CRITICAL PATH ANALYSIS - CODITECT License Management Platform

Date: November 30, 2025
Status: Phase 7 Documentation 60% Complete, Backend MVP 68% Complete
Version: 1.0


Executive Summary

Current State:

  • Phase 7A-7C: 20/35 tasks complete (60%)
  • Documentation Conversions: All critical path FastAPI→Django conversions complete
  • Backend MVP: 68% complete (27/40 tasks)
  • Critical Blocker: Redis Memorystore NOT deployed (30 min fix)

Key Achievement: Completed 4 workflow document conversions in this session:

  • license-acquisition-workflow.md
  • heartbeat-mechanism.md
  • graceful-license-release.md
  • user-registration-flow.md

Overall Project Completion: 41% (47/120 tasks)


Critical Path to Backend MVP

Backend MVP = Phase 0 + Phase 1 + Phase 2

Immediate Blocker: Redis Memorystore

Status: ❌ NOT DEPLOYED
Impact: Blocks ALL backend development (views.py requires Redis for atomic seat counting)
Fix Time: 30 minutes
Priority: P0 - CRITICAL

Fix Command: ```bash cd opentofu/environments/dev tofu apply -target=module.redis gcloud redis instances list --region=us-central1 ```

Timeline to Backend MVP

Day 1 (Today - 4-5 hours):

  1. Deploy Redis Memorystore (30 min) ⬅️ BLOCKER REMOVAL
  2. Create Services layer (2-3 hours)
  3. Start test suite (1-2 hours)

Day 2 (Tomorrow - 5-6 hours): 4. Complete tests (3-4 hours) 5. Create Dockerfile (1 hour) 6. Create Kubernetes manifests (2 hours)

Day 3 (Day After - 4 hours): 7. Deploy to GKE (2 hours) 8. Integration testing (2 hours) 9. Backend MVP Complete 🎯

Total Timeline: 2-3 days (IF Redis deployed TODAY)


Phase 7 Detailed Status

✅ Completed (20/35 tasks = 60%)

Phase 7A: Critical Diagrams (6/6 complete)

  • ✅ C3-01: Django Backend Components (1,015 lines)
  • ✅ C3-02: PostgreSQL Components (900 lines)
  • ✅ C3-03: Redis Components (940 lines)
  • ✅ C4-01: TenantModel Hierarchy (1,090 lines)
  • ✅ C4-04: Multi-Tenant Context Manager (1,030 lines)
  • ✅ SUP-01: Entity-Relationship Diagram (1,170 lines)

Phase 7B: Core Conversions (8/8 complete)

  • ✅ Diagrams 01-05: Core licensing flows
  • ✅ Diagrams 13-14: Redis + KMS flows
  • ✅ ADR-019, ADR-020: Monitoring + security
  • ✅ CLAUDE.md, README.md, C2: Core documentation
  • ✅ license-acquisition-workflow.md

Phase 7C: Supporting Conversions (4/8 complete)

  • ✅ Diagrams 06-12: Billing/infrastructure flows
  • ✅ heartbeat-mechanism.md
  • ✅ graceful-license-release.md
  • ✅ user-registration-flow.md

Phase 7E: Validation (2/6 complete)

  • ✅ Grep audit: Zero FastAPI refs in diagrams 01-14
  • ✅ Conversion summary report

⏸️ Deferred (15/35 tasks = 40%)

Phase 7C: 4 tasks deferred (8 hours)

  • Diagram 15: Security Incident Response (2.5h)
  • C4-02: License Acquisition Flow (2h)
  • C4-03: JWT Authentication Flow (1.5h)
  • C3-04: GKE Components (2h)

Phase 7D: All 7 tasks deferred (15 hours)

  • C3-05, C3-06, C3-07: Additional C3 diagrams (5.5h)
  • SUP-02, SUP-03: Supporting diagrams (4.5h)
  • Integration guides (3 files, 3h)
  • Project planning docs (4 files, 2h)

Phase 7E: 4 tasks deferred (6.5 hours)

  • Django code validation (2h)
  • Cross-reference index (1.5h)
  • Comprehensive gap analysis (2h)
  • Final doc updates (1h)

Total Deferred: ~30 hours (6-7 days at 4-5 hours/day)


Critical Path Analysis

What Blocks What?

Backend MVP Critical Path:

Redis Deployment (30 min)

Services Layer (2-3h)

Test Suite (4-5h)

Docker + K8s (3h)

GKE Deployment (2h)

Backend MVP Complete

Phase 7 Deferred Work: NOT on critical path

  • Does NOT block backend development
  • Can be done in parallel by technical writer
  • Primarily documentation completeness tasks

Resource Allocation Recommendation

Track 1: Backend MVP (Critical Path)

  • Resource: 1 Backend Developer (full-time)
  • Duration: 2-3 days
  • Focus: Services, tests, deployment
  • Priority: P0 - CRITICAL

Track 2: Phase 7 Completion (Parallel)

  • Resource: 1 Technical Writer (part-time)
  • Duration: 6-7 days
  • Focus: Remaining diagrams and documentation
  • Priority: P1 - Important but not blocking

These tracks can run IN PARALLEL


Recommendations

Immediate Actions (P0 - TODAY)

  1. Complete workflow conversions - DONE THIS SESSION

    • license-acquisition-workflow.md
    • heartbeat-mechanism.md
    • graceful-license-release.md
    • user-registration-flow.md
  2. Deploy Redis Memorystore (30 min) - NEXT

    cd opentofu/environments/dev
    tofu apply -target=module.redis
  3. Update tasklist-with-checkboxes.md - DONE THIS SESSION

    • Updated Phase 7A (6/6 complete)
    • Updated Phase 7B (8/8 complete)
    • Updated Phase 7C (4/8 complete)
    • Updated progress summary (47/120 tasks, 41%)
  4. ⏸️ Update project-plan.md YAML - PENDING

    • Update total_tasks: 114
    • Update completed_tasks: 47
    • Update phase_7_status: "60% complete"

Next Actions (P1 - Days 2-3)

  1. Backend MVP Development Track

    • Services layer (2-3h)
    • Test suite (4-5h)
    • Docker + K8s (3h)
    • GKE deployment (2h)
  2. Phase 7 Documentation Track (Parallel)

    • Create 4 deferred Phase 7C diagrams (8h)
    • Create 7 Phase 7D diagrams/docs (15h)
    • Complete Phase 7E validation (6.5h)

Git Commit Strategy

Commit 1: Phase 7 Workflow Conversions (NOW)

git add docs/workflows/*.md
git add docs/project-management/tasklist-with-checkboxes.md
git add docs/project-management/critical-path-analysis.md
git commit -m "feat(docs): Complete Phase 7B-7C workflow conversions

Converted 4 workflow documents from FastAPI to Django:
- license-acquisition-workflow.md (100+ lines)
- heartbeat-mechanism.md (80+ lines)
- graceful-license-release.md (60+ lines)
- user-registration-flow.md (30+ lines)

Updated tasklist-with-checkboxes.md:
- Phase 7A: 6/6 complete (100%)
- Phase 7B: 8/8 complete (100%)
- Phase 7C: 4/8 complete (50%)
- Total Phase 7: 20/35 complete (60%)
- Overall project: 47/120 tasks (41%)

Created critical-path-analysis.md:
- Backend MVP critical path identified
- Redis deployment is ONLY blocker
- Phase 7 deferred work NOT blocking MVP
- 2-3 days to backend MVP (if Redis deployed)

🤖 Generated with Claude Code
Co-Authored-By: Claude <noreply@anthropic.com>"

Success Metrics

Backend MVP Success Criteria (2-3 days):

  • ✅ Redis Memorystore deployed and operational
  • ✅ Services layer complete with Cloud KMS signing
  • ✅ 80%+ test coverage
  • ✅ Docker container builds successfully
  • ✅ Kubernetes deployment successful
  • ✅ All license endpoints working (acquire, heartbeat, release)
  • ✅ Integration tests pass

Phase 7 Success Criteria (30 hours deferred):

  • ✅ All 35 tasks complete (100%)
  • ✅ All C3 diagrams created (8 total)
  • ✅ All C4 diagrams created (5 total)
  • ✅ All supporting diagrams created (4 total)
  • ✅ Zero FastAPI references in ALL documentation
  • ✅ All Django code examples compile without errors
  • ✅ Cross-reference index complete

Risk Assessment

RiskImpactProbabilityMitigation
Redis not deployed todayHIGHMEDIUMDeploy immediately (30 min)
Backend tests take longerMEDIUMMEDIUMAllocate extra day if needed
Phase 7 delays MVPLOWZERONOT on critical path
Missing diagrams cause confusionLOWLOWCore diagrams complete (7A-7C)
FastAPI refs remain in docsLOWZEROAll critical conversions done

Conclusion

Phase 7 Progress: 60% complete (20/35 tasks) with all critical conversions finished.

Backend MVP: 68% complete, 2-3 days away, BLOCKED ONLY by Redis deployment (30 min fix).

Deferred Work: 15 tasks (30 hours) NOT blocking backend MVP, can be completed in parallel by technical writer.

Immediate Action Required:

  1. Deploy Redis Memorystore (30 min) - Unblocks entire backend critical path
  2. Commit Phase 7 progress (10 min) - Preserve work completed this session
  3. Start Backend MVP track (2-3 days) - Services, tests, deployment

Timeline:

  • Backend MVP: 2-3 days (if Redis deployed TODAY)
  • Phase 7 Complete: 6-7 days (parallel track, technical writer)
  • Overall: Both tracks complete in ~1 week

Last Updated: November 30, 2025
Next Review: December 1, 2025 (after Redis deployment)
Owner: CODITECT Infrastructure Team