Unified Timeline Gantt Chart
Rollout-Master + V2 Master Plan Comparison
Created: 2025-12-18 Purpose: Visual reconciliation of two planning timelines Status: DRAFT - Requires stakeholder decision
Timeline Comparison Overview
Key Findings
| Dimension | Rollout-Master | V2 Master Plan | Alignment |
|---|---|---|---|
| Launch Date | March 11, 2026 | September 5, 2026 (Sprint 56) | ❌ 6 months gap |
| Days Remaining | 83 days | 261 days | ❌ Misaligned |
| Current Phase | P0 → Pilot (Dec 24) | Sprint 25 of 56 | ⚠️ Partial |
| Pilot Timeline | Dec 24 - Feb 18 (8 weeks) | Sprint 52-56 (Nov 2026) | ❌ 10 months gap |
Gantt Chart: Rollout-Master Timeline
Project Span: August 27, 2025 → March 11, 2026 (196 days)
Gantt Chart: V2 Master Plan Timeline
Project Span: December 16, 2025 → September 5, 2026 (261 days)
Critical Conflict Visualization
Issue: Two different launch dates exist
Analysis:
- Rollout-Master: Launch on March 11, 2026 (83 days away)
- V2 E010 text mentions March 11, 2026 launch
- V2 Sprint roadmap extends to September 5, 2026 (261 days)
- Gap: 6 months between stated launch (Mar 11) and V2 completion (Sep 5)
Pilot Phase Comparison
Issue: Pilot scheduled at different times in two plans
Analysis:
- Rollout-Master Pilot: Dec 24, 2025 - Feb 18, 2026 (8 weeks)
- V2 E010 Pilot: Sprint 52-56 (Nov 6, 2026 - Sep 5, 2026)
- Gap: V2 schedules Pilot 10 months after rollout-master start
Recommended Unified Timeline
Option A: Compress V2 to March 11 Launch
Key Changes:
- E001, E002, E010 delivered by March 11 (critical path)
- E003-E009 delivered post-launch as monthly releases
- Pilot aligned with Sprint 25-28 (Dec 16 - Feb 7)
- September 2026 becomes "Platform 2.0" milestone (full autonomy)
Sprint-to-Phase Mapping
Weeks 1-4: P0 + Pilot Wave 1 (Dec 18 - Jan 21)
Weeks 5-9: Pilot Wave 2 (Jan 22 - Feb 18)
Weeks 10-12: GTM Launch (Feb 19 - Mar 11)
Epic Delivery Timeline
Pre-Launch Epics (Critical Path)
Post-Launch Epics (Incremental Delivery)
Resource Allocation Timeline
Critical Path Summary
Path to March 11 Launch (83 Days)
Week 1 (Dec 18-24): P0 Critical Path
- Must-complete: Authentication, license management, core stability
- V2 Sprint 25 start (E001 autonomy begins)
- Gate: Pilot-ready platform
Week 2-5 (Dec 25 - Jan 21): Pilot Wave 1
- 5 pilot customers onboarded
- V2 Sprint 25-26 (E001 complete by Jan 10)
- V2 Sprint 27 start (E002 Toon UI begins Jan 13)
- Gate: >60 NPS from first cohort
Week 6-9 (Jan 22 - Feb 18): Pilot Wave 2
- 5 additional pilot customers
- V2 Sprint 28-29 (E002 Toon UI in progress)
- Gate: 10+ pilot customers, >40% conversion commitment
Week 10-11 (Feb 19 - Mar 4): Final Polish
- Pilot analysis & iteration
- GTM campaign preparation
- V2 Sprint 30 (E002 complete, E010 launch prep)
- Gate: Documentation complete, marketing ready
Week 12 (Mar 5-11): Launch Week
- Soft launch → Public launch
- V2 E010 execution
- Gate: Zero critical vulnerabilities, 99.9% uptime
Decision Matrix
Option A: Rollout-Master Authoritative (RECOMMENDED)
Timeline: March 11, 2026 launch (83 days)
Changes Required:
- V2 compressed to Sprint 25-30 (pre-launch)
- E001, E002, E010 critical path
- E003-E009 delivered post-launch
Pros:
- Meets market window (March 11)
- Aligns with stakeholder expectations
- Pilot timeline intact
Cons:
- V2 scope reduced at launch
- Advanced features deferred
Option B: V2 Authoritative
Timeline: September 5, 2026 launch (261 days)
Changes Required:
- Rollout-master extended 6 months
- Pilot delayed to November 2026
- Stakeholders informed of delay
Pros:
- Full V2 scope delivered at launch
- All 10 epics complete
Cons:
- 6-month market delay
- Misses March window
- Pilot customers waiting 10 months
Option C: Hybrid Approach
Timeline: March 11 soft launch, September full launch
Implementation:
- March 11: Core features (E001, E002, E010)
- Monthly releases (E003-E009)
- September 5: Platform 2.0 (full autonomy)
Pros:
- Meets March market window
- Full V2 scope delivered incrementally
- Continuous value delivery
Cons:
- Two launch events to coordinate
- Ongoing development post-launch
Recommendations
URGENT (By Dec 20)
- Stakeholder Decision: Choose Option A, B, or C
- Update V2 E010: Move Pilot to Sprint 25-29
- Communicate Timeline: Unified message to team
HIGH PRIORITY (By Dec 24)
- Create Unified Gantt: Export to project management tool
- Reconcile Tasks: Map V2's 17,546 to rollout-master's 1,629
- Compress V2: Identify E001-E002 critical path
MEDIUM PRIORITY (By Jan 7)
- Align Sprints: Match V2 sprints to Pilot waves
- Define MVP: Document launch scope vs. post-launch
- Update Docs: Deprecate conflicting plans
Document Status: DRAFT Requires: Stakeholder decision on Option A/B/C Next Update: Post-decision (by Dec 20) Owner: Hal Casteel, Founder/CEO/CTO
CRITICAL: This unified timeline cannot be finalized until stakeholder decision is made on which plan (rollout-master vs V2) is authoritative for the March 11, 2026 public launch.