Project Plan: Hyper-Scale SaaS with Django and Citus

Project: CODITECT Hyper-Scale Multi-Tenant SaaS Platform Date: November 22, 2025 Owner: CODITECT Architecture Team Status: DRAFT


1. Executive Summary

This document outlines the project plan for building and scaling the CODITECT SaaS platform to support 1 million+ tenant organizations. The architecture is based on the "Hyper-Scale" recommendation from the SAAS-FRAMEWORK-COMPARISON-2025.md document.

The core of the architecture is a shared-table multi-tenancy model using Django as the application framework, Citus for distributed PostgreSQL, and django-multitenant for application-level tenant isolation.

The project is divided into three main phases:

  1. Phase 1: Foundation (MVP on django-tenants): To achieve rapid product-market fit.
  2. Phase 2: Scale Preparation: To refactor the application in preparation for migration.
  3. Phase 3: Migration to Citus: To transition to the hyper-scale architecture.

2. Technology Stack

The technology stack is defined by the "Hyper-Scale (1M+ Tenants)" requirements.

ComponentRecommended Solution
ArchitectureMicroservices
Backend FrameworkDjango 5.x
Multi-Tenancydjango-multitenant + Citus
DatabaseCitus (Distributed PostgreSQL)
AuthenticationOry Hydra + Authlib
PaymentsStripe Billing API
API GatewayKong or Traefik
Load BalancerGoogle Cloud Load Balancer
CachingRedis Cluster
Task QueueCelery + RabbitMQ Cluster
OrchestrationKubernetes (GKE)
ObservabilityPrometheus + Grafana + Jaeger

3. Phase 1: Foundation & MVP (0 - 10,000 Tenants)

Goal: Launch an MVP quickly to validate product-market fit. Use a simpler, schema-per-tenant architecture that is faster to develop. Timeline: 3 Months Architecture: Monolithic Django application with django-tenants.

Phase 1 Tasks:

Task IDTask NameTeamEffort (days)Description
P1-T01Environment SetupDevOps5Set up development, staging, and production environments on Google Cloud Platform (GCP).
P1-T02Django Project InitializationBackend3Initialize Django project, configure settings, and set up basic application structure.
P1-T03Multi-Tenancy with django-tenantsBackend5Integrate django-tenants for schema-per-tenant isolation. Define Tenant and Domain models.
P1-T04Core API DevelopmentBackend15Build core business logic, models (Project, Task, etc.), and DRF-based APIs. Crucially, all models must include a tenant_id field from day one to prepare for Phase 2.
P1-T05User Authentication with AuthlibBackend7Implement user registration, login, and session management using Authlib integrated into Django.
P1-T06Subscription & Billing with StripeBackend10Integrate Stripe Billing for subscription management. Implement webhook handlers for payment events.
P1-T07Frontend ScaffoldingFrontend10Set up a React/Vue frontend application. Implement routing, state management, and basic UI components.
P1-T08Frontend-Backend IntegrationFrontend/Backend10Connect frontend to backend APIs for all core features.
P1-T09CI/CD PipelineDevOps5Implement GitHub Actions for automated testing and deployment to staging and production.
P1-T10MVP LaunchAll5Final testing, documentation, and go-live.

Phase 1 Milestones:

  • M1.1: Development environment is fully operational.
  • M1.2: Core backend APIs with django-tenants are complete.
  • M1.3: User authentication and billing are functional.
  • M1.4: MVP is live and accepting tenants.

4. Phase 2: Scale Preparation (10,000 - 50,000 Tenants)

Goal: Refactor the application to be compatible with django-multitenant and Citus. Begin building out the microservices architecture in a staging environment. Timeline: 6 Months Architecture: Hybrid. Production remains on Phase 1 monolith. A new staging environment is built with the microservices architecture.

Phase 2 Tasks:

Task IDTask NameTeamEffort (days)Description
P2-T01Setup Citus Staging ClusterDevOps10Deploy a 3-worker Citus cluster in a dedicated staging environment.
P2-T02Data Migration ScriptingBackend15Develop and test scripts to migrate data from django-tenants (schemas) to a shared-table model (using tenant_id).
P2-T03Refactor to django-multitenantBackend20In a separate branch, replace django-tenants with django-multitenant. Ensure all queries are correctly filtered by tenant_id.
P2-T04Microservices Scaffolding (GKE)DevOps15Set up a Google Kubernetes Engine (GKE) cluster. Define services for Auth, Core API, and Billing.
P2-T05Auth Service (Ory Hydra)Backend15Build and deploy the standalone authentication service using Ory Hydra.
P2-T06API Gateway Setup (Kong)DevOps10Deploy and configure Kong as the API gateway for routing requests to the new microservices.
P2-T07Observability StackDevOps10Deploy Prometheus, Grafana, and Jaeger to the Kubernetes cluster for monitoring.
P2-T08Staging Migration TestBackend/DevOps10Perform a full migration of a subset of production data (e.g., 1,000 tenants) to the Citus staging environment. Validate data integrity and performance.
P2-T09Load TestingQA/DevOps10Use Locust to load-test the new microservices architecture to ensure it meets performance requirements.

Phase 2 Milestones:

  • M2.1: Citus staging cluster is operational.
  • M2.2: Data migration scripts are complete and validated.
  • M2.3: All core services are containerized and deployed on Kubernetes in staging.
  • M2.4: Successful end-to-end test of the hyper-scale architecture in the staging environment.

5. Phase 3: Migration to Citus & Hyper-Scale (50,000 - 1M+ Tenants)

Goal: Complete the full migration of the production environment to the hyper-scale microservices architecture with zero downtime. Timeline: 3-6 Months Architecture: Blue-Green deployment strategy.

Phase 3 Tasks:

Task IDTask NameTeamEffort (days)Description
P3-T01Deploy Citus Production ClusterDevOps10Deploy a production-grade Citus cluster (e.g., 10+ worker nodes).
P3-T02Deploy Microservices to ProductionDevOps10Deploy the new microservices stack (the "Green" environment) into the production namespace, running parallel to the existing monolith (the "Blue" environment).
P3-T03Setup Real-time Data SyncBackend/DevOps15Implement a data synchronization mechanism (e.g., logical replication or application-level triggers) from the old database to the new Citus cluster.
P3-T04Blue-Green Traffic RoutingDevOps5Configure the load balancer to allow for gradual traffic shifting from the Blue environment to the Green environment.
P3-T05Initial Tenant Migration (10%)All7Migrate a small percentage of new and low-activity tenants to the Green environment. Monitor closely for any issues.
P3-T06Incremental Tenant MigrationAll30Gradually migrate the remaining tenants in batches over several weeks.
P3-T07Full CutoverAll2Shift 100% of traffic to the Green environment. The Blue environment is now on standby.
P3-T08Decommission Old InfrastructureDevOps5After a 30-day observation period with no major issues, decommission the old monolithic infrastructure.
P3-T09Scale Citus ClusterDevOpsOngoingAdd more worker nodes to the Citus cluster as the number of tenants grows towards 1M+.

Phase 3 Milestones:

  • M3.1: Production hyper-scale environment is live and running in parallel.
  • M3.2: 10% of tenants successfully migrated and operating on the new architecture.
  • M3.3: 100% of traffic is successfully routed to the new Citus-based architecture.
  • M3.4: Old infrastructure is successfully decommissioned. The project is complete.

6. Risk Assessment

RiskLikelihoodImpactMitigation
django-tenants performance bottleneckMediumMediumOccurs during Phase 1. Mitigated by migrating to Phase 3. Monitor DB performance closely.
Data Migration ComplexityHighHighDevelop robust, idempotent migration scripts (P2-T02). Perform multiple test runs in staging (P2-T08). Have a clear rollback plan.
Citus Performance TuningMediumHighEngage with CitusData/Microsoft support. Dedicate DevOps time for performance tuning and query optimization.
Microservice ComplexityHighMediumInvest heavily in the observability stack (P2-T07) and distributed tracing to manage complexity.
Vendor Lock-in (Stripe/AWS/GCP)MediumMediumAbstract payment logic and infrastructure provisioning to allow for future changes if necessary.