Project Status Brief (Auto-Generated)
Generated: 2026-02-17T03:10:35.087Z Project: coditect-biosciences-qms-platform
Summary
- Overall: 33% (137/410 tasks)
- Tracks: 17 total | 1 active | 0 in-progress | 12 planned | 4 complete
- Sections: 87 total | 23 complete | 0 in-progress | 64 pending
- Velocity: 45.7 tasks/day | high trend | ~6 days remaining | 3 active work days
Tracks
| Track | Name | Status | Progress | Sections | Sprint |
|---|---|---|---|---|---|
| A | Presentation & Publishing | complete | 100% (34/34) | 6C/0P/0W | S1-S3 |
| B | Competitive Intelligence & GTM | complete | 100% (28/28) | 5C/0P/0W | S2-S3 |
| C | Technical Foundation | complete | 100% (42/42) | 5C/0P/0W | S3-S6 |
| D | Compliance & Security | complete | 100% (33/33) | 7C/0P/0W | S3-S6 |
| E | Operations & Deployment | planned | 0% (0/20) | 0C/0P/5W | S5-S6 |
| F | Documentation & Training | active | 0% (0/24) | 0C/0P/6W | S3+ |
| G | Revenue & Billing Operations | planned | 0% (0/24) | 0C/0P/5W | S5-S7 |
| H | Customer Operations | planned | 0% (0/24) | 0C/0P/5W | S5-S8 |
| I | Sales & Business Development | planned | 0% (0/20) | 0C/0P/5W | S4-S7 |
| J | Product Management & Analytics | planned | 0% (0/22) | 0C/0P/5W | S6-S8 |
| K | Platform Reliability & Maintenance | planned | 0% (0/24) | 0C/0P/6W | S6-S9 |
| L | Data & Business Intelligence | planned | 0% (0/22) | 0C/0P/5W | S7-S9 |
| M | Security Operations | planned | 0% (0/18) | 0C/0P/5W | S6-S9 |
| N | Legal & Regulatory Operations | planned | 0% (0/26) | 0C/0P/5W | S5-S8 |
| O | Partner Ecosystem | planned | 0% (0/19) | 0C/0P/4W | S8-S10 |
| P | Accessibility & Internationalization | planned | 0% (0/18) | 0C/0P/5W | S4-S10 |
| Q | AI & Automation Governance | planned | 0% (0/12) | 0C/0P/3W | S8-S10 |
At-Risk Tracks (0% Progress)
- E Operations & Deployment: 20 tasks, status=planned, sprint=S5-S6
- F Documentation & Training: 24 tasks, status=active, sprint=S3+
- G Revenue & Billing Operations: 24 tasks, status=planned, sprint=S5-S7
- H Customer Operations: 24 tasks, status=planned, sprint=S5-S8
- I Sales & Business Development: 20 tasks, status=planned, sprint=S4-S7
- J Product Management & Analytics: 22 tasks, status=planned, sprint=S6-S8
- K Platform Reliability & Maintenance: 24 tasks, status=planned, sprint=S6-S9
- L Data & Business Intelligence: 22 tasks, status=planned, sprint=S7-S9
- M Security Operations: 18 tasks, status=planned, sprint=S6-S9
- N Legal & Regulatory Operations: 26 tasks, status=planned, sprint=S5-S8
- O Partner Ecosystem: 19 tasks, status=planned, sprint=S8-S10
- P Accessibility & Internationalization: 18 tasks, status=planned, sprint=S4-S10
- Q AI & Automation Governance: 12 tasks, status=planned, sprint=S8-S10
Cross-Track Dependencies
- Viewer foundation: A.1 → A.2, A.3, P.1 (Markdown rendering before nav/search/a11y)
- Cloud platform: A.4 → A.5 (Deploy before auth)
- Competitive data: B.1 → B.2, I.2 (Market analysis before GTM and sales collateral)
- Backend scaffold: C.1 → C.2-C.5, G.1, H.1-H.2, J.1, N.2 (API framework before all backend features)
- State machine: C.2 → J.3 (WO engine before WO analytics)
- Integrations: C.5 → O.2, O.3 (Integration layer before marketplace/SDK)
- Crypto foundation: D.1 → C.4, M.4 (Gap closure before e-sig and secrets mgmt)
- HIPAA controls: D.3 → N.2, N.3 (HIPAA before GDPR engine and BAA management)
- CI/CD pipeline: E.1 → M.1, K.3 (Pipeline before security scanning and patching)
- Infrastructure: E.2 → K.1, L.1, P.4 (GCP before SLA monitoring, data warehouse, regions)
- Monitoring: E.3 → K.1-K.2, M.3 (Observability before SLA/incident management)
- Subscriptions: G.1 → G.2-G.5, H.3 (Subscription model before pricing/billing/health)
- Payments: G.3 → H.4, I.4 (Payment processing before billing portal/contracts)
- CRM: I.1 → I.3-I.5, H.3 (CRM before assessment tool, proposals, partner mgmt)
- Telemetry: J.1 → J.2-J.4 (Event tracking before analytics/experimentation)
- Partner program: I.5, O.1 → O.2-O.4 (Foundation before marketplace/SDK/analytics)
- i18n framework: P.2 → P.3, P.4 (i18n before localization and regional data)
- AI governance: Q.1 → Q.2-Q.3 (Model governance before AI testing/risk mgmt)
- Agent framework: C.3 → Q.1 (Agent orchestration before AI governance)
- Data warehouse: L.1 → Q.2 (Warehouse before AI model monitoring data)
- Validation: D.7 → Q.2 (Validation framework before AI validation)
- Tenant lifecycle: D.6 → H.1, G.1 (Tenant provisioning before onboarding/billing)
- DR automation: E.5 → K.5 (DR validation before chaos engineering)
- Training records: F.6 → D.2 (Training records for Part 11 compliance)
- Multi-site: K.6 → O.1 (Site management before partner coordination)
- All tracks: * → F.* (Documentation continuous across all work)
Sprint Load
- S1 (Wk 1-2): Presentation + Doc Verification — 7 sections
- S2 (Wk 3-4): Cloud Publishing + Competitive Analysis — 5 sections
- S3 (Wk 5-6): Auth + GTM + Foundation Start — 8 sections
- S4 (Wk 7-8): Backend Core + Sales Enablement — 7 sections
- S5 (Wk 9-10): Agents + Integrations + Billing — 9 sections
- S6 (Wk 11-12): Ops + Payments + Data Warehouse — 16 sections
- S7 (Wk 13-14): Analytics + Monitoring + Reliability — 26 sections
- S8 (Wk 15-16): Docs + BI + Marketplace + AI Governance — 24 sections
- S9 (Wk 17-18): Patching + Resilience + Vulnerability — 10 sections
- S10 (Wk 19-20): Final Polish — 24 sections
Agent Workload
frontend-react-typescript-expert: 1 trackscompetitive-analyst: 1 trackssenior-architect: 1 trackssecurity-specialist: 1 tracksdevops-engineer: 1 trackscodi-documentation-writer: 1 trackspayment-systems-specialist: 1 trackscustomer-onboarding: 1 trackssales-workflow: 1 tracksproduct-analytics-specialist: 1 trackssre-on-call-assistant: 1 tracksdata-pipeline-specialist: 1 tracksincident-response-specialist: 1 tracksregulatory-change-monitor: 1 trackspartner-onboarding: 1 tracksaccessibility-testing-specialist: 1 tracksresponsible-ai: 1 tracks
Recent Session Logs
- 2026-02-16 — BIO-QMS
- 2026-02-15 — BIO-QMS
- 2026-02-14 — BIO-QMS
Completed Work (Active Tracks)
A: Presentation & Publishing (34 done)
- A.1.1: Install unified/remark/rehype markdown pipeline
- A.1.2: Create
MarkdownRenderer.jsxcomponent with frontmatter extraction - A.1.3: Build
publish.jsonmanifest generator from docs/ directory tree - A.1.4: Extend
viewer.jsxto route markdown docs alongside JSX dashboards - A.1.5: Implement hash-based URL routing (
/#/audience/category/document) - A.1.6: Add print-friendly CSS and document metadata display
- A.2.1: Integrate MiniSearch for client-side full-text search
- A.2.2: Build search index from all markdown content at build time
- A.2.3: Create sidebar navigation tree from publish.json categories
- A.2.4: Add breadcrumb navigation and document table of contents
- A.2.5: Implement keyboard shortcuts (/, Ctrl+K for search)
- A.3.1: Fullscreen presentation mode with minimal chrome
- A.3.2: Keyboard navigation (arrows for prev/next, Escape to exit)
- A.3.3: Section-by-section slide progression within documents
- A.3.4: Presentation timer and progress indicator
- A.4.1: Create
publish.jsonschema and validation - A.4.2: Build static site generator from Vite configuration
- A.4.3: Create Cloud Run deployment configuration
- A.4.4: Implement environment-based auth mode switching
- A.4.5: Create deployment script (
scripts/deploy.sh) - A.4.6: Implement CDN caching with Cloud CDN
- A.4.7: Add custom domain and SSL configuration
- A.4.8: Create publish CLI command for one-click deployment
- A.5.1: Implement NDARecord Django model in auth.coditect.ai
- A.5.2: Implement DocumentViewToken Django model
- A.5.3: Create NDA verification API endpoints
- A.5.4: Implement client-side auth flow in viewer
- A.5.5: Build audit trail for document access
- A.5.6: Implement token revocation and admin controls
- A.5.7: Create local bypass mode for development/presentations
- A.6.1: Extract viewer core into
@coditect/doc-viewernpm package - A.6.2: Create project scaffolding CLI
- A.6.3: Publish to npm with semantic versioning
- A.6.4: Create customer onboarding documentation
B: Competitive Intelligence & GTM (28 done)
- B.0.1: Audit all TRACK-referenced documents for existence
- B.0.2: Create or update missing referenced documents
- B.0.3: Verify document cross-references are bidirectional
- B.0.4: Create document readiness gate for sprint start
- B.1.1: Execute Phase 1 Turn 1 — Market sizing (TAM/SAM/SOM)
- B.1.2: Execute Phase 1 Turn 2 — Customer segmentation & ICP
- B.1.3: Execute Phase 2 Turn 3 — Competitor profiling
- B.1.4: Execute Phase 2 Turn 4 — Moat & positioning
- B.1.5: Execute Phase 3 Turn 5 — Synthesis
- B.1.6: Update existing artifacts (05-10) with new competitive data
- B.1.7: Regenerate competitive-comparison dashboard (54.jsx)
- B.2.1: Execute Turn 1 — GTM model & revenue architecture
- B.2.2: Execute Turn 2 — Channel strategy & sales process
- B.2.3: Execute Turn 3 — Demand gen & content strategy
- B.2.4: Execute Turn 4 — Customer success & expansion
- B.2.5: Execute Turn 5 — Phased launch plan
- B.2.6: Execute Turn 6 — Metrics & dashboards
- B.2.7: Update 09-go-to-market-strategy.md
- B.2.8: Update 62-unified-execution-plan.md with GTM phases
- B.3.1: Execute impact register generation
- B.3.2: Identify cascade update requirements
- B.3.3: Generate impact visualization dashboard
- B.4.1: Audit existing market docs (05-10) against new analysis
- B.4.2: Update executive summary (01-executive-summary.md)
- B.4.3: Update investment thesis (02-executive-summary-updated.md)
- B.4.4: Update financial projections (03-business-case.md)
- B.4.5: Update document inventory (30-document-inventory.md)
- B.4.6: Regenerate publish.json manifest with new artifacts
C: Technical Foundation (42 done)
- C.1.1: Initialize NestJS project with TypeScript strict mode
- C.1.2: Configure Prisma ORM with PostgreSQL schema
- C.1.3: Implement authentication module (JWT + OAuth2)
- C.1.4: Implement RBAC authorization system
- C.1.5: Create base CRUD module with audit trail
- C.1.6: Set up database migrations and seeding
- C.1.7: Configure OpenAPI/Swagger documentation
- C.1.8: Set up testing framework (unit + integration)
- C.2.1: Implement XState workflow engine core (80/80 tests pass, 5 suites)
- C.2.2: Define CAPA state machine (54/54 tests pass)
- C.2.3: Define Deviation state machine (44/44 tests pass)
- C.2.4: Define Change Control state machine (50/50 tests pass, 196/196 full regression)
- C.2.5: Implement state transition API endpoints (239/239 tests pass)
- C.2.6: Add state machine visualization endpoint (264/264 tests pass)
- C.2.7: Implement change control regulatory classification (284/284 tests pass, 70 change control tests)
- C.2.8: Build deviation-to-change linking (306/306 tests pass, 22 cross-entity linking tests)
- C.2.9: Implement change effectiveness verification workflow ✅ 336/336 tests, 30 new
- C.2.10: Create change communication engine ✅ 360/360 tests, 24 new
- C.2.11: Design rollback testing per change type ✅ 386/386 tests, 26 new
- C.3.1: Implement agent execution engine ✅ 2026-02-15
- C.3.2: Create Document Analysis Agent ✅ 2026-02-15
- C.3.3: Create CAPA Investigation Agent ✅ 2026-02-15
- C.3.4: Create Compliance Monitoring Agent ✅ 2026-02-15
- C.3.5: Implement agent API and scheduling ✅ 2026-02-15
- C.3.6: Implement tenant-scoped context isolation ✅ 2026-02-15
- C.3.7: Build agent decision audit trail ✅ 2026-02-15
- C.3.8: Create coditect-core registry components for BIO-QMS agents ✅ 2026-02-15
- C.4.1: Implement cryptographic signing module
- C.4.2: Create electronic signature service
- C.4.3: Implement document integrity verification
- C.4.4: Create timestamping authority integration
- C.4.5: Build signature verification UI components
- C.5.1: Implement webhook event system
- C.5.2: Create ERP integration adapter
- C.5.3: Create LIMS integration adapter
- C.5.4: Create document management integration
- C.5.5: Implement API rate limiting and quotas
- C.5.6: Create integration testing suite
- C.5.7: Implement HL7 FHIR data exchange
- C.5.8: Build batch record traceability — 57 tests pass, 1067/1067 full regression
- C.5.9: Create Electronic Batch Record (EBR) generation — 41 tests pass, 1108/1108 full regression
- C.5.10: Implement quality hold automation — 35 tests pass, 1143/1143 full regression
D: Compliance & Security (33 done)
- D.1.1: Define cryptographic algorithm selection and key management policy
- D.1.2: Design HSM integration architecture for production key management
- D.1.3: Implement certificate chain for document signing
- D.1.4: Create validation test suite for cryptographic operations
- D.2.1: Create IQ/OQ/PQ validation protocol documents
- D.2.2: Implement electronic record controls
- D.2.3: Implement electronic signature controls
- D.2.4: Create validation execution evidence package
- D.2.5: Conduct validation review and approval
- D.3.1: Implement access controls for PHI data
- D.3.2: Implement encryption for PHI at rest and in transit
- D.3.3: Build BAA (Business Associate Agreement) management module
- D.3.4: Create HIPAA audit and reporting capabilities
- D.4.1: Map SOC 2 Trust Service Criteria to system controls
- D.4.2: Implement continuous monitoring controls
- D.4.3: Create SOC 2 evidence collection automation
- D.4.4: Prepare SOC 2 readiness assessment
- D.5.1: Implement immutable audit trail storage
- D.5.2: Create audit trail search and reporting API
- D.5.3: Build compliance dashboard for ongoing monitoring
- D.5.4: Package regulatory submission documentation
- D.5.5: Implement ALCOA+ format preservation controls
- D.5.6: Build original/copy/amendment tracking system
- D.5.7: Create accuracy monitoring dashboard
- D.5.8: Implement legibility controls for long-term storage
- D.6.1: Implement per-tenant encryption key management
- D.6.2: Build automated tenant provisioning workflow
- D.6.3: Create tenant deletion and data purge workflow
- D.6.4: Implement tenant data export and migration
- D.7.1: Build validation test execution framework
- D.7.2: Create validation approval and sign-off workflow
- D.7.3: Implement validation binder assembly automation
- D.7.4: Build periodic re-validation scheduling
Next Up (Pending Tasks in Active Tracks)
F: Documentation & Training (24 remaining)
- F.1.1: Create Getting Started guide
- F.1.2: Create Document Management user guide
- F.1.3: Create CAPA Management user guide
- F.1.4: Create Deviation Management user guide
- F.1.5: Create Search & Reporting user guide
- ... and 19 more
Section Detail (Active Tracks)
A: Presentation & Publishing
- [DONE] A.1 Viewer Enhancement — Markdown Rendering (6/6)
- [DONE] A.2 Navigation & Search (5/5)
- [DONE] A.3 Presentation Mode (4/4)
- [DONE] A.4 Cloud Publishing Platform (ADR-195) (8/8)
- [DONE] A.5 NDA-Gated Access Control (ADR-196) (7/7)
- [DONE] A.6 Multi-Project Reusable Package (4/4)
B: Competitive Intelligence & GTM
- [DONE] B.0 Pre-Sprint Document Verification (4/4)
- [DONE] B.1 Competitive Market Analysis (Prompt 76) (7/7)
- [DONE] B.2 GTM Strategy Generation (Prompt 77) (8/8)
- [DONE] B.3 Cross-Artifact Impact Register (Prompt 78) (3/3)
- [DONE] B.4 Artifact Reconciliation & Update (6/6)
C: Technical Foundation
- [DONE] C.1 Backend API Scaffold (NestJS/Prisma) (8/8)
- [DONE] C.2 State Machine Engine Implementation (11/11)
- [DONE] C.3 Agent Orchestration Framework (8/8)
- [DONE] C.4 E-Signature & Crypto Foundation (5/5)
- [DONE] C.5 Integration & API Layer (10/10)
D: Compliance & Security
- [DONE] D.1 Critical Gap Closure (Crypto/Signatures) (4/4)
- [DONE] D.2 FDA 21 CFR Part 11 Validation (5/5)
- [DONE] D.3 HIPAA Security Controls (4/4)
- [DONE] D.4 SOC 2 Compliance Implementation (4/4)
- [DONE] D.5 Audit Trail & Evidence Package (8/8)
- [DONE] D.6 Multi-Tenancy & Tenant Lifecycle (4/4)
- [DONE] D.7 Validation Execution & Management (4/4)
F: Documentation & Training
- [TODO] F.1 User Documentation (0/5)
- [TODO] F.2 API Documentation (0/4)
- [TODO] F.3 Admin & Compliance Docs (0/4)
- [TODO] F.4 Training Materials (0/5)
- [TODO] F.5 Document Inventory Updates (0/2)
- [TODO] F.6 Training Record Management & Qualification (0/4)
Recent Work (Session Log Excerpts)
2026-02-16:
- 2026-02-16T09:20:47Z — [D.1-D.7] Track D: Compliance & Security — Session Completion Summary
- 2026-02-16T10:35:08Z — [A.4.1-A.4.8] Track A.4: Cloud Publishing Platform — Session Start
- 2026-02-16T15:30:00Z — [ADR-196] NDARecord Django Model Technical Design Document
- 2026-02-16T11:10:52Z — [A.4.1-A.4.8, A.5.1-A.5.7] Track A Sections A.4 + A.5 Complete
- 2026-02-16T11:14:20Z — [A.6] Track A.6: Multi-Project Reusable Package — START
- 2026-02-16T11:30:00Z — [A.6.1-A.6.4] Track A Complete — 100% (34/34 tasks)
- 2026-02-16T11:35:00Z — [E.1-E.5] Track E: Operations & Deployment — START
- 2026-02-16T18:02:00Z — [J.18] Dashboard Consolidation — BIO-QMS becomes consumer 2026-02-15:
- 2026-02-15T10:45:00Z — [C.4.1-C.4.5] E-Signature & Crypto Foundation Complete
- 2026-02-15T10:50:00Z — [C.5] Session Start: Integration & API Layer
- 2026-02-15T11:30:00Z — [C.5.1] Webhook Event System Complete
- 2026-02-15T16:46:21Z — [C.5.2] ERP Integration Adapter Complete + API Research
- 2026-02-15T09:45:00Z — [C.5.3] LIMS Integration Adapter — Complete
- 2026-02-15T21:45:00Z — [C.5.4] Document Management Integration Complete
- 2026-02-15T10:45:00Z — [C.5.5] API Rate Limiting & Quotas Complete
- 2026-02-15T19:04:28Z — [H.0] Project Status Updated + Velocity Dashboard Bug Fix