CODITECT Business Alignment - Executive Summary

Date: December 18, 2025 Status: CRITICAL REVIEW REQUIRED Distribution: Executive Team, Board of Directors


Bottom Line Up Front (BLUF)

DO NOT CONSOLIDATE Rollout-Master and V2 plans - they serve complementary purposes. However, CRITICAL timeline misalignment requires immediate correction to avoid Pilot launch failure (Dec 24 deadline at risk).


Critical Findings

1. Timeline Misalignment (CRITICAL)

Issue: V2 plan schedules Pilot/GTM for August 2026, but actual target is March 11, 2026 (5+ months earlier).

ACTUAL Timeline (Rollout-Master):
Dec 24 ──► Jan 21 ──► Feb 18 ──► Mar 11, 2026
Pilot P1 Pilot P2 Analysis PUBLIC LAUNCH

V2 Timeline (WRONG):
Aug 25 - Sep 5, 2026
└── 5+ MONTHS AFTER PUBLIC LAUNCH!

Impact: Engineering team executing to wrong timeline, jeopardizing Dec 24 Pilot Phase 1 launch.

Action Required: Update V2 E010 epic immediately to Sprint 25-30 (Dec 2025 - Feb 2026).


2. Budget Scope Confusion

Issue: Two dramatically different budget numbers with no explanation.

PlanBudgetScope
Rollout-Master$2,566KTOTAL - Engineering + Marketing + Sales + Operations
V2 Plan$105KENGINEERING ONLY - Autonomous agent system development

Reality: V2's $105K is a 4% subset of Rollout-Master's $2.5M total investment.

Action Required: Document scope difference in both plans to avoid stakeholder confusion.


3. ICP Strategy Missing from V2

Issue: V2 lacks Ideal Customer Profile, customer segmentation, or market targeting.

Rollout-Master defines:

  • ✅ Regulated industries (Healthcare, Finance, Legal)
  • ✅ Beta/Pilot/GTM user personas
  • ✅ 3-tier pricing model ($0 → $49/user → Enterprise)

V2 references:

  • ❌ Generic "users" with no segmentation
  • ❌ No customer validation criteria
  • ❌ No pricing integration

Action Required: Create ICP strategy document bridging both plans.


4. FUTUREPRISE Vision Not Formalized

Issue: 7-Phase platform evolution exists in diagrams but not formalized as strategic plan.

Current Status:

  • Phase 1-3: ✅ Complete (Claude Framework, IDE Cloud, Workflow Analyzer)
  • Phase 4-7: 📋 Defined in diagrams but not in V2 roadmap

Gap: No formal ADR, inconsistent timelines between vision and V2 sprints.

Action Required: Create ADR-007 formalizing FUTUREPRISE 7-Phase vision.


Document Strategy

Why TWO Plans Are Necessary

Rollout-Master PROJECT-PLAN:

  • Audience: Stakeholders, investors, customers, executives
  • Focus: Commercial milestones, revenue targets, market strategy
  • Timeline: Beta → Pilot → GTM (customer-facing phases)
  • Metrics: NPS, conversion rates, MRR, customer count

V2-MASTER-PROJECT-PLAN:

  • Audience: Engineering team, scrum master, product owner
  • Focus: Technical delivery, sprint execution, feature development
  • Timeline: 32 sprints, 10 epics, 17,546 tasks (granular execution)
  • Metrics: Velocity, test coverage, uptime, autonomy %

Relationship:

┌─────────────────────────────┐
│ Rollout-Master (Business) │ ← Drives requirements for
└──────────────┬──────────────┘


┌─────────────────────────────┐
│ V2 Plan (Engineering) │ ← Executes technical delivery
└─────────────────────────────┘

Recommendation: Keep separate, establish explicit cross-references.


Immediate Actions (This Week)

P0: Critical Path (Dec 18-24, 2025)

#ActionOwnerDeliverableDue
1Update V2 E010 timeline from Aug 2026 to Dec 2025 - Feb 2026Product OwnerUpdated V2 planDec 19
2Create V2-to-Pilot dependency map for Dec 24 launchProgram ManagerDependency docDec 20
3Document budget scope ($105K engineering vs $2.5M total)CFOBudget clarificationDec 21

P1: High Priority (Dec 25 - Jan 7, 2026)

#ActionOwnerDeliverableDue
4Formalize FUTUREPRISE 7-Phase vision as ADR-007CTOADR documentJan 3
5Create ICP strategy documentProduct MarketingICP docJan 5
6Build unified risk register (commercial + technical)Risk LeadRisk registerJan 7
7Add customer value statements to V2 epic overviewsProduct OwnerUpdated epicsJan 7

Success Metrics Dashboard

Customer-Facing (Rollout-Master)

MetricTargetCurrentStatusTimeline
Pilot Customers10+0📅 PendingDec 24 start
Platform Uptime99.9%Measuring⚡ ActiveContinuous
Beta NPS>60Gathering⚡ ActiveDec 10-24
MRR (Month 12)$150K$0🎯 TargetMar 11, 2026
Pilot-to-Paid40%TBD📅 PendingFeb 18, 2026

Engineering (V2 Plan)

MetricBaselineTargetCurrentSprint
Autonomy %0%95%0%Sprint 25-26
Velocity50/day100/dayTBDSprint 25+
Test CoverageN/A80%+TBDSprint 25+
Component Activation0290TBDSprint 25-26

Recommendation: Create unified KPI dashboard for executive visibility.


Risk Summary

Top 5 Risks (Ranked by Impact × Probability)

RankRiskImpactProbabilityMitigation
1V2 timeline misalignment delays Pilot launchCRITICALHIGHP0: Update V2 timeline immediately
2Revenue target miss ($150K MRR)HighMediumPilot conversion tracking, multi-channel GTM
3Engineering velocity <50 tasks/dayHighMediumAutomated task execution, parallel sprints
4Platform stability <99.9% uptimeCriticalLowBeta testing, monitoring, circuit breakers
5Customer acquisition failureHighMediumICP strategy, regulated industry focus

Recommendation: Establish weekly risk review with executive team.


Strategic Recommendations

Document Management

  1. Keep Both Plans Separate - They serve different audiences and purposes
  2. Establish Cross-References - Explicit links between milestones/epics
  3. Create Unified Supporting Artifacts - Risk register, budget dashboard, ICP strategy

Timeline Synchronization

  1. Align V2 E010 with Rollout-Master Pilot/GTM - Dec 2025 - Mar 2026, not Aug 2026
  2. Create Dependency Maps - Sprint 25 deliverables → Pilot Phase 1 prerequisites
  3. Establish Phase Gates - Engineering readiness checks before customer milestones

Customer Strategy

  1. Formalize ICP - Document regulated industry focus, customer personas
  2. Add Customer Value to V2 - Every epic should state customer benefit
  3. Create FUTUREPRISE ADR - 7-Phase vision as architectural decision record

ROI Summary

Year 1 Investment & Returns

Total Investment: $2,566K (Development + Beta + Pilot + GTM)

Revenue Target: $150K MRR = $1,800K ARR (Month 12)

Year 1 ROI: -30% (investment recovery phase - expected)

Year 2 Projection:

  • Revenue: $4,500K ARR (2.5x growth)
  • ROI: 75%+ (profitable)

Engineering ROI (V2 Autonomous System):

  • Investment: $105K
  • Year 1 Benefit: $130K (operational efficiency)
  • Year 1 ROI: 29%
  • Year 2 ROI: 858%

Conclusion: Investment strategy is sound, timeline misalignment is primary risk.


Next Review

Date: January 7, 2026 Agenda:

  1. V2 E010 timeline update verification
  2. Pilot Phase 1 launch post-mortem (Dec 24 start)
  3. Dependency map effectiveness review
  4. ICP strategy approval
  5. FUTUREPRISE ADR-007 review

Approval Required

This executive summary requires approval from:

  • CEO / Founder
  • CTO
  • Product Owner
  • CFO
  • Board of Directors (if applicable)

Sign-Off Date: __________________


Document Classification: CONFIDENTIAL - INTERNAL ONLY Next Update: Bi-weekly during Pilot phase (Jan 7, Jan 21, Feb 4, Feb 18) Owner: Business Intelligence / Strategy Team Contact: [Executive Team]


Prepared By: Business Intelligence Analyst Date: December 18, 2025 Version: 1.0.0