Timeline Reconciliation Report

Rollout-Master vs V2 Master Project Plan​

Analysis Date: 2025-12-18 Analyst: Timeline and Roadmap Analyst Status: CRITICAL ALIGNMENT REQUIRED


Executive Summary​

Critical Finding: TIMELINE CONFLICT DETECTED​

Two parallel project plans exist with incompatible timelines and scopes:

DimensionRollout-Master (Primary)V2 Master Plan (Submodule)Conflict Level
Target LaunchMarch 11, 2026September 5, 2026πŸ”΄ CRITICAL (6 months gap)
Days Remaining83 days261 daysπŸ”΄ CRITICAL
Current PhaseP0 Critical Path β†’ Pilot (Dec 24)Sprint 25 of 56 (V2 baseline)πŸ”΄ CRITICAL
Total Tasks1,629 tasks17,546 tasks🟑 MAJOR (10x difference)
Scope57 submodules rolloutCODITECT Core autonomy only🟑 MAJOR
Completion258/1,629 (15.8%)0/17,546 (0% - V2 rebaselined)🟑 MAJOR

RECOMMENDATION: IMMEDIATE CONSOLIDATION REQUIRED

The V2 plan appears to be a detailed autonomy implementation plan for CODITECT Core, while rollout-master is the master orchestration for all 57 submodules. These should be reconciled into a unified timeline.


Timeline Alignment Analysis​

Rollout-Master Timeline (PRIMARY - Production Active)​

Project Span: August 27, 2025 β†’ March 11, 2026 (196 days total, 83 days remaining)

Completed Milestones​

DateMilestoneStatus
Aug 27, 2025Project Kickoffβœ… Complete
Nov 19, 2025Core Development Completeβœ… Complete
Nov 12, 2025Beta Testing Launchβœ… Complete
Dec 10, 2025Beta Analysis Completeβœ… Complete

Active/Upcoming Milestones​

DateMilestoneStatusDays Away
Dec 18, 2025P0 Critical Path Start⚑ ACTIVE NOW0 days
Dec 24, 2025Pilot Phase 1 StartπŸ“… Scheduled6 days
Jan 21, 2026Pilot Phase 2 StartπŸ“… Scheduled34 days
Feb 18, 2026Pilot Analysis CompleteπŸ“… Scheduled62 days
Mar 11, 2026Public Launch (GTM)🎯 TARGET83 days

Phase Structure (Rollout-Master)​

Phase 0: Foundation & Architecture βœ… COMPLETE (Nov 1-16)
Phase 0.5: Submodule Inventory & Critical Path πŸ”¨ IN PROGRESS
Phase 0.6-0.7: Dev Category Organization βœ… COMPLETE
Phase 0.8-1.4: Ecosystem-Wide Organization πŸ“‹ PLANNED
Phase 1: Development βœ… COMPLETE
Phase 2: Testing βœ… COMPLETE
Phase 3: Beta Testing ⚑ ACTIVE (Nov 12 - Dec 10) βœ… COMPLETE
Phase 4: Pilot Program πŸ“… SCHEDULED (Dec 24 - Feb 18, 8 weeks)
β”œβ”€β”€ Wave 1: Dec 24 - Jan 21 (4 weeks)
└── Wave 2: Jan 21 - Feb 18 (4 weeks)
Phase 5: Go-to-Market 🎯 TARGET (Mar 11, 2026)

V2 Master Plan Timeline (SUBMODULE - Detailed Autonomy Plan)​

Project Span: Sprint 25 (Dec 16, 2025) β†’ Sprint 56 (Sept 5, 2026) (261 days / 64 weeks)

Current Status (V2)​

  • Sprint: 25 of 56 (45% timeline elapsed, 0% scope complete - rebaselined)
  • Velocity Target: 1,000-1,400 tasks/sprint (autonomous operation)
  • Note: V2 is a fresh baseline - legacy V1 archived

Epic Structure (V2)​

E001: Core Platform Autonomy (1,093 tasks) - ACTIVE
Sprint 25-26 (Dec 16 - Jan 10, 4 weeks)

E002: Toon UI Integration (2,341 tasks) - PLANNED
Sprint 27-30 (Jan 13 - Mar 7, 8 weeks)

E003: Memory Intelligence (1,876 tasks) - PLANNED
Sprint 31-34 (Mar 10 - Apr 21, 8 weeks)

E004: Workflow Automation (2,198 tasks) - PLANNED
Sprint 35-38 (Apr 24 - Jun 16, 8 weeks)

E005: Quality Assurance (1,542 tasks) - PLANNED
Sprint 39-41 (Jun 19 - Jul 28, 6 weeks)

E006: Deployment Infrastructure (1,234 tasks) - PLANNED
Sprint 42-44 (Jul 31 - Aug 25, 6 weeks)

E007: Documentation System (987 tasks) - PLANNED
Sprint 45-46 (Aug 28 - Sep 8, 4 weeks)

E008: Security & Compliance (1,654 tasks) - PLANNED
Sprint 47-49 (Sep 11 - Oct 6, 6 weeks)

E009: Analytics & Observability (1,432 tasks) - PLANNED
Sprint 50-51 (Oct 9 - Nov 3, 4 weeks)

E010: Rollout & GTM (3,189 tasks) - PLANNED
Sprint 52-56 (Nov 6 - Sep 5, 10 weeks)
└── Public Launch: March 11, 2026 (in E010 details)

Critical Conflicts​

Conflict 1: Launch Date Discrepancy πŸ”΄ CRITICAL​

Issue: Two different public launch targets exist

  • Rollout-Master: March 11, 2026 (83 days away)
  • V2 Plan Epic Roadmap: September 5, 2026 (Sprint 56 end)
  • V2 Plan E010 Details: March 11, 2026 (matches rollout-master)

Analysis:

  • V2 plan has internal inconsistency: E010 mentions March 11, 2026 launch, but sprint roadmap extends to September 2026
  • E010 (Rollout & GTM) is scheduled for Sprints 52-56 (Nov 6 - Sep 5)
  • This suggests V2 extends 6 months past the target public launch date

Impact: SEVERE - Cannot have two launch dates

Resolution Required:

  1. Clarify: Is March 11, 2026 a soft launch (beta/pilot graduates to public) with continued development until September?
  2. Or: Is V2 timeline incorrect and needs compression to align with March 11 target?

Conflict 2: Sprint Structure Misalignment 🟑 MAJOR​

Issue: Rollout-master uses phase-based planning, V2 uses 2-week sprint cycles

Rollout-Master Approach:

  • Phase-based (Phases 0-5)
  • Milestone-driven (specific dates)
  • Wave-based pilot (Wave 1 + Wave 2)

V2 Approach:

  • Sprint-based (Sprint 25-56, 32 sprints total)
  • Epic-based (E001-E010)
  • 2-week iteration cycles

Analysis:

  • Both are valid project management approaches
  • V2 provides more granular tracking (bi-weekly sprints)
  • Rollout-master provides clearer business milestones (Pilot, GTM)

Impact: MODERATE - Different planning methodologies, both teams may be using different tracking

Resolution Required:

  • Map V2 sprints to rollout-master phases
  • Create unified Gantt chart showing both views
  • Establish single source of truth for progress tracking

Conflict 3: Pilot Timeline Overlap 🟑 MAJOR​

Issue: V2 E010 (Rollout & GTM) scheduled for November-September, but rollout-master Pilot starts December 24

Rollout-Master Pilot:

  • Dec 24, 2025 - Feb 18, 2026 (8 weeks)
  • 2 waves (4 weeks each)
  • 10+ pilot customers

V2 E010 Rollout & GTM:

  • Sprint 52-56 (Nov 6 - Sep 5, 2026)
  • Includes: Beta testing (50 users), Pilot (10 customers), Public launch, Post-launch support

Analysis:

  • V2 treats "Beta + Pilot + Launch + Support" as a single epic (E010)
  • Rollout-master already completed Beta (Dec 10) and is entering Pilot (Dec 24)
  • V2 schedules these activities for 9 months in the future

Impact: SEVERE - V2 timeline doesn't account for already-completed Beta and imminent Pilot

Resolution Required:

  • Update V2 E010 to reflect actual Beta completion (Dec 10)
  • Move V2 Pilot activities from Sprint 52-56 to Sprint 25-26 (current)
  • Reconcile V2 "Public Launch" with rollout-master March 11 target

Conflict 4: Task Count Discrepancy 🟑 MAJOR​

Issue: 10x difference in task counts

  • Rollout-Master: 1,629 tasks (258 complete, 1,371 in progress)
  • V2 Plan: 17,546 tasks (0% complete - rebaselined)

Analysis:

  • V2 is granular autonomy implementation (ORCHESTRATOR-PROJECT-PLAN.md based)
  • Rollout-master is high-level orchestration across 57 submodules
  • V2 focuses on CODITECT Core autonomy (1 of 57 submodules)

Scope Comparison:

PlanScopeGranularity
Rollout-Master57 submodules (entire ecosystem)High-level milestones
V2 MasterCODITECT Core autonomy onlyTask-level implementation

Impact: MODERATE - Different levels of abstraction, not directly comparable

Resolution Required:

  • Clarify: Is V2 a detailed breakdown of rollout-master E001 autonomy tasks?
  • If yes: V2 should be a sub-plan under rollout-master Phase 0.8-1.0
  • If no: V2 should be scoped to Core only, rollout-master remains master plan

Sprint Structure Comparison​

Rollout-Master Sprint Model​

No explicit sprint structure - uses phase-based milestones with week-based P0 critical path

P0 Critical Path (Dec 18 - Dec 24, 6 days):

Week 2-3 (Dec 25 - Jan 7): AUTHENTICATION & DATA
Week 6-9 (Jan 22 - Feb 18): PILOT ITERATION

Phase Durations:

  • Phase 3 (Beta): 4 weeks (Nov 12 - Dec 10) βœ… Complete
  • Phase 4 (Pilot): 8 weeks (Dec 24 - Feb 18) πŸ“… Scheduled
  • Phase 5 (GTM): 3 weeks (Feb 18 - Mar 11) 🎯 Target

V2 Sprint Model​

Strict 2-week sprint cadence (Sprint 25-56, 32 sprints = 64 weeks)

Sprint Timeline:

SprintDatesEpicGoalTasks
25Dec 16-27E001V2 Launch + Autonomy Start547
26Dec 30-Jan 10E001Autonomy Complete546
27Jan 13-24E002Toon UI Start585
28Jan 27-Feb 7E002Toon Components585
29Feb 10-21E002Generative UI586
30Feb 24-Mar 7E002Toon Complete585
31Mar 10-21E003Memory Intelligence Start469
...............
56Aug 25-Sep 5E010Public Launch637

Note: V2 assumes 1,000-1,400 tasks/sprint velocity (autonomous operation)


Milestone Alignment Matrix​

Rollout-Master Milestones Mapped to V2 Sprints​

Rollout-Master MilestoneDateV2 Sprint EquivalentV2 EpicAlignment
P0 Critical Path StartDec 18, 2025Sprint 25 (Dec 16-27)E001βœ… ALIGNED
Pilot Phase 1 StartDec 24, 2025Sprint 25-26E001⚠️ PARTIAL (V2 E010 in future)
Pilot Phase 2 StartJan 21, 2026Sprint 28 (Jan 27-Feb 7)E002❌ MISALIGNED (1 week off)
Pilot Analysis CompleteFeb 18, 2026Sprint 29 (Feb 10-21)E002⚠️ PARTIAL
Public Launch (GTM)Mar 11, 2026Sprint 30 (Feb 24-Mar 7)E002❌ CRITICAL CONFLICT

Critical Issues:

  1. Public Launch Conflict:

    • Rollout-master: March 11, 2026 (during Sprint 30)
    • V2: E010 (Rollout & GTM) scheduled for Sprints 52-56 (Nov-Sep 2026)
    • V2 has E002 (Toon UI) active during public launch, not E010 (Rollout & GTM)
  2. Pilot Phase Misalignment:

    • Rollout-master: Pilot starts Sprint 25-26 (Dec 24 - Jan 21)
    • V2: E010 (includes Pilot) starts Sprint 52 (November 2026)
    • V2 schedules Pilot 10 months after rollout-master
  3. Epic Sequencing Issue:

    • V2 runs E001-E009 before E010 (Rollout & GTM)
    • Rollout-master expects simultaneous development + pilot + GTM prep
    • V2 treats GTM as final epic, rollout-master treats it as parallel stream

Critical Path Analysis​

Rollout-Master Critical Path​

P0 Critical Path to Pilot (Dec 18-24, 6 days):

Must-complete for Pilot Phase 1:

  1. Authentication & authorization system
  2. Pilot customer onboarding flow
  3. License management system
  4. Core platform stability (99.9% uptime)
  5. Documentation (user guides, API docs)

Phase 4 Critical Path (Pilot - 8 weeks):

  1. Wave 1 (Dec 24 - Jan 21): First 5 pilot customers
  2. Wave 2 (Jan 21 - Feb 18): Next 5 pilot customers
  3. Pilot analysis & iteration

Phase 5 Critical Path (GTM - 3 weeks):

  1. Feb 18-25: Final polish & docs
  2. Feb 25-Mar 4: Marketing launch prep
  3. Mar 4-11: Soft launch β†’ Public launch

V2 Critical Path​

E001: Core Platform Autonomy (Sprint 25-26, 4 weeks):

  • Component activation system (290 components)
  • Message bus (RabbitMQ) for inter-agent communication
  • Task queue manager (Redis + RQ)
  • Agent discovery service
  • Circuit breaker resilience

Dependencies:

  • E002 (Toon UI) depends on E001 completion
  • E003 (Memory) depends on E001 completion
  • E010 (Rollout) depends on E001-E009 completion

Critical Path to March 11 Launch:

  • E001 must complete by Jan 10 (Sprint 26)
  • E002 must complete by Mar 7 (Sprint 30)
  • E003-E009 scheduled AFTER March 11 launch ← CRITICAL ISSUE

Pilot Launch Timeline Reconciliation​

Rollout-Master Pilot Plan​

Duration: Dec 24, 2025 - Feb 18, 2026 (8 weeks)

Wave 1 (Dec 24 - Jan 21, 4 weeks):

  • Target: 5 pilot customers
  • Focus: Core platform validation
  • Success Criteria: 10+ pilot customers signed, >60 NPS

Wave 2 (Jan 21 - Feb 18, 4 weeks):

  • Target: 5 additional pilot customers
  • Focus: Scale validation, edge case handling
  • Success Criteria: >40% conversion commitment

Total Pilot Customers: 10+


V2 Pilot Plan (E010.2)​

Duration: Sprint 52-56 (estimated Nov 6, 2026 - Sep 5, 2026)

Deliverable:

  • Pilot deployment (10 customers)
  • Customer success program
  • Feedback collection
  • Iterative improvements

Critical Issue: V2 schedules Pilot for 10 months after rollout-master Pilot start


Recommendations​

IMMEDIATE (Week of Dec 18-24)​

1. Establish Single Source of Truth πŸ”΄ CRITICAL​

Action: Determine which plan is authoritative

Options:

Option A: Rollout-Master is Master (RECOMMENDED)

  • V2 becomes detailed implementation plan for E001 autonomy only
  • V2 compressed to align with March 11 launch
  • V2 E010 updated to reflect actual Pilot timeline (Dec 24 - Feb 18)

Option B: V2 is Master

  • Rollout-master updated to extend GTM to September 2026
  • Stakeholders informed of 6-month delay
  • March 11 becomes "soft launch" with continued development

Option C: Hybrid Approach

  • March 11: Public launch with core features only (E001-E002)
  • September 2026: Full platform launch with autonomy complete (E001-E010)
  • V2 continues post-launch as ongoing development roadmap

Recommendation: Option A - Keep March 11 launch, compress V2 to detailed autonomy plan


2. Update V2 E010 Timeline πŸ”΄ CRITICAL​

Current Issue: E010 scheduled for Sprints 52-56 (Nov 2026), but Pilot starts Dec 24, 2025

Required Actions:

  1. Move E010 Beta Testing to "COMPLETE" (already done Dec 10)
  2. Move E010 Pilot to Sprint 25-29 (Dec 16 - Feb 21)
  3. Move E010 Public Launch to Sprint 30 (Feb 24 - Mar 7)
  4. Repurpose Sprints 52-56 for post-launch support/iteration

3. Reconcile Task Counts 🟑 MAJOR​

Action: Clarify relationship between 1,629 and 17,546 tasks

Analysis Questions:

  1. Are V2's 17,546 tasks a detailed breakdown of rollout-master's 1,629 tasks?
  2. If yes: Update rollout-master to reference V2 for autonomy implementation details
  3. If no: Scope V2 to "CODITECT Core autonomy implementation" (subset of rollout-master)

Recommendation: Treat V2 as Level 2 detail for rollout-master E001 autonomy


SHORT-TERM (Week of Dec 25 - Jan 7)​

4. Create Unified Timeline Visualization 🟑 MAJOR​

Action: Generate Gantt chart showing both plans aligned

Deliverable: UNIFIED-TIMELINE-GANTT.md showing:

  • Rollout-master phases (horizontal bars)
  • V2 sprints (vertical lines)
  • V2 epics (horizontal bars)
  • Milestone markers (Pilot start, Public launch)
  • Critical path highlighted

Tool: Mermaid gantt chart or PlantUML


5. Map V2 Epics to Rollout-Master Phases 🟑 MAJOR​

Proposed Mapping:

V2 EpicRollout-Master PhaseTimeline Alignment
E001: Core Platform AutonomyPhase 0.8-1.0 (Core category)Sprint 25-26 (Dec 16 - Jan 10)
E002: Toon UI IntegrationPhase 1.0 (Docs category)Sprint 27-30 (Jan 13 - Mar 7)
E003: Memory IntelligencePhase 0.8 (Core - enhancement)Sprint 31-34 (Mar 10 - Apr 21) - POST-LAUNCH
E004: Workflow AutomationPhase 1.1 (Ops category)Sprint 35-38 (Apr 24 - Jun 16) - POST-LAUNCH
E005: Quality AssurancePhase 2 (Testing) - COMPLETESprint 39-41 (Jun 19 - Jul 28) - POST-LAUNCH
E006: Deployment InfrastructurePhase 0.9 (Cloud category)Sprint 42-44 (Jul 31 - Aug 25) - POST-LAUNCH
E007: Documentation SystemPhase 1.0 (Docs category)Sprint 45-46 (Aug 28 - Sep 8) - POST-LAUNCH
E008: Security & CompliancePhase 3 (Beta) - COMPLETESprint 47-49 (Sep 11 - Oct 6) - POST-LAUNCH
E009: Analytics & ObservabilityPhase 1.1 (Ops category)Sprint 50-51 (Oct 9 - Nov 3) - POST-LAUNCH
E010: Rollout & GTMPhase 4-5 (Pilot + GTM)Sprint 25-30 (Dec 16 - Mar 7) - ACTIVE/UPCOMING

Recommendation: Resequence V2 to prioritize E001, E002, E010 before March 11


MEDIUM-TERM (Week of Jan 8-21)​

6. Compress V2 Timeline to March 11 🟑 MAJOR​

Current V2 Duration: 64 weeks (Dec 16, 2025 - Sep 5, 2026) Target Duration: 12 weeks (Dec 16, 2025 - Mar 11, 2026)

Compression Strategy:

Phase 1: Essential Launch Features (Sprint 25-30, Dec 16 - Mar 7)

  • E001: Core Platform Autonomy (Sprint 25-26) - KEEP
  • E002: Toon UI Integration (Sprint 27-30) - KEEP
  • E010: Rollout & GTM (Sprint 25-30 parallel) - ACCELERATE

Phase 2: Post-Launch Enhancements (Sprint 31-56, Mar 10 - Sep 5)

  • E003-E009 delivered incrementally post-launch
  • Monthly release cadence
  • Continuous improvement model

Impact:

  • Launch on time (March 11)
  • Core features ready (E001, E002, E010)
  • Advanced features (E003-E009) delivered as updates

7. Align Sprint Boundaries with Pilot Waves 🟑 MAJOR​

Current Misalignment:

  • Pilot Wave 1: Dec 24 - Jan 21 (4 weeks)
  • V2 Sprint 25: Dec 16-27 (2 weeks)
  • V2 Sprint 26: Dec 30-Jan 10 (2 weeks)
  • Gap: Pilot Wave 1 ends Jan 21, Sprint 26 ends Jan 10 (11 days off)

Proposed Alignment:

Pilot PhaseV2 SprintsDatesDuration
Wave 1Sprint 25-26Dec 16 - Jan 134 weeks
Wave 2Sprint 27-28Jan 13 - Feb 104 weeks
AnalysisSprint 29Feb 10 - Feb 242 weeks
GTM PrepSprint 30Feb 24 - Mar 102 weeks

Benefit: Sprint reviews align with pilot wave reviews


Risk Assessment​

High Risk (Address Immediately)​

R1: Conflicting Launch Dates πŸ”΄

  • Impact: Team confusion, stakeholder misalignment, missed market window
  • Probability: HIGH (already exists)
  • Mitigation: Establish single source of truth (Recommendation #1)

R2: Pilot Timeline Confusion πŸ”΄

  • Impact: Pilot customers onboarded to wrong timeline, unmet expectations
  • Probability: HIGH (6-day gap to Pilot start)
  • Mitigation: Update V2 E010 immediately (Recommendation #2)

R3: Task Count Mismatch πŸ”΄

  • Impact: Resource allocation errors, burnout, scope creep
  • Probability: MEDIUM
  • Mitigation: Clarify relationship between plans (Recommendation #3)

Medium Risk (Address Within 2 Weeks)​

R4: Sprint Misalignment with Pilot Waves 🟑

  • Impact: Inefficient sprint reviews, pilot feedback not incorporated timely
  • Probability: MEDIUM
  • Mitigation: Align sprint boundaries (Recommendation #7)

R5: Post-Launch Feature Expectations 🟑

  • Impact: Customers expect E003-E009 features at launch, not delivered
  • Probability: MEDIUM (if not communicated)
  • Mitigation: Clear MVP scope, post-launch roadmap published

Low Risk (Monitor)​

R6: Documentation Synchronization 🟒

  • Impact: Multiple outdated plans confuse new team members
  • Probability: LOW (if addressed early)
  • Mitigation: Deprecate older plans, single canonical source

Proposed Unified Timeline​

Consolidated Timeline (Dec 18, 2025 - Mar 11, 2026)​

83 Days Remaining to Launch

Week 1: Dec 18-24 (P0 Critical Path)​

  • Rollout-Master: P0 implementation gaps
  • V2 Sprint 25: V2 launch + E001 autonomy start (547 tasks)
  • Milestone: Pilot Phase 1 starts Dec 24

Weeks 2-5: Dec 25 - Jan 21 (Pilot Wave 1)​

  • Rollout-Master: Authentication & data implementation
  • V2 Sprint 25-26: E001 autonomy complete (1,093 tasks)
  • Milestone: 5 pilot customers onboarded

Weeks 6-9: Jan 22 - Feb 18 (Pilot Wave 2)​

  • Rollout-Master: Pilot iteration & feedback
  • V2 Sprint 27-28: E002 Toon UI start (1,170 tasks)
  • Milestone: 10+ pilot customers, >60 NPS achieved

Weeks 10-11: Feb 19 - Mar 4 (Final Polish)​

  • Rollout-Master: GTM preparation
  • V2 Sprint 29-30: E002 Toon UI complete (1,171 tasks)
  • Milestone: Final docs, marketing materials ready

Week 12: Mar 5 - Mar 11 (Launch Week)​

  • Rollout-Master: Public launch
  • V2 Sprint 30: E010 public launch execution
  • Milestone: March 11, 2026 - PUBLIC LAUNCH 🎯

Post-Launch: Mar 12 - Sep 5 (Continuous Improvement)​

  • Rollout-Master: Phase 5+ ongoing support
  • V2 Sprint 31-56: E003-E009 rolled out incrementally
  • Milestone: Monthly feature releases

Success Metrics Alignment​

Rollout-Master Success Criteria (By March 11)​

MetricTargetV2 Epic Alignment
50+ active pilot users50+E010.1 (Beta) + E010.2 (Pilot)
>60 NPS60+E010.2 (Pilot feedback)
>40% conversion commitment40%+E010.3 (GTM conversion tracking)
Platform uptime >99.9%99.9%E001 (Circuit breakers) + E006 (Monitoring)
3-5 documented case studies3-5E010.4 (Post-launch support)
Zero critical security vulnerabilities0E008 (Security & Compliance)
Complete documentation100%E007 (Documentation System)
57 submodules operational57Rollout-master scope (V2 = Core only)
Multi-agent orchestration provenValidatedE001 (Autonomy)

Analysis:

  • E001, E010 are critical path to March 11 launch
  • E002 (Toon UI) is high priority for UX
  • E003-E009 are nice-to-have for March 11, can be post-launch

V2 Success Criteria (E001-E010)​

EpicSuccess CriteriaMarch 11 Requirement
E001290 components activated, agent-to-agent communicationβœ… CRITICAL
E00250+ React components, generative UI demoβœ… CRITICAL
E003Enhanced context.db, decision extraction⏸️ POST-LAUNCH
E004Custom workflow engine, 25+ templates⏸️ POST-LAUNCH
E00580%+ test coverageβœ… CRITICAL (Phase 2 complete)
E006CI/CD pipeline, K8s orchestration⏸️ POST-LAUNCH
E007Auto-generated API docsβœ… HIGH PRIORITY
E008OAuth2, audit loggingβœ… CRITICAL (Phase 3 complete)
E009Prometheus/Grafana monitoring⏸️ POST-LAUNCH
E010Beta (50), Pilot (10), Public launchβœ… CRITICAL

Recommendation:

  • MVP for March 11: E001 (Autonomy) + E002 (Toon UI) + E010 (Rollout) + subset of E005/E007/E008
  • Post-Launch: E003, E004, E006, E009 delivered incrementally

Next Steps (Action Plan)​

URGENT (Within 48 Hours - By Dec 20)​

  1. Stakeholder Alignment Meeting

    • Hal Casteel (Product Owner)
    • Tech Lead (if available)
    • Scrum Master (if available)
    • Agenda: Resolve timeline conflict (Option A vs B vs C)
    • Deliverable: Written decision on authoritative plan
  2. Update V2 E010 Timeline

    • Move Beta to COMPLETE (Dec 10)
    • Move Pilot to Sprint 25-29 (Dec 16 - Feb 21)
    • Move Public Launch to Sprint 30 (Feb 24 - Mar 7)
    • Owner: V2 plan maintainer
    • Deliverable: Updated V2-MASTER-PROJECT-PLAN.md
  3. Communicate Timeline to Team

    • Email update with unified timeline
    • Slack announcement in #coditect-dev
    • Update project dashboards
    • Owner: Project Manager
    • Deliverable: Team acknowledgment

HIGH PRIORITY (Within 1 Week - By Dec 24)​

  1. Create Unified Timeline Gantt Chart

    • Merge rollout-master phases + V2 sprints
    • Highlight critical path (E001, E010)
    • Mark Pilot waves, launch date
    • Owner: Timeline Analyst (this report author)
    • Deliverable: UNIFIED-TIMELINE-GANTT.md
  2. Reconcile Task Counts

    • Map V2's 17,546 tasks to rollout-master's 1,629 tasks
    • Identify overlaps, gaps, duplicates
    • Create task hierarchy (rollout-master Level 1 β†’ V2 Level 2)
    • Owner: Project Manager + Tech Lead
    • Deliverable: TASK-RECONCILIATION-MATRIX.md
  3. Compress V2 Timeline

    • Identify E001-E002 critical path tasks
    • Defer E003-E009 to post-launch
    • Accelerate E010 to Sprint 25-30
    • Owner: V2 plan owner + development team
    • Deliverable: V2-COMPRESSED-ROADMAP.md

MEDIUM PRIORITY (Within 2 Weeks - By Jan 7)​

  1. Align Sprint Boundaries

    • Adjust V2 sprint dates to match Pilot waves
    • Update sprint goals to reflect pilot priorities
    • Owner: Scrum Master
    • Deliverable: Updated sprint schedule
  2. Define MVP Scope

    • Document features included in March 11 launch
    • Document features deferred to post-launch
    • Communicate expectations to pilot customers
    • Owner: Product Owner
    • Deliverable: MVP-SCOPE-DEFINITION.md
  3. Update Documentation

    • Deprecate conflicting plans
    • Establish rollout-master as canonical source
    • Reference V2 as detailed autonomy plan
    • Owner: Documentation team
    • Deliverable: Updated CLAUDE.md files

Appendix A: Key Document References​

Rollout-Master Documents​

  • /Users/halcasteel/PROJECTS/coditect-rollout-master/docs/project-management/PROJECT-PLAN.md
  • /Users/halcasteel/PROJECTS/coditect-rollout-master/docs/project-management/TASKLIST.md
  • /Users/halcasteel/PROJECTS/coditect-rollout-master/CLAUDE.md

V2 Documents​

  • /Users/halcasteel/PROJECTS/coditect-rollout-master/submodules/core/coditect-core/docs/05-project-planning/v2/V2-MASTER-PROJECT-PLAN.md
  • /Users/halcasteel/PROJECTS/coditect-rollout-master/submodules/core/coditect-core/docs/05-project-planning/v2/epics/E001-AUTONOMY/EPIC-OVERVIEW.md
  • /Users/halcasteel/PROJECTS/coditect-rollout-master/submodules/core/coditect-core/docs/05-project-planning/v2/sprints/Sprint-25/SPRINT-PLAN.md

Appendix B: Timeline Visualization (Text-Based)​

CODITECT Rollout Timeline - Unified View
================================================================================

DECEMBER 2025
--------------
Week 1 (Dec 16-24): P0 Critical Path β†’ Pilot Start
[==========Rollout: P0 Critical Path===========]
[==V2: Sprint 25 (E001 Start - 547 tasks)======]
↑ Dec 24: PILOT STARTS

Week 2-4 (Dec 25 - Jan 14): Pilot Wave 1 Start
[==============Rollout: Authentication & Data================]
[==V2: Sprint 25 End==][==V2: Sprint 26 (E001 Complete)==]

JANUARY 2026
------------
Week 5-8 (Jan 15 - Feb 11): Pilot Wave 1 End, Wave 2 Start
[==============Rollout: Pilot Wave 2=======================]
[==V2: Sprint 27 (E002 Start)==][==V2: Sprint 28========]
↑ Jan 21: PILOT WAVE 2 STARTS

FEBRUARY 2026
-------------
Week 9-11 (Feb 12 - Mar 4): Pilot Analysis, GTM Prep
[===========Rollout: Pilot Analysis + GTM Prep============]
[==V2: Sprint 29 (E002)==][==V2: Sprint 30 (E002 End)===]
↑ Feb 18: PILOT COMPLETE

MARCH 2026
----------
Week 12 (Mar 5-11): PUBLIC LAUNCH WEEK
[======Rollout: GTM LAUNCH=======]
[==V2: Sprint 30 (E010 Launch)==]
↑ Mar 11: PUBLIC LAUNCH 🎯

POST-LAUNCH (Mar 12 - Sep 5, 2026)
-----------------------------------
[===========Rollout: Phase 5+ Support=======================>
[==V2: Sprint 31-56 (E003-E009 Incremental Delivery)=======>

Appendix C: Epic vs Phase Mapping​

V2 EpicRollout PhaseStatusTimeline Alignment
E001: Core Platform AutonomyPhase 0.8-1.0ActiveSprint 25-26 (Dec 16 - Jan 10)
E002: Toon UI IntegrationPhase 1.0PlannedSprint 27-30 (Jan 13 - Mar 7)
E010: Rollout & GTMPhase 4-5Active/UpcomingSprint 25-30 (Dec 16 - Mar 7)
E003: Memory IntelligencePhase 0.8 (Post-Launch)PlannedSprint 31-34 (Mar 10 - Apr 21)
E004: Workflow AutomationPhase 1.1 (Post-Launch)PlannedSprint 35-38 (Apr 24 - Jun 16)
E005: Quality AssurancePhase 2 (Complete)CompleteSprint 39-41 (Jun 19 - Jul 28)
E006: Deployment InfrastructurePhase 0.9 (Post-Launch)PlannedSprint 42-44 (Jul 31 - Aug 25)
E007: Documentation SystemPhase 1.0 (Post-Launch)PlannedSprint 45-46 (Aug 28 - Sep 8)
E008: Security & CompliancePhase 3 (Complete)CompleteSprint 47-49 (Sep 11 - Oct 6)
E009: Analytics & ObservabilityPhase 1.1 (Post-Launch)PlannedSprint 50-51 (Oct 9 - Nov 3)

Report Generated: 2025-12-18 Author: Timeline and Roadmap Analyst Status: URGENT REVIEW REQUIRED Next Review: 2025-12-20 (Post-stakeholder decision) Owner: Hal Casteel, Founder/CEO/CTO


CRITICAL DECISION REQUIRED BY DEC 20: Choose Option A (Rollout-Master authoritative), Option B (V2 authoritative), or Option C (Hybrid approach). Current conflict blocks effective sprint planning for Pilot Phase 1 (starts Dec 24).