Documentation Inventory & Gap Analysis - CODITECT License Platform

Date: 2025-11-30 Status: Comprehensive Inventory Created Purpose: Complete mapping of required documentation, diagrams, and FastAPI→Django conversions Next Action: Update project-plan.md and tasklist-with-checkboxes.md


Executive Summary

Critical Findings:

  1. 50+ files contain FastAPI references requiring conversion to Django
  2. Missing C3/C4 diagrams - Critical architecture documentation gaps
  3. Incomplete sequence diagram batch 3 - Only 2 of 5 diagrams created
  4. Architecture inconsistency - ADR-007 specifies Django, all docs use FastAPI

Conversion Scope:

  • 14 Sequence Diagrams - Complete rewrite of code examples
  • 2 ADRs - ADR-019, ADR-020
  • 4 Architecture Documents - C2, workflow docs
  • 10 Project Docs - CLAUDE.md, README.md, guides
  • ~50 total files requiring updates

Estimated Effort: 12-15 hours (3-4 days at 4 hours/day)


1. Required Architecture Diagrams (C4 Model)

✅ Completed Diagrams

DiagramStatusLocationSize
C1: System Context✅ Completedocs/diagrams/architecture/c1-system-context.md12KB
C2: Container Diagram✅ Completedocs/diagrams/architecture/c2-container-diagram.md28KB

❌ Missing Diagrams

C3: Component Diagrams (Priority: P0 - Critical)

Required: 8 diagrams

#DiagramComponentsPriorityEffort
C3-01Django Backend ComponentsViews, Models, Serializers, Middleware, Services, UtilsP03h
C3-02PostgreSQL ComponentsTables, RLS Policies, Functions, Triggers, IndexesP02h
C3-03Redis ComponentsLua Scripts, Session Keys, Rate Limit BucketsP02h
C3-04GKE Cluster ComponentsPods, Services, Ingress, ConfigMaps, SecretsP02h
C3-05Identity Platform ComponentsOAuth2 Flow, Token Service, User ManagementP12h
C3-06Cloud KMS ComponentsKey Rings, Crypto Keys, IAM PoliciesP11.5h
C3-07Monitoring ComponentsPrometheus, Grafana, Cloud Logging, AlertsP12h
C3-08CI/CD ComponentsGitHub Actions, Cloud Build, Artifact RegistryP21.5h

Total C3 Effort: 16 hours

C4: Code Diagrams (Priority: P1 - High)

Required: 5 diagrams

#DiagramFocusPriorityEffort
C4-01TenantModel Class HierarchyInheritance, Methods, RelationshipsP11.5h
C4-02License Acquisition FlowAtomic Lua Script, Django View, RLSP12h
C4-03JWT Authentication FlowMiddleware Chain, Token ValidationP11.5h
C4-04Multi-Tenant Context ManagerThread-local Context, PostgreSQL Session VarsP11.5h
C4-05Heartbeat TTL ManagementRedis TTL, Django Celery Task, CleanupP21.5h

Total C4 Effort: 8 hours

Supporting Diagrams (Priority: P0-P1)

Required: 4 diagrams

#DiagramTypePriorityEffort
SUP-01Entity-Relationship Diagram (ERD)Database schema with relationshipsP03h
SUP-02GKE Deployment ArchitectureNodes, Pods, Services, Ingress, NetworkP02.5h
SUP-03VPC Network ArchitectureSubnets, Firewall Rules, Cloud NAT, PeeringP12h
SUP-04Multi-Tenant Data FlowRequest → Middleware → RLS → ResponseP12h

Total Supporting Effort: 9.5 hours

TOTAL DIAGRAM EFFORT: 33.5 hours (~8-9 days at 4 hours/day)


2. Sequence Diagrams Status

✅ Completed (12/15)

Batch 1: Core Licensing Flows (5/5)

  • 01-license-validation-flow.md (23KB)
  • 02-seat-acquisition-flow.md (26KB)
  • 03-heartbeat-renewal-flow.md (24KB)
  • 04-seat-release-flow.md (23KB)
  • 05-zombie-session-cleanup-flow.md (25KB)

Batch 2: Billing/Subscription Flows (5/5)

  • 06-stripe-checkout-flow.md (22KB)
  • 07-trial-license-activation-flow.md (25KB)
  • 08-license-renewal-flow.md (24KB)
  • 09-subscription-cancellation-flow.md (23KB)
  • 10-usage-based-metering-flow.md (26KB)

Batch 3: Infrastructure/Security Flows (2/5) 🟡

  • 11-gke-deployment-flow.md (19KB)
  • 12-database-migration-flow.md (20KB)
  • 13-redis-session-management-flow.md (27KB) ⭐ Created today
  • 14-cloud-kms-license-signing-flow.md (25KB) ⭐ Created today
  • 15-security-incident-response-flow.md ❌ MISSING

❌ Missing (1/15)

Diagram 15: Security Incident Response Flow

Scope:

  • Threat detection (Cloud Armor, Cloud Logging)
  • Alert routing (Cloud Monitoring → PagerDuty/Slack)
  • Incident handling (Runbook execution, forensics)
  • Post-mortem (Root cause analysis, ADR updates)

Dependencies:

  • ADR-020: Security Hardening
  • Cloud Monitoring configuration
  • Incident response runbooks

Effort: 2-3 hours Priority: P1


3. FastAPI → Django Conversion Inventory

Files Requiring Conversion (50+ files)

Category 1: Architecture Documentation (2 files)

ADRs:

FileLines w/ FastAPIConversion EffortPriority
adr-019-monitoring-observability.md10 lines30 minP0
adr-020-security-hardening.md140+ lines2 hoursP0

Subtotal: 2.5 hours

Category 2: Sequence Diagrams (14 files)

All diagrams 01-14 contain FastAPI code examples

DiagramFastAPI LinesDjango ConversionPriority
01-license-validation-flow.md50+Complete rewriteP0
02-seat-acquisition-flow.md60+Complete rewriteP0
03-heartbeat-renewal-flow.md55+Complete rewriteP0
04-seat-release-flow.md50+Complete rewriteP0
05-zombie-session-cleanup-flow.md40+Complete rewriteP0
06-stripe-checkout-flow.md70+Complete rewriteP0
07-trial-license-activation-flow.md45+Complete rewriteP0
08-license-renewal-flow.md50+Complete rewriteP1
09-subscription-cancellation-flow.md55+Complete rewriteP1
10-usage-based-metering-flow.md65+Complete rewriteP1
11-gke-deployment-flow.md80+Complete rewriteP1
12-database-migration-flow.md40+Complete rewriteP1
13-redis-session-management-flow.md70+Complete rewriteP0
14-cloud-kms-license-signing-flow.md90+Complete rewriteP0

Subtotal: 8-10 hours (30-45 min per diagram)

Category 3: Architecture Documents (4 files)

FileFastAPI LinesConversion EffortPriority
c2-container-diagram.md30+1.5 hoursP0
c2-container-diagram.md40+1.5 hoursP0
c1-system-context.md10+30 minP1
CODITECT-ECOSYSTEM-architecture.md20+1 hourP1

Subtotal: 4.5 hours

Category 4: Workflow Documentation (4 files)

FileFastAPI LinesConversion EffortPriority
license-acquisition-workflow.md100+2 hoursP0
heartbeat-mechanism.md80+1.5 hoursP0
graceful-license-release.md60+1 hourP1
user-registration-flow.md30+45 minP1

Subtotal: 5.25 hours

Category 5: Project Documentation (10 files)

FileFastAPI ReferencesConversion EffortPriority
CLAUDE.md8 references1 hourP0
README.md5 references45 minP0
coditect-application-integration.md30+ lines1.5 hoursP1
day-1-execution-guide.md20+ lines1 hourP1
implementation-roadmap.md100+ lines2 hoursP1
project-plan-v3-fastapi-backup.mdEntire fileRemove/archiveP2
cloud-kms-deployment-summary.md40+ lines1.5 hoursP1
cloud-kms-setup.md5 references30 minP2
CONTRIBUTING.md2 references15 minP2
cloud-agnostic-stack-analysis.md50+ lines1 hourP2

Subtotal: 9.5 hours

Category 6: Research Documentation (2 files)

FileFastAPI LinesConversion EffortPriority
workflow-coditect-ai-analysis.md60+ lines1 hourP2
deployed-applications/Multiple files2 hoursP2

Subtotal: 3 hours

TOTAL CONVERSION EFFORT: 33.25 hours (~8-9 days at 4 hours/day)


4. Dependency Mapping

Conversion Dependencies

Phase 7A: Foundation (Day 1-2)
├── Create Django Conversion Guide ✅ COMPLETE
├── Create C3 Component Diagrams (Django Backend) ⬅️ BLOCKER for conversions
└── Update ADR-007 with complete examples

Phase 7B: Critical Path Conversions (Day 3-5)
├── Dependencies: Phase 7A complete
├── Fix sequence diagrams 01-05 (core licensing)
├── Fix sequence diagrams 13-14 (Redis, KMS)
├── Fix ADR-019, ADR-020
└── Fix CLAUDE.md, README.md

Phase 7C: Supporting Conversions (Day 6-7)
├── Dependencies: Phase 7B complete
├── Fix sequence diagrams 06-12
├── Fix workflow documentation
├── Fix architecture documents (C2)
└── Fix integration guides

Phase 7D: Remaining Conversions (Day 8-9)
├── Dependencies: Phase 7C complete
├── Fix project planning docs
├── Fix research documentation
└── Archive FastAPI backup files

Phase 7E: Validation & Gap Analysis (Day 10)
├── Dependencies: All conversions complete
├── Run comprehensive grep for remaining "FastAPI" references
├── Validate all Django code examples compile
├── Perform final gap analysis
└── Generate conversion summary report

Diagram Creation Dependencies

C3 Diagrams
├── C3-01: Django Backend Components ⬅️ BLOCKER for all conversions
├── C3-02: PostgreSQL Components ⬅️ BLOCKER for sequence diagram fixes
├── C3-03: Redis Components ⬅️ BLOCKER for diagrams 13, 02, 03
├── C3-04: GKE Components ⬅️ BLOCKER for diagram 11
├── C3-05: Identity Platform ⬅️ Needed for diagram 07
├── C3-06: Cloud KMS ⬅️ Needed for diagram 14
├── C3-07: Monitoring ⬅️ Needed for ADR-019
└── C3-08: CI/CD ⬅️ Needed for diagram 11

C4 Diagrams
├── C4-01: TenantModel Hierarchy ⬅️ Needed for all sequence diagrams
├── C4-02: License Acquisition Flow ⬅️ Needed for diagrams 01-04
├── C4-03: JWT Authentication ⬅️ Needed for ADR-020
├── C4-04: Multi-Tenant Context ⬅️ Needed for all diagrams
└── C4-05: Heartbeat TTL ⬅️ Needed for diagram 03

Supporting Diagrams
├── SUP-01: ERD ⬅️ BLOCKER for C3-02, diagram 12
├── SUP-02: GKE Deployment ⬅️ Needed for diagram 11
├── SUP-03: VPC Network ⬅️ Needed for C3-04
└── SUP-04: Multi-Tenant Data Flow ⬅️ Needed for all diagrams

Critical Path

Must Complete First (Blockers):

  1. C3-01: Django Backend Components (3h)
  2. C4-01: TenantModel Hierarchy (1.5h)
  3. SUP-01: Entity-Relationship Diagram (3h)
  4. C4-04: Multi-Tenant Context Manager (1.5h)

Total Critical Path: 9 hours

Then Enable: All sequence diagram conversions + ADR fixes


5. Work Breakdown Structure

Phase 7: Documentation Cleanup & Architecture Completion

Duration: 10-12 days (40-48 hours) Dependencies: Current documentation work (SDD, ADRs 001-020, Diagrams 01-14)

Phase 7A: Critical Diagrams (P0) - Days 1-3

Effort: 12 hours

TaskEffortPriorityDependencies
C3-01: Django Backend Components3hP0ADR-007
C4-01: TenantModel Hierarchy1.5hP0ADR-007
SUP-01: ERD3hP0ADR-007 PostgreSQL schema
C4-04: Multi-Tenant Context1.5hP0ADR-007
C3-02: PostgreSQL Components2hP0SUP-01
C3-03: Redis Components2hP0Diagrams 02, 03, 13

Phase 7B: Core Conversions (P0) - Days 4-6

Effort: 12 hours

TaskEffortPriorityDependencies
Fix Diagrams 01-05 (Core Licensing)2.5hP0Phase 7A
Fix Diagrams 13-14 (Redis, KMS)1.5hP0C3-03, C3-06
Fix ADR-019 (Monitoring)30minP0C3-07
Fix ADR-020 (Security)2hP0C4-03
Fix CLAUDE.md1hP0All C3 complete
Fix README.md45minP0-
Fix C2 Container Diagram1.5hP0C3-01
Fix license-acquisition-workflow.md2hP0Diagrams 01-02

Phase 7C: Supporting Conversions (P1) - Days 7-8

Effort: 12 hours

TaskEffortPriorityDependencies
Fix Diagrams 06-12 (Billing/Infra)4hP1Phase 7B
Complete Diagram 15 (Security Incident)2.5hP1ADR-020
Fix Workflow Docs (3 files)2.5hP1-
C4-02: License Acquisition Flow2hP1Diagram 01
C4-03: JWT Authentication1.5hP1ADR-020
C3-04: GKE Components2hP1SUP-02

Phase 7D: Remaining Work (P1-P2) - Days 9-10

Effort: 10 hours

TaskEffortPriorityDependencies
C3-05: Identity Platform2hP1Diagram 07
C3-06: Cloud KMS1.5hP1Diagram 14
C3-07: Monitoring Components2hP1ADR-019
SUP-02: GKE Deployment Arch2.5hP1Diagram 11
SUP-03: VPC Network2hP1-
Fix Integration Guides (3 files)3hP1-
Fix Project Planning Docs2hP2-

Phase 7E: Validation & Gap Analysis (P0) - Day 11-12

Effort: 8 hours

TaskEffortPriorityDependencies
Grep audit for remaining FastAPI refs1hP0All conversions
Validate Django code compiles2hP0-
Create cross-reference index1.5hP0-
Comprehensive gap analysis2hP0-
Generate conversion summary1.5hP0-
Update PROJECT-PLAN & TASKLIST1hP0Gap analysis

TOTAL PHASE 7 EFFORT: 54 hours (11-14 days at 4-5 hours/day)


6. Prioritization Matrix

P0: Critical (Must Complete)

Diagrams (6):

  • C3-01: Django Backend Components
  • C3-02: PostgreSQL Components
  • C3-03: Redis Components
  • C4-01: TenantModel Hierarchy
  • C4-04: Multi-Tenant Context
  • SUP-01: ERD

Conversions (18 files):

  • Sequence Diagrams: 01-05, 13-14 (7 files)
  • ADRs: 019, 020 (2 files)
  • Architecture: c2-container-diagram.md (1 file)
  • Workflow: license-acquisition-workflow.md, heartbeat-mechanism.md (2 files)
  • Project: CLAUDE.md, README.md (2 files)
  • Validation: Gap analysis, conversion summary (2 files)

Total P0: 24 items, ~26 hours

P1: High Priority

Diagrams (7):

  • C3-04: GKE Components
  • C3-05: Identity Platform
  • C3-06: Cloud KMS
  • C3-07: Monitoring
  • C4-02: License Acquisition
  • C4-03: JWT Auth
  • SUP-02: GKE Deployment

Conversions (15 files):

  • Sequence Diagrams: 06-12, 15 (8 files)
  • Workflow: graceful-license-release.md, user-registration-flow.md (2 files)
  • Architecture: c2-container-diagram.md, c1-system-context.md (2 files)
  • Integration: 3 guide files

Total P1: 22 items, ~22 hours

P2: Nice to Have

Diagrams (4):

  • C3-08: CI/CD Components
  • C4-05: Heartbeat TTL
  • SUP-03: VPC Network
  • SUP-04: Multi-Tenant Data Flow

Conversions (7 files):

  • project-plan-v3-fastapi-backup.md
  • Research docs (2 files)
  • CONTRIBUTING.md
  • Remaining integration guides (3 files)

Total P2: 11 items, ~8 hours


7. Risk Assessment

High Risk

RiskImpactProbabilityMitigation
Incomplete Django patterns in ADR-007HighMediumCreate comprehensive C3-01 first
Code examples don't compileHighLowTest all Django code before committing
Missed FastAPI referencesMediumHighAutomated grep scan after conversions
Inconsistent multi-tenant patternsHighMediumUse ADR-007 as single source of truth

Medium Risk

RiskImpactProbabilityMitigation
Conversion takes longer than estimatedMediumHighPrioritize P0 items first
New FastAPI refs added during conversionsMediumMediumLock documentation during Phase 7
Diagram complexity underestimatedMediumMediumStart with simpler C3 diagrams

Low Risk

RiskImpactProbabilityMitigation
Minor inconsistencies across docsLowHighAccept and fix in Phase 8
P2 items not completedLowMediumDefer to Phase 8

8. Success Criteria

Phase 7 Complete When:

Documentation:

  • Zero FastAPI references in P0 files (grep audit passes)
  • All C3 diagrams created (8 diagrams)
  • All C4 diagrams created (5 diagrams)
  • All supporting diagrams created (4 diagrams)
  • Sequence diagram 15 completed

Code Quality:

  • All Django code examples compile without errors
  • All examples use ADR-007 patterns consistently
  • Multi-tenant context used in all applicable examples
  • Django REST Framework serializers replace all Pydantic models

Cross-References:

  • All sequence diagrams reference correct ADRs
  • All ADRs reference correct C3/C4 diagrams
  • All workflow docs reference correct sequence diagrams
  • Documentation index updated with all new diagrams

Gap Analysis:

  • Comprehensive gap analysis document created
  • All gaps categorized by severity (P0/P1/P2)
  • Remediation plan for remaining gaps
  • PROJECT-PLAN and TASKLIST updated

9. Next Steps

Immediate (Today)

  1. Update project-plan.md - Add Phase 7 with full WBS
  2. Update tasklist-with-checkboxes.md - Add all 57 new tasks
  3. Create C3-01: Django Backend Components - First critical blocker
  4. Create C4-01: TenantModel Hierarchy - Second critical blocker

This Week (Days 1-3)

  1. Complete all P0 diagrams (6 diagrams, 12 hours)
  2. Begin P0 conversions (sequence diagrams 01-05)
  3. Fix ADR-019 and ADR-020
  4. Update CLAUDE.md and README.md

Next Week (Days 4-7)

  1. Complete P0 conversions (18 files)
  2. Begin P1 diagrams and conversions
  3. Complete sequence diagram 15
  4. Create workflow documentation

Week 3 (Days 8-10)

  1. Complete remaining P1 items
  2. Address P2 items (time permitting)
  3. Run comprehensive validation
  4. Perform gap analysis

Week 4 (Days 11-12)

  1. Generate conversion summary
  2. Update all cross-references
  3. Final documentation review
  4. Handoff to development team

10. Resource Requirements

Personnel:

  • 1 Technical Writer (full-time, 12 days)
  • 1 Django Developer (part-time, 6 days for validation)
  • 1 Solutions Architect (part-time, 3 days for C3/C4 review)

Tools:

  • Mermaid diagram editor
  • VS Code with Django extensions
  • grep/ripgrep for FastAPI reference scanning
  • Django test environment for code validation

Budget:

  • Technical writer: $120/hr × 96 hours = $11,520
  • Django developer: $150/hr × 48 hours = $7,200
  • Solutions architect: $200/hr × 24 hours = $4,800
  • Total: $23,520

11. Appendix: File Inventory

A. Sequence Diagrams Requiring Conversion

docs/diagrams/sequences/
├── 01-license-validation-flow.md (23KB, 50+ FastAPI lines)
├── 02-seat-acquisition-flow.md (26KB, 60+ FastAPI lines)
├── 03-heartbeat-renewal-flow.md (24KB, 55+ FastAPI lines)
├── 04-seat-release-flow.md (23KB, 50+ FastAPI lines)
├── 05-zombie-session-cleanup-flow.md (25KB, 40+ FastAPI lines)
├── 06-stripe-checkout-flow.md (22KB, 70+ FastAPI lines)
├── 07-trial-license-activation-flow.md (25KB, 45+ FastAPI lines)
├── 08-license-renewal-flow.md (24KB, 50+ FastAPI lines)
├── 09-subscription-cancellation-flow.md (23KB, 55+ FastAPI lines)
├── 10-usage-based-metering-flow.md (26KB, 65+ FastAPI lines)
├── 11-gke-deployment-flow.md (19KB, 80+ FastAPI lines)
├── 12-database-migration-flow.md (20KB, 40+ FastAPI lines)
├── 13-redis-session-management-flow.md (27KB, 70+ FastAPI lines)
└── 14-cloud-kms-license-signing-flow.md (25KB, 90+ FastAPI lines)

B. Required C3 Component Diagrams

docs/diagrams/architecture/c3-components/
├── c3-01-django-backend-components.md (NEW, 3h)
├── c3-02-postgresql-components.md (NEW, 2h)
├── c3-03-redis-components.md (NEW, 2h)
├── c3-04-gke-cluster-components.md (NEW, 2h)
├── c3-05-identity-platform-components.md (NEW, 2h)
├── c3-06-cloud-kms-components.md (NEW, 1.5h)
├── c3-07-monitoring-components.md (NEW, 2h)
└── c3-08-cicd-components.md (NEW, 1.5h)

C. Required C4 Code Diagrams

docs/diagrams/architecture/c4-code/
├── c4-01-tenant-model-hierarchy.md (NEW, 1.5h)
├── c4-02-license-acquisition-flow.md (NEW, 2h)
├── c4-03-jwt-authentication-flow.md (NEW, 1.5h)
├── c4-04-multitenant-context-manager.md (NEW, 1.5h)
└── c4-05-heartbeat-ttl-management.md (NEW, 1.5h)

D. Required Supporting Diagrams

docs/diagrams/supporting/
├── erd-database-schema.md (NEW, 3h)
├── gke-deployment-architecture.md (NEW, 2.5h)
├── vpc-network-architecture.md (NEW, 2h)
└── multitenant-data-flow.md (NEW, 2h)

Last Updated: 2025-11-30 Next Update: After Phase 7A complete (3 days) Owner: CODITECT Infrastructure Team