Unified Execution Plan — Gap Closure + Website Build

Classification: Internal — Execution
Date: 2026-02-13
Version: 1.0
Source Plans: Doc 57 (Website Build, 32 prompts) + Doc 58 (Gap Closure, 28 prompts)
Total Effort: ~70 hours across 60 prompts, organized into 12 sprints


Strategy: Why Interleave Gaps and Website?

Building the website first and then closing gaps means publishing known deficiencies. Closing all gaps first delays visibility. The optimal strategy interleaves: close Critical/High gaps that affect the compliance narrative, build the website in parallel, then close Medium/Low gaps with live dashboard updates.

This plan organizes 60 prompts into 12 one-week sprints. Each sprint produces deployable output.


Sprint Plan

Sprint 1: Foundation (Week 1, ~8 hours)

Goal: Project scaffold + security foundation. Nothing is visible yet, but everything after depends on this.

OrderIDSourceTitleDepends OnHours
1P00Doc 57Project scaffolding & monorepo2
2P01Doc 57Configuration data filesP001.5
3G01Doc 58Credential vault integration3
4G02Doc 58§11.70 cryptographic hash bindingG011.5

Sprint 1 Deliverable: Next.js project scaffold with all config files. Vault integration spec + signature hash spec ready. Two Critical gaps closed.

Milestone: grep -c "⚠️" 20-regulatory-compliance-matrix.md decreases by 1.


Sprint 2: Crypto + Core Rendering (Week 2, ~7 hours)

Goal: Complete crypto foundation (unblocks all compliance phases). Get first pages rendering.

OrderIDSourceTitleDepends OnHours
5G03Doc 58Audit trail hash chainG022
6G04Doc 58Agent message signingG011.5
7P03Doc 57Root layout, nav, responsive shellP012
8P04Doc 57MDX content pipeline & rendererP031.5

Sprint 2 Deliverable: All crypto primitives specified (Phase A complete). MDX rendering pipeline working — first markdown docs visible in browser.

Milestone: Phase A (Security Foundation) complete. Hash chain, message signing, vault all specified.


Sprint 3: Landing + FDA Compliance (Week 3, ~8 hours)

Goal: Landing page live. FDA Part 11 gaps closing.

OrderIDSourceTitleDepends OnHours
9P05Doc 57Landing page with embedded simulatorP042
10G05Doc 58§11.100(b) re-authentication flowG011.5
11G06Doc 58§11.10(i) training integration2
12G07Doc 58§11.10(j) written policies1.5
13G08Doc 58FDA compliance verificationG05-G071

Sprint 3 Deliverable: Landing page with embedded state machine simulator. All FDA Part 11 gaps closed. IQ/OQ/PQ test stubs generated.

Milestone: FDA 21 CFR Part 11: 18/18 Ready. Landing page live at localhost:3000.


Sprint 4: Hub Pages + HIPAA (Week 4, ~8 hours)

Goal: Four audience hub pages. HIPAA gaps closing.

OrderIDSourceTitleDepends OnHours
14P06Doc 57Audience hub pages (4)P052
15P07Doc 57Document sub-pages & categoriesP062
16G09Doc 58PHI detection scanner2
17G10Doc 58Break-glass emergency access1
18G11Doc 58Session management & auto logoff0.5
19G12Doc 58HIPAA compliance verificationG09-G110.5

Sprint 4 Deliverable: All 31 markdown documents navigable by audience. All HIPAA gaps closed. PHI scanner designed.

Milestone: HIPAA: 12/12 Ready. All documents browsable at localhost.


Sprint 5: Dashboards + SOC 2 (Week 5, ~8 hours)

Goal: Dashboard embedding infrastructure. SOC 2 gaps closing.

OrderIDSourceTitleDepends OnHours
20P08Doc 57Glossary & reference pagesP071.5
21P09Doc 57Dashboard wrapper & dynamic importsP041.5
22P10Doc 57System/architecture dashboards (8)P091
23G13Doc 58SIEM integration & streaming1.5
24G14Doc 58Incident response WO generationG131
25G15Doc 58Access deprovisioning0.75
26G16Doc 58Risk assessment & CAPA0.75

Sprint 5 Deliverable: 8 engineering dashboards live. Glossary searchable. All SOC 2 gaps closed.

Milestone: SOC 2: 12/12 Ready. Interactive dashboards rendering in browser.


Sprint 6: All Dashboards Live (Week 6, ~6 hours)

Goal: Complete dashboard integration. All 25 JSX components accessible.

OrderIDSourceTitleDepends OnHours
27P11Doc 57Compliance dashboards (4)P091
28P12Doc 57Business/market dashboards (8)P091.5
29P13Doc 57Planning/operations dashboards (5)P091
30G17Doc 58Optimistic locking enforcement1
31G18Doc 58DAG cycle detection1.5

Sprint 6 Deliverable: All 25 dashboards + all 31 documents live on localhost. Optimistic locking and DAG validation designed.

Milestone: Local website MVP complete. All 56 original artifacts accessible. 93% → ~96% audit ready.


Sprint 7: Operational Gaps (Week 7, ~5 hours)

Goal: Close remaining operational resilience gaps.

OrderIDSourceTitleDepends OnHours
32G19Doc 58Partial Master WO completion1.5
33G20Doc 58Vendor WO timeout/escalation1
34G21Doc 58Vendor coordination portalG201
35G22Doc 58Vendor IQ/OQ document uploadG210.75
36G23Doc 58Experience expiration checks0.75

Sprint 7 Deliverable: All operational and vendor gaps closed. Phase E + F complete.

Milestone: All Critical, High, and Medium gaps resolved.


Sprint 8: Auth + NDA Gate (Week 8, ~8 hours)

Goal: Build the GCP authentication and NDA workflow.

OrderIDSourceTitleDepends OnHours
37P14Doc 57Auth architecture — dual modeP001.5
38P15Doc 57Registration flowP141.5
39P16Doc 57NDA signing flowP152
40P17Doc 57Approval workflow & adminP161.5
41P18Doc 57Role-based content filteringP171
42P19Doc 57Session mgmt & securityP180.5

Sprint 8 Deliverable: Complete auth pipeline: register → NDA → approve → access. Admin panel for user management.

Milestone: GCP auth flow functional in local dev mode.


Sprint 9: GCP Deployment (Week 9, ~6 hours)

Goal: Production deployment on Google Cloud.

OrderIDSourceTitleDepends OnHours
43P02Doc 57CI/CD + Terraform IaCP002
44P20Doc 57Cloud Run deploymentP021
45P21Doc 57Cloud SQL + migrationsP201
46P22Doc 57Environment + Secret ManagerP210.5
47P23Doc 57CDN, caching, performanceP221
48P24Doc 57Monitoring & alertingP230.5

Sprint 9 Deliverable: Production site live at docs.coditect.ai with NDA gating, Cloud SQL, CDN, monitoring.

Milestone: GCP production deployment complete. NDA-gated access functional.


Sprint 10: Polish (Week 10, ~5 hours)

Goal: Search, PDF export, analytics, accessibility.

OrderIDSourceTitleDepends OnHours
49P25Doc 57Full-text search (Cmd+K)P081.5
50P26Doc 57PDF export + watermarksP191
51P27Doc 57Analytics integrationP241
52P28Doc 57Accessibility + mobileP061.5

Sprint 10 Deliverable: Polished production site with search, PDF export, analytics, WCAG 2.1 AA accessibility.

Milestone: Site ready for investor/partner distribution.


Sprint 11: Scaling + Living Docs (Week 11, ~5 hours)

Goal: Low-priority gaps + content pipeline.

OrderIDSourceTitleDepends OnHours
53G24Doc 58Batch WO API1.5
54G25Doc 58Schedule constraint solver1.5
55G26Doc 58Resource optimization loop1
56P29Doc 57Git-based content workflowP021

Sprint 11 Deliverable: Scaling designs complete. Content update pipeline in CI/CD.


Sprint 12: Final Sync (Week 12, ~4 hours)

Goal: Sync all artifacts. Update all dashboards. Ship final state.

OrderIDSourceTitleDepends OnHours
57P30Doc 57Programmatic APIP291.5
58P31Doc 57Changelog & version trackingP301
59G27Doc 58Artifact gap status updatesAll G-prompts0.75
60G28Doc 58Dashboard data synchronizationG270.75

Sprint 12 Deliverable: All 61 artifacts updated to final state. All dashboards show 0 gaps. API live. Changelog publishing.

Milestone: PROJECT COMPLETE. 98%+ audit ready. All artifacts consistent. Website live with NDA gating.


Critical Path

Week 1   ██████████ Foundation (P00, P01, G01, G02)
Week 2 ██████████ Crypto + Rendering (G03, G04, P03, P04)
Week 3 ██████████ Landing + FDA (P05, G05-G08)
Week 4 ██████████ Hubs + HIPAA (P06, P07, G09-G12)
Week 5 ██████████ Dashboards + SOC2 (P08-P10, G13-G16)
Week 6 ████████── ALL DASHBOARDS LIVE — LOCAL MVP ✓
Week 7 ██████──── Operational Gaps (G19-G23)
Week 8 ██████████ Auth + NDA (P14-P19)
Week 9 ████████── GCP DEPLOYMENT — PRODUCTION ✓
Week 10 ██████──── Polish (P25-P28)
Week 11 ██████──── Scaling + Living Docs (G24-G26, P29)
Week 12 ████────── FINAL SYNC — PROJECT COMPLETE ✓

Week 6 = Local MVP (all content browsable, 96% audit ready)
Week 9 = Production (NDA-gated, fully deployed)
Week 12 = Complete (98%+ audit ready, all gaps closed, all dashboards synced)


GTM Alignment

Cross-Reference: Full GTM strategy at docs/market/gtm-execution-plan.md

This technical execution plan directly enables the go-to-market milestones. The table below maps product delivery sprints to GTM launch phases, showing where technical capabilities unlock commercial activities.

Technical Sprint → GTM Phase Mapping

GTM PhaseTimelineKey MilestonesProduct Delivery RequiredSprint Dependencies
Phase 1: Design PartnerMonths 1-6M1-2: First design partner signed
M3-4: Initial deployment + feedback
M5-6: Case study + reference customer
Sprint 6: Local MVP (all dashboards live)
Sprint 9: GCP production deployment
Sprint 10: Polished site with analytics
Sprints 1-6 (foundation + dashboards)
Sprints 7-9 (deployment + auth)
Sprint 10 (polish + PDF export)
Phase 2: Limited GAMonths 7-12M7-8: 3-5 paying customers
M9-10: Channel partner onboarded
M11-12: $360K ARR milestone
Sprint 9: NDA-gated production site
Sprint 10: PDF export + watermarks
Sprint 12: API + changelog
Sprint 8 (auth + NDA workflow)
Sprint 9 (Cloud SQL + monitoring)
Sprint 12 (programmatic API)
Phase 3: Full GAMonths 13-18M13-14: Self-serve pipeline active
M15-16: 15-20 customers, $1.5M ARR
M17-18: Series A readiness, $3.2M ARR
Sprint 11: Living docs workflow
Sprint 12: Changelog + version tracking
Post-Sprint: Self-serve onboarding
Sprint 11 (Git-based content pipeline)
Sprint 12 (programmatic API)
Post-delivery: automated provisioning
Phase 4: ScaleMonths 19+M19-24: Partner ecosystem expansion
M24+: International, $9M ARR target
Post-Sprint: Multi-tenant architecture
Post-Sprint: Partner portal + APIs
Post-Sprint: Localization
All sprints complete
New epic: Enterprise scale features

Product Readiness Gates

Each GTM phase has product readiness gates that must pass before commercial activities begin:

GateCriteriaDelivered ByGTM Phase Unlocked
Gate 1: Design Partner Ready• All 56 original artifacts accessible
• Compliance audit readiness ≥96%
• Local demo environment functional
• Interactive dashboards working
Sprint 6 (Week 6)
Local MVP complete
Phase 1: Design Partner
Can sign first design partner
Gate 2: Production Deployment• NDA-gated production site live
• GCP Cloud Run + Cloud SQL deployed
• Monitoring & alerting functional
• PDF export with watermarks working
Sprint 9 (Week 9)
Production deployment complete
Phase 1: Initial Deployment
Can deploy to design partner
Gate 3: Limited GA Launch• Polished site (Lighthouse ≥90/95)
• Full-text search functional
• Analytics tracking active
• NDA approval workflow automated
Sprint 10 (Week 10)
Polish complete
Phase 2: Limited GA
Can onboard 3-5 paying customers
Gate 4: Programmatic Access• Programmatic API live
• Changelog publishing automated
• Living docs pipeline operational
• All gaps closed (98%+ audit ready)
Sprint 12 (Week 12)
Project complete
Phase 2-3 Transition
Can onboard channel partners
Gate 5: Self-Serve Pipeline• Git-based content workflow
• Automated provisioning
• Customer self-onboarding
• Partner API documentation
Post-Sprint
New epic required
Phase 3: Full GA
Can launch self-serve

Revenue Alignment

Technical delivery directly enables revenue milestones:

Revenue MilestoneAmountGTM TargetProduct Capability RequiredDelivery Sprint
First Design Partner$0-50KM1-2 (Months 1-2)Local MVP + dashboards liveSprint 6 (Week 6)
Initial Deployment$96K pilot contractM3-4 (Months 3-4)Production site + NDA gatingSprint 9 (Week 9)
3-5 Paying Customers$360K ARRM11-12 (Months 11-12)Polished site + API accessSprint 10-12 (Weeks 10-12)
15-20 Customers$1.5M ARRM15-16 (Months 15-16)Self-serve pipeline + automationPost-Sprint (Month 13+)
Series A Readiness$3.2M ARR targetM17-18 (Months 17-18)Full platform + partner ecosystemPost-Sprint (Month 16+)
Scale Phase$9M ARR targetM24+ (Months 24+)Enterprise features + internationalNew development cycle

Critical Path Synchronization

The Critical Path (Sprint 1 → Sprint 6 → Sprint 9 → Sprint 12) directly enables GTM phase transitions:

SPRINT DELIVERY                      GTM PHASE TRANSITION
Week 1-5 Foundation + Dashboards → [Prep: design partner outreach begins]
Week 6 ✓ LOCAL MVP COMPLETE → [GATE 1: Can sign design partner]
Week 7-8 Auth + NDA workflow → [Prep: legal review, partner negotiation]
Week 9 ✓ PRODUCTION DEPLOYED → [GATE 2: Can deploy to design partner]
Week 10 ✓ POLISHED SITE → [GATE 3: Can launch Limited GA]
Week 11 Living docs + scaling → [Prep: channel partner onboarding]
Week 12 ✓ PROJECT COMPLETE → [GATE 4: Can onboard paying customers]
Month 13+ Self-serve pipeline → [GATE 5: Can launch Full GA]

Sprint-to-Revenue Dependency Map

SprintTechnical OutputGTM Activity EnabledRevenue Impact
Sprint 6Local MVP — all dashboards + docs accessibleDesign partner demos begin$0-50K design partner contract
Sprint 9Production deployment — NDA-gated site liveDesign partner deployment + feedback loop$96K pilot contract milestone
Sprint 10Polished site — search, PDF export, analyticsLimited GA launch materials ready3-5 customer pipeline activation
Sprint 12API + changelog — programmatic access liveChannel partner onboarding begins$360K ARR milestone unlocked
Post-SprintSelf-serve pipeline — automated provisioningFull GA launch + self-serve signup$1.5M ARR milestone unlocked

Risk Mitigation: GTM Delays

If GTM activities lag technical delivery:

ScenarioMitigation
Design partner signing delayedSprint 6 MVP ready early → use extra time for polish, user testing, or advanced features in Sprint 7-8
Production deployment blockedSprint 9 infrastructure ready → deploy staging environment, run extended QA, prepare training materials
Limited GA customers not readySprint 10-12 complete → focus on content updates, SEO, partner ecosystem prep for Phase 3
Self-serve pipeline not needed yetPost-Sprint work deferred → redirect engineering to enterprise features, international localization, or scaling

Success Metrics Alignment

Technical success criteria (from "Success Criteria" section) directly support GTM metrics:

Technical MetricTargetGTM Metric Enabled
All 56 artifacts accessible100% (Sprint 6)Design partner can evaluate full platform
Compliance audit readiness≥98% (Sprint 12)Customer procurement teams approve purchase
Lighthouse performance score≥90 (Sprint 10)Customer experience drives retention + referrals
NDA sign → access latency<24 hours (Sprint 9)Limited GA conversion rate optimization
Time to first value (investor)<5 min (Sprint 6)Fundraising materials ready for Series A
All dashboards consistent0 conflicts (Sprint 12)Customer trust in platform reliability

Bottom line: Technical execution is paced to GTM demand. Sprint 6 MVP unlocks design partner activities. Sprint 9 production deployment enables pilot contracts. Sprint 12 completion supports $360K ARR milestone. Post-Sprint self-serve pipeline unlocks $1.5M ARR and Series A readiness.


Risk Register

RiskLikelihoodImpactMitigation
Vault integration complexity delays Sprint 1MediumHighUse GCP Secret Manager (simpler) as first pass; migrate to Vault later
NDA legal review delays Sprint 8HighMediumDraft NDA in Sprint 1; send to counsel immediately
Cloud SQL cold start affects UXLowMediumMin 1 Cloud Run instance; connection pooling
Dashboard rendering issues in Next.jsMediumLowAll dashboards already tested as standalone; dynamic import isolates failures
Content updates during build conflictLowLowFreeze content after Sprint 6; resume updates in Sprint 12

Success Criteria

MetricTargetMeasured At
All 56 original artifacts accessible100%Sprint 6
Compliance audit readiness≥98%Sprint 12
Lighthouse performance score≥90Sprint 10
Lighthouse accessibility score≥95Sprint 10
Time to first value (investor)<5 minSprint 6
Time to first value (engineer)<15 minSprint 6
NDA sign → access latency<24 hoursSprint 9
All gaps closed or explicitly deferred100%Sprint 12
All dashboards show consistent data0 conflictsSprint 12