- T0044: Create
/epiccommand spec - T0045: Implement
/epic create - T0046: Implement
/epic list - T0047: Implement
/epic progress - T0048: Implement
/epic details --tree - T0049: Create
/featurecommand spec - T0050: Implement
/feature create - T0051: Implement
/feature list - T0052: Implement
/feature progress - T0053: Implement
/feature assign(to epic) - T0054: Write integration tests (both commands)
- T0055: Update component activation status
Stream C: Task & Work Items Commands (40 hours, command-developer-3)
- T0056: Create
/taskcommand spec - T0057: Implement
/task create - T0058: Implement
/task listwith filters - T0059: Implement
/task start(status update) - T0060: Implement
/task complete - T0061: Implement
/task block//task unblock - T0062: Implement
/task assign(sprint/assignee) - T0063: Create
/workitemscommand spec - T0064: Implement
/workitems import - T0065: Implement
/workitems export(JSON/CSV/Markdown) - T0066: Write integration tests (both commands)
- T0067: Update component activation status
Deliverables:
- ✅ 6 new commands fully operational
- ✅ All commands activated in component registry
- ✅ Integration tests with 90%+ coverage
- ✅ Command reference documentation
Acceptance Criteria:
- All commands accessible via
/command-name - Error handling for invalid inputs
- Helpful error messages with suggestions
- JSON output available for automation
- Commands respect ID validation rules
Phase 3: Query Interface Extension (P0)
Duration: 2 weeks (80 hours) Token Budget: 35K tokens Agent: integration-engineer Dependencies: Phase 1-2 complete
Tasks
-
Core Query Extensions (40 hours)
- T0068: Modify
commands/cxq.mdto add new modes - T0069: Implement
--epic-progress <ID> - T0070: Implement
--feature-progress <ID> - T0071: Implement
--sprint-status <ID> - T0072: Implement
--project-status <ID> - T0073: Implement
--velocity --sprints N - T0074: Implement
--blocked(all blocked items) - T0075: Implement
--overdue(past due items) - T0076: Implement
--unassigned(tasks without assignee) - T0077: Implement
--my-tasks(current user filter) - T0078: Add
--work-item <ID>(detailed work item view)
- T0068: Modify
-
Output Formatting (24 hours)
- T0079: Design progress bar visualization
- T0080: Design hierarchical tree output
- T0081: Design sprint burndown chart (ASCII)
- T0082: Implement table formatting for lists
- T0083: Implement JSON output for all queries
- T0084: Add color coding (green=completed, yellow=in_progress, red=blocked)
-
Integration Testing (16 hours)
- T0085: Test all query modes with demo data
- T0086: Performance test with 1000+ work items
- T0087: Test edge cases (empty projects, orphaned items)
- T0088: Update
cxq.mddocumentation with examples
Deliverables:
- ✅
/cxqextended with 10+ new query modes - ✅ Beautiful ASCII visualizations for progress
- ✅ JSON output for automation
- ✅ Updated documentation with examples
Acceptance Criteria:
- All queries return results in <1 second
- Output is human-readable and informative
- JSON output is valid and complete
- Help text updated with new modes
Phase 4: Templates & Standards (P1)
Duration: 2 weeks (80 hours) Token Budget: 30K tokens Agents: template-designer + documentation-writer (parallel) Dependencies: Phase 1-3 complete
Parallel Work Streams
Stream A: Templates (40 hours, template-designer)
- T0089: Create
PROJECT-PLAN-TEMPLATE-V2.mdwith hierarchy - T0090: Create
TASKLIST-TEMPLATE-V2.mdwith rollup - T0091: Create
PROJECT-REPORTING-STANDARD.md - T0092: Create
SPRINT-RETROSPECTIVE-TEMPLATE.md - T0093: Test templates with real data
- T0094: Add templates to CODITECT-CORE-STANDARDS/
Stream B: HOW-TO Guides (40 hours, documentation-writer)
- T0095: Create
HOW-TO-CREATE-NEW-EPIC.md - T0096: Create
HOW-TO-CREATE-NEW-FEATURE.md - T0097: Create
HOW-TO-CREATE-NEW-TASK.md - T0098: Create
HOW-TO-PLAN-SPRINT.md - T0099: Create
HOW-TO-MIGRATE-EXISTING-PLAN.md - T0100: Create
WORK-ITEM-HIERARCHY-GUIDE.md(comprehensive) - T0101: Update
COMPONENT-REFERENCE.mdwith new commands
Deliverables:
- ✅ 4 new templates ready for use
- ✅ 5 HOW-TO guides complete
- ✅ 1 comprehensive user guide
Acceptance Criteria:
- Templates follow CODITECT standard format
- HOW-TO guides are actionable (copy-paste commands)
- User guide covers all major workflows
- Documentation reviewed for clarity
Phase 5: Import/Export & Migration (P1)
Duration: 2 weeks (80 hours) Token Budget: 30K tokens Agent: backend-engineer Dependencies: Phase 1-4 complete
Tasks
-
Markdown Parser (32 hours)
- T0102: Design parser for project-plan.md format
- T0103: Implement Phase detection
- T0104: Implement Epic extraction (### Epic: E001 - Title)
- T0105: Implement Feature extraction (#### Feature: F001 - Title)
- T0106: Implement Task extraction (- [ ] T001: Title)
- T0107: Handle checkbox states ([ ], [x], [>], [!])
- T0108: Extract story points from task lines
- T0109: Parse sprint assignments (#S23)
- T0110: Write comprehensive parser tests
-
Export Functionality (24 hours)
- T0111: Implement JSON export (full hierarchy)
- T0112: Implement CSV export (flat task list)
- T0113: Implement Markdown export (round-trip format)
- T0114: Test round-trip (import → export → import)
- T0115: Validate exported data integrity
-
Migration Script (24 hours)
- T0116: Create
scripts/migrate-project-plans.py - T0117: Auto-discover project-plan.md files
- T0118: Batch import with progress reporting
- T0119: Handle import errors gracefully
- T0120: Generate migration report (summary statistics)
- T0121: Create rollback functionality
- T0122: Test on real CODITECT projects
- T0116: Create
Deliverables:
- ✅ Markdown import parser operational
- ✅ 3 export formats (JSON, CSV, Markdown)
- ✅ Migration script tested on existing data
- ✅ Migration report generated
Acceptance Criteria:
- Parser handles 95%+ of existing project-plan.md files
- Round-trip preserves all data
- Migration script runs without errors
- Rollback functionality tested
Phase 6: Testing & Documentation (P0)
Duration: 1 week (40 hours) Token Budget: 20K tokens Agent: test-engineer Dependencies: Phase 1-5 complete
Tasks
-
Test Suite Expansion (24 hours)
- T0123: Add
work_itemscategory to test-suite.py - T0124: Write unit tests for CRUD module (target 95%+)
- T0125: Write integration tests for commands
- T0126: Write end-to-end tests (create → update → query → delete)
- T0127: Write performance tests (1000+ items)
- T0128: Test error handling and edge cases
- T0129: Run full test suite and fix failures
- T0123: Add
-
Documentation Finalization (16 hours)
- T0130: Create
WORK-ITEMS-COMMAND-REFERENCE.md - T0131: Update
CHANGELOG.mdfor v2.0.0 - T0132: Update
README.mdwith work items feature - T0133: Create demo video/GIF showing workflows
- T0134: Review all documentation for consistency
- T0135: Create troubleshooting section
- T0130: Create
Deliverables:
- ✅ Test coverage 95%+ for all new code
- ✅ All tests passing
- ✅ Complete command reference
- ✅ Updated CHANGELOG and README
Acceptance Criteria:
- Test suite runs in <5 minutes
- No failing tests
- Documentation is clear and complete
- Demo materials ready for users
🔀 Dependency Graph
Phase 1: Database Schema (Foundation)
↓
Phase 2: Commands (3 parallel streams)
├─→ Stream A: /project, /sprint
├─→ Stream B: /epic, /feature
└─→ Stream C: /task, /workitems
↓
Phase 3: /cxq Integration
↓
Phase 4: Templates & Docs (2 parallel streams)
├─→ Stream A: Templates
└─→ Stream B: HOW-TO Guides
↓
Phase 5: Import/Export & Migration
↓
Phase 6: Testing & Documentation
Critical Path: Phase 1 → Phase 2 → Phase 3 → Phase 5 → Phase 6 (9 weeks) Parallel Optimization: Phase 2 saves 6 weeks, Phase 4 saves 2 weeks Total Duration: 10 weeks (vs. 18 weeks sequential)
👥 Agent Assignment Matrix
| Phase | Agent | Role | Tools | Estimated Tokens |
|---|---|---|---|---|
| 1 | database-architect | Schema design | Read, Write, Bash | 30K |
| 2A | command-developer-1 | /project, /sprint | Write, Read | 15K |
| 2B | command-developer-2 | /epic, /feature | Write, Read | 15K |
| 2C | command-developer-3 | /task, /workitems | Write, Read | 15K |
| 3 | integration-engineer | /cxq extension | Edit, Read, Bash | 35K |
| 4A | template-designer | Templates | Write | 15K |
| 4B | documentation-writer | HOW-TO guides | Write | 15K |
| 5 | backend-engineer | Import/export | Write, Read, Bash | 30K |
| 6 | test-engineer | Testing | Write, Bash | 20K |
| - | orchestrator | Coordination | All | 10K |
Total: 200K tokens (100% of budget) Agents: 9 specialists + 1 orchestrator
📈 Progress Tracking
Phase Completion Checklist
Phase 1: Database Schema ✅
- All 4 tables created
- All 7 views operational
- CRUD module complete (800 lines)
- Unit tests passing (95%+ coverage)
- Migration integrated
Phase 2: Commands ✅
- 6 commands implemented
- All commands activated
- Integration tests passing
- Documentation complete
Phase 3: Query Extension ✅
- 10+ new query modes
- Visualizations working
- JSON output validated
- Performance tests passing
Phase 4: Templates & Standards ✅
- 4 templates created
- 5 HOW-TO guides written
- User guide complete
- Documentation reviewed
Phase 5: Import/Export ✅
- Markdown parser working
- 3 export formats operational
- Migration script tested
- Round-trip verified
Phase 6: Testing & Docs ✅
- Test coverage 95%+
- All tests passing
- Command reference complete
- CHANGELOG updated
Success Metrics
| Metric | Target | Actual |
|---|---|---|
| Database tables | 4 | - |
| SQL views | 7 | - |
| New commands | 6 | - |
| Lines of code | 4,200+ | - |
| Lines of docs | 8,000+ | - |
| Test coverage | 95%+ | - |
| Query performance | <1s for 1000+ items | - |
| Migration success rate | 95%+ | - |
🚨 Risk Mitigation
Technical Risks
Risk 1: Schema Migration Breaks Existing Database
- Probability: Medium
- Impact: High
- Mitigation:
- Create backup before migration
- Test on copy of production database
- Implement rollback functionality
- Version database schema
Risk 2: Performance Degradation with Large Datasets
- Probability: Medium
- Impact: Medium
- Mitigation:
- Add comprehensive indexes
- Use pre-computed views
- Benchmark with 10K+ work items
- Optimize recursive queries
Risk 3: Import Parser Fails on Edge Cases
- Probability: High
- Impact: Low
- Mitigation:
- Extensive test suite with real data
- Graceful error handling
- Manual import fallback
- Import validation report
Risk 4: Agent Coordination Failures
- Probability: Low
- Impact: High
- Mitigation:
- Clear handoff protocols
- Phase completion validation
- Checkpoints between phases
- Orchestrator oversight
Project Risks
Risk 5: Scope Creep
- Mitigation: Strict adherence to ADR-006 specification, defer nice-to-haves to Phase 7
Risk 6: Token Budget Exceeded
- Mitigation: Monitor token usage per phase, compress outputs, use checkpoints
Risk 7: Timeline Slippage
- Mitigation: Weekly progress reviews, adjust parallel work streams if needed
🎯 Quality Gates
Gate 1: After Phase 1 (Database)
- ✅ All tables created without errors
- ✅ All views return correct results
- ✅ CRUD module has 95%+ test coverage
- ✅ Performance benchmarks met (<100ms queries)
- Decision: Proceed to Phase 2 OR fix issues
Gate 2: After Phase 2 (Commands)
- ✅ All 6 commands functional
- ✅ Integration tests pass
- ✅ Commands activated in registry
- ✅ No critical bugs
- Decision: Proceed to Phase 3 OR fix issues
Gate 3: After Phase 3 (Integration)
- ✅ All
/cxqmodes working - ✅ Output formatting correct
- ✅ JSON output validated
- ✅ Performance acceptable
- Decision: Proceed to Phase 4 OR fix issues
Gate 4: After Phase 5 (Import/Export)
- ✅ Round-trip import/export working
- ✅ Migration script tested
- ✅ 95%+ import success rate
- ✅ Data integrity validated
- Decision: Proceed to Phase 6 OR fix issues
Gate 5: Final Release Gate
- ✅ All tests passing (95%+ coverage)
- ✅ Documentation complete
- ✅ CHANGELOG updated
- ✅ Demo materials ready
- ✅ Migration path validated
- Decision: RELEASE v2.0.0 OR hold for fixes
📋 Execution Plan (Week-by-Week)
Week 1-2: Phase 1 - Database Foundation
Agent: database-architect
Week 1:
- Days 1-2: Schema design and review
- Days 3-4: Table creation and view implementation
- Day 5: CRUD module scaffolding
Week 2:
- Days 1-3: CRUD operations implementation
- Day 4: Unit test development
- Day 5: Migration integration and testing
Checkpoint: Database schema operational, CRUD module complete
Week 3-5: Phase 2 - Commands (Parallel)
Agents: command-developer-1, command-developer-2, command-developer-3
Week 3:
- All agents: Command spec design and review
- All agents: Start implementation of primary commands
Week 4:
- All agents: Complete command implementations
- All agents: Integration testing
Week 5:
- All agents: Bug fixes and refinement
- All agents: Documentation and activation
- Orchestrator: Synthesis and validation
Checkpoint: All 6 commands operational and tested
Week 6-7: Phase 3 - Query Extension
Agent: integration-engineer
Week 6:
- Days 1-3: Implement core query modes
- Days 4-5: Output formatting and visualization
Week 7:
- Days 1-2: Remaining query modes
- Days 3-4: Integration testing
- Day 5: Documentation update
Checkpoint: /cxq extended with all new modes
Week 8-9: Phase 4 - Templates & Standards (Parallel)
Agents: template-designer, documentation-writer
Week 8:
- template-designer: Create all 4 templates
- documentation-writer: Create 3 HOW-TO guides
Week 9:
- template-designer: Test templates with real data
- documentation-writer: Create remaining 2 HOW-TO guides + user guide
- Orchestrator: Review and synthesis
Checkpoint: Templates and HOW-TO guides complete
Week 10-11: Phase 5 - Import/Export & Migration
Agent: backend-engineer
Week 10:
- Days 1-3: Markdown parser implementation
- Days 4-5: Export functionality (JSON, CSV, Markdown)
Week 11:
- Days 1-3: Migration script development
- Days 4-5: Testing on real data, migration report
Checkpoint: Import/export operational, migration tested
Week 12: Phase 6 - Final Testing & Documentation
Agent: test-engineer
Week 12:
- Days 1-2: Test suite expansion
- Days 3-4: Documentation finalization
- Day 5: Final review and release preparation
Checkpoint: v2.0.0 READY FOR RELEASE
🔧 Handoff Protocols
Phase Completion Handoff
From: Completing Agent To: Orchestrator Format: JSON + Markdown
Required Information:
-
Completion Status:
- All tasks marked complete (checkbox tracking)
- Test results (pass/fail counts)
- Known issues or limitations
-
Deliverables:
- List of created/modified files with paths
- Line counts for new code
- Token usage actual vs. estimated
-
Next Phase Requirements:
- Prerequisites for next phase
- Any blocking issues
- Recommended adjustments
Example Handoff:
{
"phase": "Phase 1: Database Schema",
"agent": "database-architect",
"status": "COMPLETE",
"completion_date": "2025-12-20",
"tasks_completed": 29,
"tasks_total": 29,
"test_results": {
"passed": 47,
"failed": 0,
"coverage": "96.2%"
},
"deliverables": [
{
"file": "scripts/context-db.py",
"type": "modified",
"lines_added": 523,
"description": "Added 4 tables + 7 views"
},
{
"file": "scripts/work_items.py",
"type": "created",
"lines": 847,
"description": "CRUD module for work items"
}
],
"token_usage": {
"estimated": 30000,
"actual": 28547,
"efficiency": "95.2%"
},
"known_issues": [],
"next_phase_ready": true,
"notes": "All performance benchmarks exceeded expectations. Ready for Phase 2."
}
Between-Agent Handoff (Parallel Streams)
Coordination Points:
- Daily standup (async via checkpoint files)
- Shared component registry updates
- Test suite integration
- Documentation cross-references
📊 Final Deliverables Checklist
Code Artifacts
-
scripts/context-db.py- Modified (+500 lines) -
scripts/work_items.py- Created (800 lines) -
scripts/migrate-project-plans.py- Created (400 lines) -
commands/project.md- Created -
commands/epic.md- Created -
commands/feature.md- Created -
commands/task.md- Created -
commands/sprint.md- Created -
commands/workitems.md- Created -
commands/cxq.md- Modified (+300 lines)
Test Artifacts
-
tests/test_work_items.py- Created (500 lines) -
tests/test_work_item_commands.py- Created (400 lines) -
scripts/test-suite.py- Modified (work_items category)
Documentation Artifacts
-
docs/02-user-guides/WORK-ITEM-HIERARCHY-GUIDE.md- Created -
docs/08-agent-reference/WORK-ITEMS-COMMAND-REFERENCE.md- Created -
CODITECT-CORE-STANDARDS/TEMPLATES/PROJECT-PLAN-TEMPLATE-V2.md- Created -
CODITECT-CORE-STANDARDS/TEMPLATES/TASKLIST-TEMPLATE-V2.md- Created -
CODITECT-CORE-STANDARDS/PROJECT-REPORTING-STANDARD.md- Created -
CODITECT-CORE-STANDARDS/HOW-TO-CREATE-NEW-EPIC.md- Created -
CODITECT-CORE-STANDARDS/HOW-TO-CREATE-NEW-FEATURE.md- Created -
CODITECT-CORE-STANDARDS/HOW-TO-CREATE-NEW-TASK.md- Created -
CODITECT-CORE-STANDARDS/HOW-TO-PLAN-SPRINT.md- Created -
CHANGELOG.md- Updated (v2.0.0 entry) -
README.md- Updated (work items feature)
Configuration Artifacts
-
config/component-counts.json- Updated (+6 commands) -
.coditect/component-activation-status.json- Updated (+6 commands)
Demo & Training Artifacts
-
scripts/work-items-demo.py- Created (demo data generator) - Demo video/GIF showing workflows
- Example PROJECT-PLAN-V2.md with hierarchy
🎉 Success Criteria Summary
Functional Requirements
- ✅ Create Project → Sub-Project → Epic → Feature → Task → Subtask hierarchy
- ✅ Completion % rolls up correctly through hierarchy (by count and by points)
- ✅ Sprint burndown calculates correctly
- ✅ Import from existing project-plan.md works
- ✅ Export to JSON/CSV/Markdown works
- ✅ Round-trip import/export preserves data
Performance Requirements
- ✅ Queries complete in <1s for 1000+ work items
- ✅ Recursive rollup efficient for deep hierarchies (10+ levels)
- ✅ Views update automatically on data changes
- ✅ Import processes 100+ work items in <5s
Usability Requirements
- ✅ Commands are intuitive and well-documented
- ✅ Output is human-readable with progress bars
- ✅ JSON output is complete for automation
- ✅ Error messages are helpful with suggestions
Quality Requirements
- ✅ Test coverage 95%+ for all new code
- ✅ All tests passing
- ✅ No critical bugs or security issues
- ✅ Code follows CODITECT standards
📞 Contact & Support
Orchestrator Agent: workflow-orchestrator Project Owner: CODITECT Core Team Related ADR: ADR-006-WORK-ITEM-HIERARCHY Related Standard: CODITECT-STANDARD-WORK-ITEMS
Questions or Issues:
- Review this orchestration plan
- Check phase-specific handoff documents
- Consult related ADR or standard
- Contact orchestrator for coordination
Document Version: 1.0.0 Last Updated: 2025-12-13 Status: ACTIVE - Ready for Execution Total Estimated Effort: 480 engineering hours (12 weeks) Token Budget: 180K tokens (90% of available budget) Expected Completion: March 2026
END OF ORCHESTRATION PLAN