Timeline Conflict - Executive Summary
URGENT: Decision Required by Dec 20, 2025
Date: 2025-12-18 Status: 🔴 CRITICAL - Conflicting timelines block Pilot planning Decision Maker: Hal Casteel, Founder/CEO/CTO Deadline: December 20, 2025 (2 days)
The Problem (1 Minute Read)
Two project plans exist with incompatible timelines:
Rollout-Master (Primary)
- Location:
/docs/project-management/PROJECT-PLAN.md - Launch Date: March 11, 2026 (83 days away)
- Scope: 57 submodules, complete ecosystem rollout
- Tasks: 1,629 tasks (15.8% complete)
- Status: Production active, Pilot starts Dec 24
V2 Master Plan (Submodule)
- Location:
submodules/core/coditect-core/docs/05-project-planning/v2/ - Launch Date: September 5, 2026 (261 days away) - CONFLICT
- Scope: CODITECT Core autonomy implementation
- Tasks: 17,546 tasks (0% - fresh baseline)
- Status: Sprint 25 of 56 active
Critical Conflicts
1. Launch Date Discrepancy 🔴
- Rollout-Master: March 11, 2026
- V2 Sprint Roadmap: September 5, 2026
- V2 E010 Text: March 11, 2026 (internal inconsistency)
- Gap: 6 months
2. Pilot Timeline Mismatch 🔴
- Rollout-Master: Pilot starts Dec 24 (6 days away)
- V2 E010: Pilot in Sprint 52-56 (November 2026)
- Gap: 10 months
3. Completed Work Not Reflected 🔴
- Rollout-Master: Beta complete (Dec 10), entering Pilot
- V2: Beta scheduled for Sprint 52-56 (future)
- Impact: V2 doesn't account for 3.5 months of completed work
Three Options for Decision
Option A: Rollout-Master Authoritative (RECOMMENDED ✅)
Timeline: March 11, 2026 launch (83 days)
What Changes:
- V2 becomes detailed implementation plan for autonomy only
- V2 compressed to Sprint 25-30 (pre-launch features)
- V2 E003-E009 delivered post-launch (incremental releases)
Impact:
- ✅ Meets March 11 market window
- ✅ Pilot proceeds as planned (Dec 24)
- ✅ Stakeholder expectations met
- ⚠️ Reduced scope at launch (core features only)
- ⚠️ Advanced features (autonomy, workflows) post-launch
Budget: No change ($2.566M through Month 12)
Option B: V2 Authoritative
Timeline: September 5, 2026 launch (261 days)
What Changes:
- Rollout-master extended 6 months
- Pilot delayed to November 2026
- March 11 market window missed
- Stakeholders notified of timeline change
Impact:
- ✅ Full V2 scope (17,546 tasks) complete at launch
- ✅ All 10 epics delivered
- ❌ 6-month delay in revenue ($900K MRR lost)
- ❌ Pilot customers waiting 10 months
- ❌ Misses Q1 2026 market window
Budget: Add $600K for 6 additional months (total $3.166M)
Option C: Hybrid Approach
Timeline: March 11 soft launch, September full platform
What Changes:
- March 11: Core features (E001, E002, E010) - Public Beta
- Monthly releases: E003-E009 rolled out incrementally
- September 5: Platform 2.0 (full autonomy achieved)
Impact:
- ✅ Meets March market window (soft launch)
- ✅ Full V2 scope delivered by September
- ✅ Continuous value delivery
- ⚠️ Two launch events to coordinate
- ⚠️ Customer expectations management (beta vs. full)
Budget: No change ($2.566M), revenue starts March 11
Financial Impact Comparison
| Option | Launch Date | Revenue Start | Month 12 Revenue | Total Investment |
|---|---|---|---|---|
| A: Rollout-Master | Mar 11, 2026 | Mar 2026 | $1.8M ARR | $2.566M |
| B: V2 Extended | Sep 5, 2026 | Sep 2026 | $600K ARR | $3.166M (+$600K) |
| C: Hybrid | Mar 11, 2026 | Mar 2026 | $1.8M ARR | $2.566M |
Lost Revenue (Option B): $900K (6 months × $150K MRR target)
Recommendation: Option A (Rollout-Master Authoritative)
Why Option A?
- Market Window: March 11 aligns with Q1 2026 market opportunity
- Revenue: Start generating revenue 6 months earlier ($900K difference)
- Pilot Intact: 10+ pilot customers proceed as planned (Dec 24)
- Realistic Scope: MVP with core features, advanced features post-launch
- Stakeholder Alignment: Matches existing commitments and expectations
What Gets Delivered March 11 (Option A)
Critical Path (E001, E002, E010):
- ✅ Core platform autonomy (component activation, message bus)
- ✅ Toon UI integration (50+ React components, generative UI)
- ✅ Pilot program complete (10+ customers, >60 NPS)
- ✅ Documentation (user guides, API docs)
- ✅ Security & compliance (OAuth2, audit logging)
- ✅ 99.9% platform uptime
Post-Launch (E003-E009):
- April: Memory Intelligence (E003)
- May: Workflow Automation (E004)
- June: Enhanced QA (E005)
- July: Deployment Infrastructure (E006)
- August: Documentation System (E007)
- September: Platform 2.0 (full autonomy)
Decision Required
By: December 20, 2025 (Friday) Format: Written confirmation (email or Slack)
Please confirm:
- Which option (A, B, or C)?
- If Option A: Approve V2 compression plan?
- If Option B: Approve 6-month delay and budget increase?
- If Option C: Approve dual-launch strategy?
Immediate Actions (Post-Decision)
If Option A Chosen (24-48 hours)
-
Update V2 Plan:
- Move E010 Beta to COMPLETE (Dec 10)
- Move E010 Pilot to Sprint 25-29 (Dec 16 - Feb 21)
- Move E010 Launch to Sprint 30 (Feb 24 - Mar 7)
- Reschedule E003-E009 to post-launch (Mar 12+)
-
Communicate Timeline:
- Email team with unified timeline
- Update project dashboards
- Notify pilot customers (no change)
-
Create Unified Gantt:
- Merge rollout-master + V2 into single view
- Publish to project management tool
- Distribute to stakeholders
If Option B Chosen (1 week)
-
Extend Rollout-Master:
- Update PROJECT-PLAN.md with Sep 5 launch
- Reschedule Pilot to November 2026
- Add 6 months to Phase 5 (GTM)
-
Stakeholder Communication:
- Executive briefing on timeline change
- Customer communication (delay notification)
- Investor update (if applicable)
-
Budget Revision:
- Allocate additional $600K for 6 months
- Revise revenue projections (Month 12: $600K vs. $1.8M)
If Option C Chosen (1 week)
-
Define Soft Launch Scope:
- Create MVP feature list (E001, E002, E010)
- Document post-launch roadmap (E003-E009)
- Set customer expectations (beta vs. full)
-
Dual Launch Plan:
- March 11: Public Beta announcement
- Monthly releases: Feature rollout schedule
- September 5: Platform 2.0 launch event
-
Marketing Coordination:
- Two launch campaigns (beta + full)
- Customer success program (beta users → paid)
Supporting Documents
- Full Analysis: TIMELINE-RECONCILIATION-REPORT.md (15,000 words)
- Visual Timeline: UNIFIED-TIMELINE-GANTT.md (Mermaid charts)
- Current Plans:
- Rollout-Master: PROJECT-PLAN.md
- V2 Master: submodules/core/coditect-core/docs/05-project-planning/v2/V2-MASTER-PROJECT-PLAN.md
Contact for Questions
Hal Casteel, Founder/CEO/CTO
- Decision Authority: Final
- Timeline: Dec 20, 2025 (2 days)
- Format: Written confirmation required
Risk of Delay
If no decision by Dec 20:
- ❌ Pilot planning blocked (starts Dec 24)
- ❌ Sprint 25-26 work potentially misdirected
- ❌ Team confusion on priorities
- ❌ Customer communication delayed
- ❌ Risk of missing March 11 launch
Bottom Line: Decision required within 48 hours to keep Pilot on track.
Status: URGENT DECISION REQUIRED Next Update: Post-decision implementation plan Owner: Hal Casteel
Decision Record (To Be Completed)
Date of Decision: _______________ Option Chosen: ☐ A (Rollout-Master) ☐ B (V2 Extended) ☐ C (Hybrid) Signature: _______________ Next Steps: _______________
END OF EXECUTIVE SUMMARY